Following consideration, the Committee unanimously resolved to: (1) Note the progress and anticipated spend at the end of the current year 2022-23 as shown in Appendix 1 to the report. (2) Note the additional emergency works raised and carried out in the 2022-23 planned maintenance programme. (3) Approve the 2023-24 planned maintenance programme at an estimated cost of £539,000 as set out in Appendix 2 to the report. (4) Subject to the Council’s financial and contract requirements , to delegate authority to the Head of Property and Regeneration to make changes within the 2023-24 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000 . (5) To agree to transfer the unspent budgets back to the Planned Maintenance Reserve at the end of the financial year.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report provides an update on the current financial year’s approved 2022-23 planned maintenance programme and requests approval for the planned maintenance programme for the next financial year 2023-24.
Recommendation (s) The Committee is asked to:
(1) To note the progress and anticipated spend at the end of the current year 2022-23 as shown in Appendix 1.
(2) To note the additional emergency works raised and carried out in the 2022- 23 planned maintenance programme.
(3) To approve the 2023-24 planned maintenance programme at an estimated cost of £539,000 as set out in Appendix 2.
(4) Subject to the Council’s financial and contract requirements, to delegate authority to the Head of Property and Regeneration to make changes within the 2023-24 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000.
(5) To agree to transfer the unspent budgets back to the Planned Maintenance Reserve at the end of the financial year.
1 Reason for Recommendation Strategy and Resources Committee 28 March 2023 1.1 Ensuring assets are protected and maintained is essential in meeting the Council’s health & safety obligations and providing fit for purpose working environments.
Background
2.1At its meeting on 29 March 2022, this committee agreed to fund the planned maintenance programme for the current year 2022-23 in the sum of £498,000.
2.2This figure is funded from the £210,000 budgeted each year to fund planned maintenance, with the remainder of £186,000 taken from the Property Maintenance Reserve and £102,000 from a Surrey County Council grant to reduce CO2 emissions in council buildings.
3 2022-23 Update
3.1During the current financial year, the Council has benefited from an earlier Surrey County Council (SCC) policy to reallocate – back to borough councils – SCC’s share of additional council tax that arises from changes to empty homes policies between 2019 and 2024. This is intended to incentivise councils to adopt policies to reduce the number of empty properties in Surrey.
3.2The SCC funding can be used to fund new or extend existing, initiatives and projects that directly support a SCC initiative or specific project.
3.3The Council’s Climate Change Action Plan is a supported SCC initiative as it aims to reduce CO2 emissions in council owned buildings. This has been achieved by the replacement of traditional lighting with energy efficient longer lasting LED lighting to the following operational buildings:
3.3.1 Longmead Depot
3.3.2 Gibraltar Rec Pavilion
3.3.3 Auriol Pavilion
3.3.4 Court Rec pavilion
3.3.5 Ewell Court House
3.3.6 Alexandra Rec Pavilion
3.3.7 Harrier Centre
3.4The works have progressed well and due to be finished by the end of March 2023 when the final property, Ewell Court House, is completed.
3.5Rosebery Park Lodge – replacement condensing boiler, radiators and alterations to the kitchen were completed within budget at £13,000. Strategy and Resources Committee 28 March 2023 3.6 The Town Hall replacement of the Building Management System (BMS) controls were put on hold (unless the controllers fail) pending the potential Town Hall relocation to 70 East Street.
3.7Court Recreation Ground, Horton Country Park and Poole Road Rec have had various drainage pipe sections relined, CCTV surveys carried out and sections of pipework renewed. This was to ensure old drainage runs do not get blocked and continue to run effectively. There is an anticipated spend of £30,000 out of a budget of £40,000.
3.8Gibraltar Pavilion has benefitted from external decorations which were completed underbudget at £10,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.