CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gedling Borough Council
Audit Committee, Tuesday 17 September 2024 at 6.30pm

Internal Audit Progress Report.

Noted Finance 2 papers

Audit Committee noted this item on Tuesday 17 September 2024. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

RESOLVED to: Note the progress of the delivery against the 2024/25 Internal Audit Plan, including the Executive Summary for the following audit reports: 1) Housing Benefits and Environment; and 2) Carbon Management Strategy.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Audit Committee

INTERNAL AUDIT PROGRESS REPORT Gedling Borough Council 2024/2025 1 INTERNAL AUDIT PROGRESS REPORT

CONTENTS

SUMMARY OF 2024/25 WORK ................................................................................. 2 REVIEW OF 2024/25 WORK .................................................................................... 3 HOUSING BENEFITS ............................................................................................. 4 ENVIRONMENT - CARBON MANAGEMENT STRATEGY........................................................ 8 SECTOR UPDATE ............................................................................................... 13 KEY PERFORMANCE INDICATORS ............................................................................. 16 APPENDIX 1 ..................................................................................................... 17

1 2 INTERNAL AUDIT PROGRESS REPORT

SUMMARY OF 2024/2025 WORK

INTERNAL AUDIT This report is intended to inform the Audit Committee of progress made against the 2024/2025 internal audit plan. It summarises the work we have done, together with our assessment of the systems reviewed and the recommendations we have raised. Our work complies with Public Sector Internal Audit Standards. As part of our audit approach, we have agreed terms of reference for each piece of work with the risk owner, identifying the headline and sub-risks, which have been covered as part of the assignment. This approach is designed to enable us to give assurance on the risk management and internal control processes in place to mitigate the risks identified.

INTERNAL AUDIT METHODOLOGY Our methodology is based on four assurance levels in respect of our overall conclusion as to the design and operational effectiveness of controls within the system reviewed. The assurance levels are set out in Appendix 1 of this report and are based on us giving either ‘substantial’, ‘moderate’, ‘limited’ or ‘no’. The four assurance levels are designed to ensure that the opinion given does not gravitate to a ‘satisfactory’ or middle band grading. Under any system we are required to make a judgement when making our overall assessment.

2024/2025 INTERNAL AUDIT PLAN We are now making good progress in the delivery of the 2024/2025 audit plan. We are pleased to present the following reports to this Audit Committee meeting:  Housing Benefits  Carbon Management Strategy. The following audits are at reporting stage but have not yet been finalised:  Cemeteries and Pet Cremation Services. Planning is underway in respect of the following audits:  Equality/Equity, Diversity and Inclusion (EDI)  IT Disaster Recovery Plan  Fleet Management. We anticipate presenting these reports at future Audit Committee meetings.

CHANGES TO THE 2024/2025 INTERNAL AUDIT PLAN There have been no changes to the 2024/25 Internal Audit Plan.

2 3 INTERNAL AUDIT PROGRESS REPORT

REVIEW OF 2024/2025 WORK

AUDIT EXEC LEAD AUDIT PLANNING FIELD REPORTING DESIGN EFFECTIVENESS COMMITTEE WORK

Housing Benefits Tina Adams, September Chief Financial 2024 S S and S151 Officer

Carbon Fran Whyley, September Management Deputy CEO 2024 S M Strategy

Cemeteries and Tina Adams, December Pet Crematorium Chief Financial 2024 Services and S151 Officer

Equality/Equity, Fran Whyley, December Diversity and Deputy CEO 2024 Inclusion (EDI)

IT Disaster Tina Adams, December Recovery Plan Chief Financial 2024 and S151 Officer

Fleet Tina Adams, December Management Chief Financial 2024 and S151 Officer

Temporary Tina Adams, December Accommodation Chief Financial 2024 and S151 Officer

Budget Tina Adams, March 2025 Management Chief Financial and S151 Officer

Procurement and Fran Whyley, March 2025 Contract Deputy CEO Management

3 4 INTERNAL AUDIT PROGRESS REPORT

HOUSING BENEFITS

CRR REFERENCE: 2. FAILURE TO MAINTAIN FINANCIAL INTEGRITY

Design Opinion S Substantial Design Effectiveness S Substantial

Recommendations 0 0 3

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1b. BDO: GBC: IA Progress Report: September 24Report 743 KB DownloadRead as text
PDF
Internal Audit Progress Report.Report 246 KB Download

At this meeting

Whole meeting

Who was there

8 of 15 attended
KR
Councillor Kyle Robinson-PayneChair, present
SB
Councillor Sandra BarnesVice-Chair, present
JC
Councillor Jim CreamerCommittee Member, present
HG
Councillor Helen GreensmithCommittee Member, present
PH
Councillor Paul HughesCommittee Member, present
AH
Councillor Alison HuntCommittee Member, present
RS
Councillor Ruth StrongCommittee Member, present
JC
Jonathan CaustonCo-Optee, present
TA
Tina AdamsOfficer, in attendance
BH
Ben HopewellOfficer, in attendance
CG
Cayte GoodallOfficer, expected
MH
Mike HillOfficer, expected

All 15 on the meeting page

On this subject at Gedling

Search all
  1. Internal Audit Progress Report.This decision
  2. BDO Internal Audit Progress ReportNoted
  3. Internal Audit Progress ReportNoted
  4. Internal Audit Annual ReportNoted
  5. Internal Audit Annual Plan - 2026/27Approved
  6. Internal Audit Progress Report 2025/2026Noted

More from Gedling Audit Committee

All decisions
MeetingDecisionOutcome
20 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
20 Oct 2026 BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... Noted Open
20 Oct 2026 Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... Noted Open
20 Oct 2026 Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... Noted Open
20 Oct 2026 Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies