INTERNAL AUDIT PROGRESS REPORT Gedling Borough Council December 2021 1 INTERNAL AUDIT PROGRESS REPORT | GEDLING BOROUGH COUNCIL
CONTENTS
SUMMARY OF 2021/2022 WORK ............................................................................... 2 REVIEW OF 2021/2022 WORK ................................................................................. 3 SECTOR UPDATE ................................................................................................ 8 KEY PERFORMANCE INDICATORS ............................................................................. 11 APPENDIX I - DEFINITIONS .................................................................................... 12
1 2 INTERNAL AUDIT PROGRESS REPORT | GEDLING BOROUGH COUNCIL
SUMMARY OF DECEMBER 2021 WORK
INTERNAL AUDIT This report is intended to inform the Audit Committee of progress made against the 2021/22 internal audit plan. It summarises the work we have done, together with our assessment of the systems reviewed and the recommendations we have raised. Our work complies with Public Sector Internal Audit Standards. As part of our audit approach, we have agreed terms of reference for each piece of work with the risk owner, identifying the headline and sub-risks, which have been covered as part of the assignment. This approach is designed to enable us to give assurance on the risk management and internal control processes in place to mitigate the risks identified.
INTERNAL AUDIT METHODOLOGY
Our methodology is based on four assurance levels in respect of our overall conclusion as to the design and operational effectiveness of controls within the system reviewed. The assurance levels are set out in Appendix 1 of this report, and are based on us giving either "substantial", "moderate", "limited" or "no". The four assurance levels are designed to ensure that the opinion given does not gravitate to a "satisfactory" or middle band grading. Under any system we are required to make a judgement when making our overall assessment.
2021/2022 INTERNAL AUDIT PLAN Four audits have been completed and we are pleased to present the following reports to this Audit Committee: • Taxi Licensing • Asset Management Plan • Homelessness and Temporary Accommodation • Regeneration - Employment and Skills The following audit has been completed and a draft report produced which we hope to present at the next Audit Committee: • IT Architecture. Fieldwork is due to commence this month on the following audit which we hope to present at the next Audit Committee: • Environmental Health Services and Enforcement.
2 3 INTERNAL AUDIT PROGRESS REPORT | GEDLING BOROUGH COUNCIL
REVIEW OF DECEMBER 2021 WORK
AUDIT AUDIT PLANNING FIELD REPORTING DESIGN EFFECTIVENESS COMMITTEE WORK
September Housing Benefits ✓ ✓ ✓ 2021
Risk Management September ✓ ✓ ✓ N/A N/A (Advisory) 2021
Taxi and PHV December ✓ ✓ ✓ Licensing (20/21) 2021
December Asset Management ✓ ✓ ✓ 2021
Regeneration December (employment and 2021 ✓ ✓ ✓ skills)
Homelessness & December Temporary ✓ ✓ ✓ 2021 Accommodation
IT Architecture March 2022 ✓ ✓ ✓
Environmental Health Services & March 2022 ✓ Enforcement
Main Financial March 2022 ✓ Systems
Procurement & Contract March 2022 ✓ Management
Sustainable March 2022 ✓ Environment
3 4 INTERNAL AUDIT PROGRESS REPORT | GEDLING BOROUGH COUNCIL
TAXI LICENSING (20/21)
Design Opinion Moderate Design Effectiveness Moderate
Recommendations 0 2 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2. GBC- Progress Report December 2021 FINALReport | 729 KB | DownloadRead as text |
PDF |
3. GBC: Taxi Licensing: Final Audit ReportReport | 451 KB | Download |
PDF |
4. GBC Asset Management Report FINALReport | 528 KB | Download |
PDF |
5. GBC Homelessness Audit Report FINALReport | 659 KB | Download |
PDF |
6. GBC Employment & Skills Final ReportReport | 459 KB | Download |
PDF |
Internal Audit Progress Report 2021/22Report | 146 KB | Download |
Follow Audit Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 20 Oct 2026 | BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... | Noted | Open |
| 20 Oct 2026 | Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... | Noted | Open |
| 20 Oct 2026 | Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... | Noted | Open |
| 20 Oct 2026 | Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.