Noted Executive 5 papers

AI summaryGuildford Executive notes updated corporate risk registers, with local government reorganisation risk scored as almost certain.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedExecutive noted Q2 and Q3 2025/26 risk registers
MoneyNot stated
What happens nextNo further stepsNo further steps for this report
Who it affectsCouncil-wide risk managementStrategic and operational risks across all services

What was decided

The Executive noted the updated corporate risk registers covering Q2 and Q3 2025/26. Report 2.1

The Audit and Risk Committee considered the same report on 18 March 2026, after being adjourned on 26 January 2026. Report 1.1, 1.2

Why

To enable the Executive to ensure that risks threatening corporate objectives are adequately addressed and managed in line with the Council's risk appetite and Risk Management Strategy. Report 3.1, P4

Without a fit for purpose and consistent risk management process the Council could be exposed to unnecessary and unacceptable risks, and would not meet Best Value duties. Report 10.1, P42, P50

What happens next

There are no further steps for this report. Report 4.1, P8

Risk owners, Strategic Directors and Assistant Directors continue to review and update register entries, with the Risk Management Group meeting quarterly and the Corporate Leadership Board receiving both registers regularly. Report 9.1, 9.2, 9.3

Options considered

  • Chosen: Note the report and consider any comments or observations from the Audit and Risk Committee. The Executive noted the report. The decision record states no other options were considered. Report P45, P46

Implications

  • Legal: Effective risk management is a statutory duty under the Accounts and Audit Regulations 2015, the Best Value duty and Public Sector Internal Audit Standards, with the Audit and Risk Committee providing independent assurance. Report P48, P49, P50, P51
  • Financial: No direct financial implications arise from the report, although individual risks may have financial implications which will be progressed through appropriate governance. Report P47
  • Equalities: The Public Sector Equality Duty has been considered and no equality and diversity implications arise directly from this report. Report P53, P57
  • Climate: No direct climate change or sustainability implications, but the Council must manage risk effectively to support its goal of being net zero carbon by 2030. Report P59
  • Staffing: Completion and oversight of the risk registers will require resource from the Joint Leadership Team, Service Leads, the Strategy and Performance team and specialists. Report P56
  • Risk: Several risks were rescored: SR1 financial sustainability likelihood reduced; SR2 local government reorganisation likelihood raised to Almost certain; SR2.1 instability during transition added as a new risk; SR3 scale and pace of change likelihood raised; SR6 governance of companies and charitable trusts raised, with company accounts filing extended to 29 March 2026; SR7 cyber security impact raised; SR9 decision making and governance likelihood reduced. Report P22, P23, P25, P27, P28, P29, P21
  • Other: Operational risk OR11 (capacity and resilience of the Planning service) was rescored with likelihood raised to Almost certain, and OR19 (governance in Repairs and Maintenance) was added as a new risk in Q3. Report P31

Who and where

  • All council services, since risk management is treated as integral to the strategic priority of a resilient and well managed Council Report 7.1, P33
  • Risk owners, Strategic Directors and Assistant Directors who review register content Report 9.1
  • Waverley Borough Council, which collaborates on the Risk Management Framework and holds quarterly joint review meetings Report 8.1, P35

Timeline

  • 26 January 2026: Audit and Risk Committee adjourned, prompting this combined Q2 and Q3 update Report 1.1
  • 18 March 2026: Audit and Risk Committee considered this report Report 1.2
  • 19 March 2026: Executive considers the report at this meeting
  • Q2 2025/26: Strategic risks SR2, SR2.1, SR3, SR7 and SR10 updated or added, with operational risk OR11 rescored Report P22, P23, P25, P28, P30, P31
  • Q3 2025/26: Strategic risks SR1, SR4, SR6 and SR9 updated, with operational risks OR3 and OR19 added or rescored Report P21, P26, P27, P29, P31
  • 29 March 2026: Extended deadline for filing of company accounts relating to SR6 Report P27
  • Q1 2026/27: NPPF and new Local Plan changes referred to in SR4 expected to come into place Report P26

Plain English for the jargon

  • RAG/DoT: Red, Amber, Green rating, with Direction of Travel compared to the previous quarter
  • MTFP: Medium-Term Financial Plan
  • LGR: Local Government Reorganisation
  • NPPF: National Planning Policy Framework
  • PSIAS: Public Sector Internal Audit Standards
  • CLB: Corporate Leadership Board, which receives and reviews both risk registers
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX150

Resolved

To note the updated corporate risk registers Reason(s): To enable the Executive to ensure that risks t hreatening corporate objectives are adequately addressed and managed in accordance with the Council’s risk appetite, as set out in the Council’s Risk Management Strategy. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1Following the adjournment of the Audit & Risk Committee on 26 January 2026, this report will provide updates on the Council’s corporate risks at the end of Q2 and Q3 2025/26.

1.2This report was considered by the Audit & Risk Committee on 18 March 2026.

Recommendation

2.1That the Executive note the updated corporate risk registers and make any observations on their contents.

3 Reason(s) for recommendation

3.1To enable the Executive to ensure that risks threatening corporate objectives are adequately addressed and managed in accordance with the Council’s risk appetite, as set out in the Council’s Risk Management Strategy.

4 Next steps

4.1There are no further steps for this report.

5 Exemption from publication

5.1No part of this report is exempt from publication.

6 Background and Proposal

Role of the Audit & Risk Committee

6.1The purpose of the Committee is to provide independent assurance to councillors of the adequacy of the risk management framework and the internal control environment. It provides independent review of the authority’s governance, risk management and control frameworks.

Strategic and operational risks

6.2The Council’s risk management strategy defines corporate risks as risks ‘that reside outside the usual course of management and require a wider corporate response or awareness …’. Risk Management and Corporate Risk Registers (Q2 and Q3 2025/26)

6.3Corporate risks are split into two categories: strategic and operational risks.

6.4Strategic risks (shown at Appendix 1 for Q2 and Appendix 2 for Q3) are risks that could impact the Council’s medium to long term priorities and objectives as set out in the Corporate Strategy or other corporate level policies and strategies, including the Medium-Term Financial Plan (MTFP).

6.5Operational risks are risks that are encountered in the delivery of services and which affect service objectives, as defined in service plans. Operational risks are usually managed as part of the usual course of management by services. However, where an operational risk cannot be managed within the service or if it is outside of the Council’s risk appetite, then it should be considered for inclusion on the operational risk register.

6.6Red rated operational risks (shown at Appendix 3 for Q2 and Appendix 4 for Q3) are reported to the Audit and Risk Committee and the Executive.

Changes to the risk registers since the last report

6.7Since the Executive last received an update on Strategic Risk Register in September, the following substantive changes have been made: Risk Management and Corporate Risk Registers (Q2 and Q3 2025/26)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item (1): Risk Management & Corp Risk Registers: App 1: Strat Risk Register: Q2 25-26Appendix 317 KB Download
PDF
Item (2): Risk Management & Corp Risk Registers: App 2: Strat Risk Register: Q3 25-26Appendix 318 KB Download
PDF
Item (3): Risk Management & Corp Risk Registers: App 3: Op Risk Register: Q2 25-26Appendix 135 KB Download
PDF
Item (4): Risk Management & Corp Risk Registers: App 4: Op Risk Register: Q3 25-26Appendix 166 KB Download
PDF
Risk Management and Corporate Risk Registers (Q2 and Q3 2025/26)Report 170 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
JM
Councillor Julia McShaneChairperson, present
VK
Councillor Vanessa KingVice-Chairperson, present
PB
Councillor Phil BellamyCommittee Member, apologies
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present, as expected, virtual
FW
Councillor Fiona WhiteCommittee Member, present
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Risk Management and Corporate Risk Registers (Q2 and Q3 2025/26)This decision
  2. Risk Management and Corporate Risk Registers (Q1 2026/27)Noted
  3. Risk Management and Corporate Risk Registers (Q4 2025/26)Noted
  4. Risk Management and Corporate Risk Registers (Q2 2025/26)Noted
  5. Risk Management and Corporate Risk Registers (Q1 2025/26)Noted
  6. Risk Management and Corporate Risk Registers (Q1 2025/26)Noted

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies