Royal Borough of Greenwich
Cabinet, Wednesday 19 November 2025 at 2.00pm

Strategic Risk Register

Noted Executive 4 papers

AI summaryRoyal Borough of Greenwich Cabinet noted the council's updated Strategic Risk Register, which had been reviewed by the Audit & Risk Management Panel in September and will go to Full Council. No direct financial implications were identified.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the updated register on 19 November 2025
MoneyNo direct financial implicationsReport states no direct financial implications arise
What happens nextFull Council to note the registerRegister to be presented to Full Council for noting
Who it affectsCouncil risk management and governanceCovers strategic risks to the council's plans

What was decided

Cabinet noted the updated Strategic Risk Register, comprising Appendices A, B and C. Report 10.1

Cabinet noted the register was presented to the Audit & Risk Management Panel on 3rd September 2025. Report P7, P12

Cabinet noted the register will be presented to Full Council for noting. Report P8

Why

The Council is legally required to have a sound system of internal control, including effective risk management arrangements. Report 7.1, P5

The Audit and Risk Management Panel is responsible under the Constitution for providing independent assurance of the risk management framework and control environment. Report P5

The report presents a register of the key risks threatening the council's corporate plans and strategies, along with the controls in place and actions to manage them. Report P9

What happens next

The Strategic Risk Register will be presented to Full Council for noting. Report P8

The register was previously considered by the Audit & Risk Management Panel on 3rd September 2025. Report P7, P12

Implications

  • Legal: The Council must ensure a sound system of internal control and effective risk management arrangements. Report 7.1
  • Risk: The report sets out the council's key strategic risks, controls in place and actions to manage them. Report P9
  • Financial: There are no direct financial implications arising from this report. Report P9
  • Equalities: The decision has remote or low relevance to the Equality Act, with no apparent equality impact on end users. Report P9

Who and where

  • Audit & Risk Management Panel Report P5, P7
  • Full Council Report P8
  • Council officers responsible for risk management Report P9, P13, P15

Timeline

  • 3rd September 2025: Strategic Risk Register presented to the Audit & Risk Management Panel for consideration. Report P7, P12
  • 19 November 2025: Cabinet noted the updated Strategic Risk Register.
  • To be confirmed: Strategic Risk Register to be presented to Full Council for noting. Report P8

Plain English for the jargon

  • Strategic Risk Register: A document listing the key risks threatening the council's corporate plans and strategies, including the controls in place and actions to manage those risks.
  • Audit & Risk Management Panel: A council committee responsible under the Constitution for providing independent assurance of the risk management framework and the associated control environment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

Noted the Council’s updated (Appendices A, B and C of the report). Noted that the updated was presented to the Audit & Risk Management Panel for consideration on 3rd September 2025. Noted that the will be presented to Full Council for noting.
Word for word from the decision Greenwich published for this meeting. Source: committees.royalgreenwich.gov.uk

Follow this further

Built from Greenwich's papers

What the report saysPro

Report to Cabinet

CABINET DATE ITEM NO 19 November 2025 10 TITLE WARD (S) Royal Borough of Greenwich All Strategic Risk Register CHIEF OFFICER CABINET MEMBER Director of Resources Finance, Resources and Social Value DECISION CLASSIFICATION IS THE FINAL DECISION ON THE RECOMMENDATIONS Non-Key IN THIS REPORT TO BE MADE AT THIS MEETING? Non-exempt Appendix Yes

1. Decision required

This report makes the following recommendations to Cabinet:

1.1To note the Council’s updated Strategic Risk Register (Appendices A, B and C).

1.2To note that the updated Strategic Risk Register was presented to the Audit & Risk Management Panel for consideration on 3rd September 2025.

1.3To note that the Strategic Risk Register will be presented to Full Council for noting.

2. Links to Our Greenwich missions

2.1This report relates to the Council’s agreed missions as follows:

• Our Council is an adaptive organisation, enabling it to navigate the increasing number of challenges it faces while remaining financially sustainable • Our Council works in the most efficient and effective ways possible

2.2The Strategic Risk Register is part of the Council’s governance, risk management and internal control framework. It supports and helps underpin the overarching ambition to develop the Borough, using resources effectively and efficiently.

ITEM NO: 10 PAGE NO: 1 3. Purpose of Report and Executive Summary

3.1On 3rd September 2025, the Council’s updated Strategic Risk Register was presented to the Audit & Risk Management Panel in line with Part 3 of the Constitution, which includes the responsibility of the Audit & Risk Management Panel as:

Governance, risk and control • To monitor the effective development and operation of risk management in the Council including progress in addressing risk- related issues reported to the Panel.

Accountability arrangements • To report to those charged with governance on the Panel’s findings, conclusions and recommendations concerning the adequacy and effectiveness of the governance, risk management and internal control framework, financial reporting arrangements and internal and external audit functions.

3.2The purpose of this report is for Cabinet to note the updated Strategic Risk Register, which has been considered by the Audit & Risk Management Panel; and refer it to Full Council.

4. Introduction and Background

4.1The updated Strategic Risk Register (Appendices A, B and C) contains the key risks that threaten the Council’s plans and strategies, and sets out the controls and mitigating actions in place to manage the risks.

4.2The Strategic Risk Register is owned by the Greenwich Management Team (GMT).

4.3In line with the Council’s organisational structure as detailed in Part 7 of the Constitution, each risk in the register is assigned to one designated Director who owns and retains responsibility for the risk.

4.4As part of the usual Risk Register review process, GMT scrutinises risks in the Strategic Risk Register to ensure they continue to represent the key strategic risks facing the Council. They also consider the reasonableness of individual risk assessments; the effectiveness of identified internal controls; and progress made with implementation and completion of identified mitigating actions. Consideration is also given to any new and/or escalated

ITEM NO: 10 PAGE NO: 2 risks for inclusion in the Strategic Risk Register, which are highlighted as “NEW” in the risk title.

4.5For this review and reporting cycle, however, there is no new and/or escalated risk.

4.6The Strategic Risk Register presents risks captured at a point in time.

4.7The identification, management, review and reporting of risks to various Committees and within decision reports as part of the Council’s decision making process remain a continuous process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 1.8 MB Download
PDF
Appendix BAppendix B 662 KB Download
PDF
Appendix CAppendix C 399 KB Download
PDF
Strategic Risk RegisterReport 76 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 20 attended
AO
Councillor Anthony OkerekeChair, present
AL
Councillor Averil LekauCommittee Member, apologies
SB
Councillor Sandra BauerCommittee Member, apologies
DH
Councillor Denise HylandCommittee Member, apologies
AK
Councillor Adel KhairehCommittee Member, apologies
ML
Councillor Mariam LolavarCommittee Member, present
MR
Councillor Majid RahmanCommittee Member, present
PS
Councillor Pat SlatteryCommittee Member, present
JS
Councillor Jackie SmithCommittee Member, present
RT
Councillor Rachel Taggart-RyanCommittee Member, present
CO
Councillor Calum O'Byrne MulliganCommittee Member, present
DO
Director of ResourcesOfficer, in attendance

All 20 on the meeting page

On this subject at Greenwich

Search all
  1. Strategic Risk RegisterThis decision
  2. Royal Borough of Greenwich Strategic Risk RegisterNoted
  3. Royal Borough of Greenwich Strategic Risk RegisterNoted
  4. Strategic Risk RegisterNoted
  5. Strategic Risk RegisterAgreed
  6. Royal Borough of Greenwich Strategic Risk RegisterNoted

More from Greenwich Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Royal Greenwich Safeguarding Adults Board Annual Report 2025-26Noted the 2025/26 Royal Greenwich Safeguarding Adults Board Annual Report Noted Open
23 Sep 2026 Private Housing Enforcement Policy 2026 to 2029Agreed to adopt the amended Private Sector Housing Enforcement Policy in Appendix 1 including the revised schedule of... Agreed Open
23 Sep 2026 Approval to publish the Local Flood Risk Management StrategyApproved the publication of the completed Greenwich’s Local Flood Risk Management Strategy (LFRMS). Approved Open
23 Sep 2026 2025/26 OutturnNoted the Council’s revenue outturn position for 2025/26 as at the end of March 2026 Noted Open
23 Sep 2026 Draft Statement of Accounts 2025/26Considered the authority’s draft Statement of Accounts for the year ended 31 March 2026 (including the Pension Fund A... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies