Resolved
The Executive
Executive Committee Report Ward(s) affected: Friary & St Nicolas Report of Strategic Services Director Author: Elizabeth Fleming Tel: 01483 4528 Email: [email protected] Lead Councillor responsible: Jan Harwood Email: [email protected] Date: 7 January 2020
Walnut Bridge – application for additional funding Executive Summary
The replacement of Walnut Bridge has had a long but consistent history – initially being identified in 2012 in the Guildford Interim Town Centre Framework and again in 2014 when it was identified as a priority in the Guildford Town and Approaches Movement Study (GTAMS). This proposal was endorsed by the Executive at the time. The project was subsequently awarded LEP funding as part of the “Unlocking Guildford, Guildford Town Centre Transport Package” in 2014. It formed one of a number of projects and interventions which together would help alleviate congestion in the Town Centre.
In July 2016 the Executive formally approved the project to replace Walnut Bridge. The replacement would provide improve access to the town centre from the station and was in anticipation of the significant developments expected in the immediate area. There was concern that the existing Bridge was too narrow to accommodate the increasing flow of pedestrians and cyclists. The improvements brought by a new Bridge were many; it would be wider, facilitate two-way cycle flow and be fully accessible, it would also lie on a more obvious alignment to encourage use by new and infrequent users as well as local people familiar to the area. Additionally, it would be seen as a catalyst for regeneration in the Bedford Plaza and Bedford Wharf area thereby becoming a critical access corridor from the Station through to the high street. Finally, it would encourage more sustainable travel and reduce the need for cyclists to have to use the Gyratory.
It has become apparent that there is a funding gap and a virement of £450k is required to get this project completed.
In addition to the above, the reincorporation of the Bedford Plaza Public Realm works into the Bridge project has been explored primarily because the lighting design of Bedford Plaza including the Bridge is included in these works. Planning consent for the Bridge requires that the public realm works are completed within 6 months of the completion of the Bridge. This would mean that it is possible the Bridge could not be opened after completion until public realm works were completed unless a temporary lighting system was installed. There is therefore a case to be made for these to be undertaken with the Bridge works. This could allow for economies of scale, savings in mobilisation costs etc. and could provide some additional funding from its £500,000 budget to be brought into the Bridge project.
The Executive is therefore also being asked to approve bringing the Bedford Plaza Public Realm works and budget back within the Walnut Bridge Project and to agree to transfer £350,000 from the provisional budget to the approved budget to allow this work to progress.
Recommendation to Executive That a virement of £450,000 is transferred from the capital contingency fund for the Walnut Bridge Project That the Bedford Plaza Public realm works are incorporated within the Walnut Bridge Project. That £350,000 is transferred from the provisional to approved capital budget to fund the public realm work.
Reason(s) for Recommendation:
It has become apparent that there is a funding gap and a virement of £450k is required to get this project completed.
The assimilation of the Bedford Plaza Public Realm works into the Bridge project is twofold: To combine the lighting design for both schemes within the main Bridge Contract and To leverage some of the associated budget for use on the Bridge project through economies of scale and mobilisation costs etc.
The budget for the public realm works needs to be transferred to the approved budget to enable the work to proceed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Walnut Bridge: application for additional fundingReport | 247 KB | DownloadRead as text |
Follow Executive at Guildford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... | Decided | Open |
| 17 Sep 2026 | Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... | Noted | Open |
| 17 Sep 2026 | Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... | Approved | Open |
| 17 Sep 2026 | Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... | Approved | Open |
| 17 Sep 2026 | GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.