Risk Management and Corporate Risk Registers (Q2 2025/26)

Noted Executive 3 papers

AI summaryGuildford Executive noted the Q2 2025/26 corporate risk registers and approved a new strategic risk on local government reorganisation transition instability.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSR2.1 on LGR transition added
MoneyNo direct financial implicationsIndividual risks may have financial effects
What happens nextNo further stepsQuarterly review process continues
Who it affectsCouncil risk management and LGR planningIncludes work with Waverley Borough Council

What was decided

The Executive noted the updated corporate risk registers for Q2 2025/26, covering strategic and operational risks. Report 2.2, 6.3

The Executive approved a new strategic risk, SR2.1, on local government reorganisation instability during the transition period. Report P26, 8.2

Why

To enable the Executive to ensure risks threatening corporate objectives are adequately addressed and managed in line with the Council's risk appetite and Risk Management Strategy. Report 3.1, 7.1

Audit and Risk Committee independently reviewed the risk management framework and provided assurance ahead of the Executive's consideration on 26 January 2026. Report 6.1, 2.1

What happens next

The report states there are no further steps arising directly from it, with the Risk Management group continuing to meet quarterly. Report 4.1, 9.2

Strategic and operational risks continue to be overseen by the Corporate Leadership Board, with red rated operational risks reported to the Audit and Risk Committee and the Executive. Report 9.3, 6.6

Options considered

  • Chosen: Note the report and consider comments from the Audit and Risk Committee. Aligns with the Risk Management Strategy and statutory Best Value duty on risk management. Report P48, 11.1

Implications

  • Legal: The Council must comply with the Accounts and Audit Regulations 2015, the Public Sector Internal Audit Standards, and its statutory Best Value duty to manage risk effectively.
  • Risk: Without a fit-for-purpose risk management process, the Council could be exposed to unnecessary and unacceptable risks across its functions. Report 10.1
  • Staffing: Completion and oversight of the risk registers requires resource from the Joint Leadership Team, Service Leads, the Strategy and Performance team and specialists.
  • Equalities: The Equalities Comprehensive Impact Assessment found no disproportionately adverse impact on people with a protected characteristic.
  • Climate: No direct climate change or sustainability implications, though effective risk management supports the Council's net-zero carbon by 2030 goal.
  • Financial: No direct financial implications from the report, although individual risks may have financial effects progressed through appropriate governance.

Who and where

  • Guildford Borough Council, including Strategic Directors, Assistant Directors and service risk owners Report 9.1
  • Waverley Borough Council, through joint risk management framework and quarterly review meetings Report 8.1, P40
  • The Audit and Risk Committee, which reviews the registers for independent assurance Report 6.1, 9.3

Timeline

  • Q2 2025/26: Reporting period covered by the strategic and operational risk registers at Appendices 1 and 2. Report 15.1, 15.2
  • September 2025: Last Strategic Risk Register update received by the Committee, since when substantive changes have been made. Report 6.7, P18
  • 26 January 2026: Audit and Risk Committee considered the report and any comments are set out in the Supplementary Agenda Pack. Report 2.1
  • 29 January 2026: Executive considered and approved the updated registers and new risk SR2.1. Report P1

Plain English for the jargon

  • LGR: Local Government Reorganisation, with government intentions announced towards the end of 2024.
  • MTFP: Medium-Term Financial Plan, referenced as a corporate level policy that strategic risks can impact.
  • CLB: Corporate Leadership Board, which reviews both risk registers and oversees the Risk Management group.
  • Residual score: Risk score after mitigations are taken into account, used to show whether risks are within the Council's risk appetite.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX121

Resolved

To note the report and the updated corporate risk registers. 2. To approve the new risk SR2.1 – Local Government Reorganisation – instability in the transition period as set out in the Strategic Risk Register. Reason: To enable the Executive to ensure that risks t hreatening corporate objectives are adequately addressed and managed in accordance with the Council’s risk appetite, as set out in the Council’s Risk Management Strategy. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Recommendation

That the Executive resolves:

2.1To note and consider any comments arising from the Audit and Risk Committee’s consideration of this report at its meeting on 26 January 2026, as set out in the Supplementary Agenda Pack.

2.2To note the updated corporate risk registers and make any observations on their contents.

Reason for recommendation

3.1To enable the Executive to ensure that risks threatening corporate objectives are adequately addressed and managed in accordance with the Council’s risk appetite, as set out in the Council’s Risk Management Strategy.

4 Next steps

4.1There are no further steps for this report.

5 Exemption from publication

5.1No part of this report is exempt from publication.

6 Background and Proposal

Role of the Audit & Risk Committee

6.1The purpose of the Committee is to provide independent assurance to councillors of the adequacy of the risk management framework and the internal control environment. It provides independent review of the authority’s governance, risk management and control frameworks. Risk Management and Corporate Risk Registers (Q2 2025/26)

Strategic and operational risks

6.2The Council’s risk management strategy defines corporate risks as risks ‘that reside outside the usual course of management and require a wider corporate response or awareness …’.

6.3Corporate risks are split into two categories: strategic and operational risks.

6.4Strategic risks (shown at Appendix 1) are risks that could impact the Council’s medium to long term priorities and objectives as set out in the Corporate Strategy or other corporate level policies and strategies, including the Medium- Term Financial Plan (MTFP).

6.5Operational risks are risks that are encountered in the delivery of services and which affect service objectives, as defined in service plans. Operational risks are usually managed as part of the usual course of management by services. However, where an operational risk cannot be managed within the service or if it is outside of the Council’s risk appetite, then it should be considered for inclusion on the operational risk register.

6.6Red rated operational risks shown at Appendix 2 are reported to the Audit and Risk Committee and the Executive.

Changes to the risk registers since the last report

6.7Since the Committee last received an update on Strategic Risk Register in September, the following substantive changes have been made:

Strategic Risk Register:

Substantive change to note (see the risk Ref. Risk register for full information)

SR1 Financial Updated – with additional actions added, sustainability together with an updated projected budget shortfall.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management and Corp Risk Registers: App 1: Strategic RRAppendix 317 KB Download
PDF
Risk Management and Corp Risk Registers: App 2: Operational RRAppendix 240 KB Download
PDF
Risk Management and Corporate Risk Registers (Q2 2025/26)Report 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
JM
Councillor Julia McShaneChair, present
VK
Councillor Vanessa KingVice-Chair, present
PB
Councillor Phil BellamyCommittee Member, present
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, apologies
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, in attendance, virtual
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Risk Management and Corporate Risk Registers (Q2 2025/26)This decision
  2. Risk Management and Corporate Risk Registers (Q1 2026/27)Noted
  3. Risk Management and Corporate Risk Registers (Q4 2025/26)Noted
  4. Risk Management and Corporate Risk Registers (Q2 and Q3 2025/26)Noted
  5. Risk Management and Corporate Risk Registers (Q1 2025/26)Noted
  6. Risk Management and Corporate Risk Registers (Q1 2025/26)Noted

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies