Resolved
The Executive
Executive decided this item on Tuesday 7 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive
Weyside Urban Village (formerly The Slyfield Area Regeneration Programme is a major 41-hectare brownfield regeneration scheme that Guildford Borough Council (the Council) anticipates could deliver 1,500 homes across a range of tenures as well as 2,000 square metres of community space and 6,500 square metres of employment space. As such, Government has designated it as one of its national Housing Zones.
The Council has been working for over 15 years to de-risk the infrastructure delivery and site assembly process. Over 44 per cent of the site is currently in Council ownership, and 100 per cent will be achieved on completion of land transfers with Thames Water. The conditional contract with Thames Water was signed on 25 April 2019.
Housing is of great significance to the Borough and forms a major theme to the Adopted Local Plan. There is an ongoing shortage of affordable housing, particularly for first time buyers which in turn contributes to a skill shortage in the Borough.
Through this report, the Council is asked to approve a capital budget of £359.504 million to enable the infrastructure phase of Weyside Urban Village Project (formerly known as the Slyfield Area Regeneration Programme (SARP)) development to be carried out. The Council has been awarded a £52.3 million grant from the Housing Infrastructure Fund (HIF).
An EM3 Local Enterprise Partnership (LEP) grant of £7.5 million has also been awarded.
Recommendation to Executive: That the Managing Director be authorised, in consultation with the Leader of the Council, to sign and complete the Grant Agreement with Homes England to implement the infrastructure works and draw down the grant expenditure. Recommendation to Council:
The Executive is asked to recommend to the Council
(1) That an additional capital supplementary estimate of £274.057 million be approved to allow a total capital budget of £359.504 million to enable the Council to deliver the infrastructure phase of this scheme.
(2) That £5.781 million of the additional capital budget be placed on the approved capital programme to progress the allotment relocation and funding of the Thames Water agreement costs during 2019-20.
(3) That the Council acts as Infrastructure Developer until completion of the Thames Water Infrastructure in 2026.
Reasons for Recommendation: The reasons for recommendation cover financial, economic and social benefits.
The budget will enable the Council to deliver the infrastructure for the development ensuring deliverability and control.
The land value will be increased by the infrastructure phase being delivered upfront and ahead of Land Parcel Sales.
The project will also deliver:
1500 new homes including 600 Affordable Homes 2000 square metres of community space 6500 square metres of employment space A new relocated “fit for purpose” Thames Water Sewage Treatment Works Extensive infrastructure improvements This scheme contributes to the delivery of the adopted Local Plan This scheme contributes £233 million in economic impacts for Guildford
The project has significant infrastructure to be put in place to enable the above critical success factors to be delivered. Allocating a capital budget of £317.355 million will enable all of the infrastructure phase to be delivered and will de-risk the site in readiness for the next stage to facilitate the delivery of homes.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Weyside Urban Village DevelopmentReport | 296 KB | DownloadRead as text |
Follow Executive at Guildford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... | Decided | Open |
| 17 Sep 2026 | Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... | Noted | Open |
| 17 Sep 2026 | Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... | Approved | Open |
| 17 Sep 2026 | Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... | Approved | Open |
| 17 Sep 2026 | GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.