Procurement Pipeline Report - over £200k (2025-2026)

Approved Executive 2 papers

AI summaryGuildford Borough Council Executive approves starting procurement for projects in Appendix 1 and delegates contract award authority to the Joint Strategic Director for Finance and Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor projects over £200k in Appendix 1
MoneyNo direct cost to this reportFinancial approval sought before each procurement
What happens nextProceed to market for listed procurementsAward subject to delegated authority and consultation
Who it affectsSuppliers, SMEs, VCSE sector, Waverley BCCouncil also prioritises resource across both councils

What was decided

The Executive approved the start of procurement for the projects listed in Appendix 1 to the report. Report 2.1, P6

Authority to award those contracts, after selecting a successful contractor, is delegated to the Joint Strategic Director for Finance and Resources, in consultation with the Lead Councillor for Finance. Report 1.3, P7

Why

The Council's Contract Procedure Rules require Executive permission before starting any procurement that could result in a Key Decision, meaning an estimated value over £200k or an impact on two or more wards. Report 1.1, P2, 3.1

Forward planning helps with stakeholder management, legal compliance, price management, ethical sourcing including climate, social value and modern slavery risk, and securing best value. Report 3.2, P10, P11, P12, P13, P14, P15

A single pipeline report avoids the need for multiple separate approval papers, making the process more agile. Report 3.3

What happens next

The Procurement team and the relevant Service Area will go to market for the procurements listed in Appendix 1 and then move to the award process and required approvals. Report 4.1, P20

Where a contract award is itself a Key Decision and no delegation exists, a further Executive report will be brought back for approval. Report 3.4

If annual third party supplier spend exceeds £100m including VAT, the Council may need to publish individual pipeline notices every 18 months for procurements over £2m including VAT under the Procurement Act 2023. Report 6.5

The money

  • over £200k Threshold for procurement to need Executive permission before starting Report 1.1, P2
  • £100m (inc VAT) Annual third party spend level that would trigger Procurement Act 2023 pipeline notice duties Report 6.5
  • £2m (inc VAT) Estimated value above which individual pipeline notices may need publishing every 18 months Report 6.5

Options considered

  • Chosen: Bring a consolidated procurement pipeline at intervals, as a more strategic planned approach. Saves officer and Executive time and shortens procurement timescales Report 11.1, P43
  • Rejected: Bring each individual procurement item to the Executive as a separate report. Would take more time and cost in writing individual reports Report 11.1, P44

Implications

  • Financial: No direct financial implications from this report; financial approval will be sought before each procurement begins. Report P46
  • Legal: No direct legal implications; the Procurement and Legal teams will provide project specific advice on each contract. Report P47, P48
  • Equalities: The Public Sector Equality Duty has been considered and no equality and diversity implications arise from this report; project teams will consider duties for each procurement. Report 12.3, P50, P51, P52, P53
  • Climate: No climate change or sustainability implications from this report; project teams will consider these for each procurement, and ethical factors including climate impact are part of procurement planning. Report 12.4, 12.5, P14
  • Risk: Without planned pipelines there is a heightened risk of non-compliant spend and contracts expiring before re-procurement, and reduced ability to engage the market early. Report 10.1, 10.2, P41
  • Staffing: New Contract Procedure Rules may need more Procurement team time for Executive papers and more service area input as subject experts. Report 10.1

Who and where

  • Suppliers and prospective bidders for the projects in Appendix 1 Report 7.2, P34
  • Small and medium enterprises and the voluntary, community and social enterprise sector, with procurement design to avoid perceived barriers Report 7.2, P34
  • Waverley Borough Council, as a potential collaboration partner on procurement activities Report 6.3, 6.4, 8.1, 8.2
  • Guildford Borough Council residents and wards, where procurements affect two or more wards and become Key Decisions Report 1.1, P2

Timeline

  • June 2024: New Contract Procedure Rules were introduced, changing who can approve procurement and award Report 6.1
  • 8 January 2026: Previous procurement pipeline was presented to the Executive Report 1.2
  • 29 January 2026: Executive considers and decides this updated pipeline report Report 1.2, P60

Plain English for the jargon

  • Key Decision: An Executive decision on a matter likely to result in significant expenditure or to affect two or more wards in the Borough.
  • CPRs: The Council's Contract Procedure Rules, which set the rules for procurement and contract award.
  • Procurement Act 2023: New UK legislation governing public sector procurement, including potential duties to publish pipeline notices for large contracts.
  • VCSE: Voluntary, Community and Social Enterprise organisations, which the Council aims to involve in procurement.
  • SME: Small and Medium sized Enterprises, which the Council aims to make procurement accessible to.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX119

Resolved

To approve commencement of the procurement process for the project listed in Appendix 1 to the report. 2. To delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance, and upon selection of a successful contractor, to award the contract as listed in Appendix 1. Reasons: 1. The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. 2. Planning procurement activity ensures: • effective stakeholder management • effective procurement and sourcing compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules • there is consideration on how contract price is to be managed in contract and what contract price model will be used • our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk. • how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. 3. This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 4. When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer Other options considered and rejected by the Executive: Bring each individual item to the Executive, which will incur more time and cost writing individual reports, so is not recommended. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provide that the Executive must give permission to commence any procurement activity which could result in the award being a Procurement Pipeline Report – over £200k (2025-2026)

Key Decision as the estimated value is greater than £200k or it significantly impacts two or more wards within the Borough.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 8 January 2026. The pipeline set out in Appendix 1 to this report includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence.

1.3In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and Leader of the Council and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to:

(1) Approve commencement of the procurement process for the project(s) listed in Appendix 1 to this report.

(2) Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance, and upon selection of a successful contractor, to award the contract(s) as listed in Appendix 1.

Reasons for recommendation

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing.

3.2Planning procurement activity ensures:

• effective stakeholder management

• effective procurement and sourcing Procurement Pipeline Report – over £200k (2025-2026)

• compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

• there is consideration on how contract price is to be managed in contract and what contract price model will be used

• our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.

• how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract.

3.3This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity.

3.4When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_GBC Procurement Pipeline 270126Appendix 1 116 KB Download
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 127 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
JM
Councillor Julia McShaneChair, present
VK
Councillor Vanessa KingVice-Chair, present
PB
Councillor Phil BellamyCommittee Member, present
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, apologies
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, in attendance, virtual
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Procurement Pipeline Report - over £200k (2025-2026)This decision
  2. Procurement Pipeline Report - over £200k (2025-2026)Approved
  3. Procurement Pipeline Report - over £200k (2025-2026)Approved
  4. Procurement Pipeline Report - over £200k (2025-2026)Approved
  5. Procurement Pipeline Report - over £200k (2025-2026)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open