Resolved
(1) That the relocation of the Council depot to accommodate administrative and operational functions, as described in the report submitted to the Executive, be approved. (2) That the sum of £2.48 million be transferred from the Provisional to the Approved Capital Programme to enable the detailed design of the new Guildford Borough Council depot to be undertaken. Reason The budget will enable the detailed design of the new depot site in order to deliver construction, thereby releasing the current depot site as part of the Weyside Urban Village Development. Alternative options considered and rejected by the Executive To cease the project, retaining the Council depot on its existing site. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted None. (1) That the relocation of the Council depot to accommodate administrative and operational functions, as described in the report submitted to the Executive, be approved. (2) That the sum of £2.48 million be transferred from the Provisional to the Approved Capital Programme to enable the detailed design of the new Guildford Borough Council depot to be undertaken. Reason The budget will enable the detailed design of the new depot site in order to deliver construction, thereby releasing the current depot site as part of the Weyside Urban Village Development.