Resolved – 1. That the Royal Borough’s Strategic Risk Register agreed by the Greenwich Management Team be noted 2. That it be noted that the will be presented to Cabinet and Full Council.
Audit and Risk Management Panel agreed this item on Wednesday 3 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – 1. That the Royal Borough’s Strategic Risk Register agreed by the Greenwich Management Team be noted 2. That it be noted that the will be presented to Cabinet and Full Council.
AUDIT AND RISK DATE: ITEM No. MANAGEMENT PANEL 3rd September 2025 8 REPORT TITLE: WARDS Royal Borough of Greenwich All Strategic Risk Register CHIEF OFFICER CABINET MEMBER Director of Resources Finance, Resources and Social Value
DECISION AND CLASSIFICATION IS THIS THE FINAL Non-Key DECISION ON THE Non-exempt Appendix RECOMMENDATIONS IN Call in - Non exempt THIS REPORT TO BE MADE AT THIS MEETING Yes
1. Decision Required
This report makes the following recommendations to the Audit & Risk Management Panel:
1.1To consider and comment on the Royal Borough’s Strategic Risk Register agreed by the Greenwich Management Team (GMT) (Appendices A, B and C).
1.2To note that the Strategic Risk Register will be presented to Cabinet and Full Council.
2. Links to Our Greenwich missions
2.1This report relates to the Council’s agreed missions as follows:
• Our Council is an adaptive organisation, enabling it to navigate the increasing number of challenges it faces while remaining financially sustainable. • Our Council works in the most efficient and effective ways possible.
2.2The Strategic Risk Register is part of the Council’s risk management framework and associated control environment. It supports and helps underpin the overarching ambition to develop the Borough, using resources effectively and efficiently. ITEM NO: 8 PAGE NO: 1 3. Purpose of Report and Executive Summary
3.1The Strategic Risk Register is presented in line with Part 3 of the Constitution, which details the Terms of Reference of the ARM Panel including the following responsibilities:
Governance, risk and control • To monitor the effective development and operation of risk management in the Council including progress in addressing risk- related issues reported to the Panel.
Accountability arrangements • To report to those charged with governance on the Panel’s findings, conclusions and recommendations concerning the adequacy and effectiveness of the governance, risk management and internal control framework, financial reporting arrangements and internal and external audit functions.
3.2The Royal Borough’s Strategic Risk Register was last presented to the Panel at the meeting held on 25th February 2025.
3.3This report presents the updated Strategic Risk Register
4. Introduction and Background
4.1The updated Strategic Risk Register (Appendices A, B and C) contains the key risks that threaten the Council’s plans and strategies, and sets out the controls and mitigating actions in place to manage the risks.
4.2The Strategic Risk Register is owned by the Greenwich Management Team (GMT).
4.3In line with the Council’s organisational structure as detailed in Part 7 of the Constitution, each risk in the register is assigned to one designated Director who owns and retains responsibility for the risk.
4.4As part of the usual Risk Register review process, GMT scrutinises risks in the Strategic Risk Register to ensure they continue to represent the key strategic risks facing the Council. They also consider the reasonableness of individual risk assessments; the effectiveness of identified internal controls; and progress made with implementation and completion of identified
ITEM NO: 8 PAGE NO: 2 mitigating actions. Consideration is also given to any new and/or escalated risks for inclusion in the Strategic Risk Register, which are highlighted as “NEW” in the risk title.
4.5For this review and reporting cycle, however, there is no new and/or escalated risk.
4.6The Strategic Risk Register presents risks captured at a point in time.
4.7The identification, management, review and reporting of risks to various Committees and within decision reports as part of the Council’s decision making process remain a continuous process.
4.8In addition to the detailed Strategic Risk Register (Appendix A), the following risk reports, which provide helpful summaries and visuals were also considered and agreed by GMT:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
8.1 Appendix AAppendix | 938 KB | Download |
PDF |
8.2 Appendix BAppendix | 595 KB | Download |
PDF |
8.3 Appendix CAppendix | 272 KB | Download |
PDF |
Strategic Risk RegisterReport | 110 KB | DownloadRead as text |
Follow Audit and Risk Management Panel at Greenwich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | Declarations of InterestResolved - That the list of Councillors’ memberships as Council appointed representatives on outside bodies, joint co... | Noted | Open |
| 24 Jun 2026 | Audit & Risk Management Panel Terms of Reference and Draft Work Programme 2026/27Resolved – 1. That the Terms of Reference for the Audit & Risk Management Panel at Appendix A of the report be noted ... | Noted | Open |
| 24 Jun 2026 | Action LogResolved – That the current status of actions, as set out in Appendix 1 of the report, be noted. | Noted | Open |
| 24 Jun 2026 | Internal Audit Plan 2026/27Resolved – That the Internal Audit Plan 2026/27 be noted and approved | Noted | Open |
| 24 Jun 2026 | Head of Audit Annual Report 2025/26Resolved – 1. That the Head of Audit annual report for the year 2025/26 be noted 2. That the Anti-Fraud Service perfo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.