The Electric Theatre: Options appraisal and next steps

Noted Executive 4 papers

AI summaryGuildford Borough Council's Executive backed a hybrid cultural model for The Electric Theatre and authorised a procurement process for a new operator, with £50,000 approved for expert support.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProcurement for new operator to follow
Money£50,000Supplementary estimate for industry expert
What happens nextProcurement processExpression of Interest across two pathways
Who it affectsTheatre users and residentsCultural venue currently vacant

What was decided

The Executive noted the options appraisal from independent experts Blue Horizon Ventures, which found the building's fabric to be fundamentally sound and identified a hybrid cultural model as the most effective option. Report P14, 1.3, P4, P5

The Executive agreed that a hybrid and cultural operating model is the most appropriate for the theatre, and authorised the Joint Strategic Director of Finance and Resources to run a compliant procurement for a new operator. Report P15, P16

A supplementary estimate of £50,000 was approved to fund an industry expert to support the procurement process. Report P17, P85

Why

The Council must meet its Best Value Duty, weighing cultural and community value against financial sustainability and strategic objectives. Report 2.2, 2.14

Stakeholder engagement showed a clear preference for retaining the theatre as a cultural asset, and the council wants to progress the work transparently to maintain confidence. Report 2.13, 2.3, 5.1

The chosen approach allows the council to test whether a viable cultural model exists while still exploring commercial alternatives. Report P9, 2.15

What happens next

An Expression of Interest exercise will run across two pathways: cultural or hybrid operating models, and commercial or alternative uses. Report P26

Officers will carry out further due diligence and information gathering to support market testing, and continue asset related remedial work using the existing capital budget. Report P27, P28, P30

A compliant procurement process will be carried out to appoint a new operator for the theatre. Report P31, P16

The money

  • £50,000 Supplementary estimate for an industry expert to support the procurement process Report P17, P85
  • £275,000 Capital funding approved in 2026/27 budget for remedial, compliance and recommissioning works Report 2.4

Options considered

  • Rejected: Do nothing, leaving The Electric Theatre vacant and unused. Not recommended; fails to test feasibility and viability of operating models and the Best Value duty Report 7.2
  • Chosen: Support market testing of a hybrid cultural operating model alongside commercial or alternative uses, followed by procurement for a new operator. Recommended; responds to stakeholder interest, allows Best Value to be tested, and progresses the work in a structured way Report 7.3, 2.15

Implications

  • Financial: Any hybrid or cultural operating model is likely to require some level of ongoing financial support from the council; the extent will depend on the model chosen and the split of responsibilities. Report P7, 2.16
  • Financial: While vacant, the theatre continues to generate holding costs including business rates, utilities, insurance, security and essential maintenance. Report 6.1
  • Legal: Further legal advice will be sought as necessary to ensure actions and decisions are robust and legally compliant. Report P88
  • Risk: Market engagement may find a cultural model unviable, in which case commercial or alternative uses could be considered, including lease or freehold disposal. Report 6.3
  • Risk: Local Government Reorganisation may create delay or uncertainty, and the shadow West Surrey Council may need to consent to future decisions under the S24 Direction. Report 6.4, 4.1
  • Equalities: The council considers there are no equality and diversity implications arising directly from this report. Report P91
  • Staffing: There are no immediate HR implications as the theatre is currently closed with no staff in place; any future operator workforce matters will be considered with HR advice. Report P90
  • Climate: Bringing the theatre back into full use will increase utility and energy consumption, with associated costs falling to the future operator. Report P94

Who and where

  • Residents and stakeholders with an interest in retaining the theatre as a cultural venue Report 2.13, 5.1
  • Future operator of The Electric Theatre Report P16, P31
  • The wider cultural sector in Guildford Report P43
  • Shadow West Surrey Council, in light of Local Government Reorganisation Report 4.1, 4.2

Timeline

  • 26 February 2026: Previous Executive decision to commission independent expert advice for the theatre Report 1.1, 12.1
  • 10 March 2026: The Surrey (Structural Changes) Order 2026 came into effect Report 4.1, P68
  • 2026/27: Capital budget of £275,000 available for remedial and compliance works Report 2.4
  • 1 April 2027: Vesting Day for transfer of functions to West Surrey Council Report 4.1

Plain English for the jargon

  • BHV: Blue Horizon Ventures, the independent expert commissioned to appraise options for the theatre
  • EOI: Expression of Interest, an early market sounding exercise
  • Best Value Duty: The council's ongoing duty to ensure continuous improvement in how it exercises its functions
  • LGR: Local Government Reorganisation, including the creation of West Surrey Council
  • S24 Direction: Direction setting thresholds above which the shadow council must consent to decisions
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX19

Resolved

Note the information shared in the accompanying ‘Electric Theatre Options Appraisal’ report from independent experts Blue Horizon Ventures; 2. Agree that the hybrid/ cultural operating model is the most appropriate operating model for The Electric Theatre; 3. Authorise the Joint Strategic Director of Finance and Resources to undertake a compliant procurement process for a new operator of The Electric Theatre; and 4. Agree a supplementary estimate of £50,000 for an industry expert to support the procurement process for a new operator for The Electric Theatre. Reason(s): 1. To update the Executive on progress made to date in relation to The Electric Theatre. 2. Consistent with the Council’s Best Value Duty, to establish the feasibility and viability of potential operating models for the theatre, including its use as a cultural and community arts venue, alongside alternative commercial options. 3. To enable the timely progression of this work in a structured and transparent way, with regard to stakeholder interest and the need to maintain confidence in the process. 4. To progress with the procurement of a new operator for The Electric Theatre. Other options considered and rejected by the Executive: Option 1 (not recommended): in noting the report from BHV, do nothing, leaving The Electric Theatre vacant and unused. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1At its meeting on 26 February 2026, the Executive, in recognising the importance of The Electric Theatre to Guildford, resolved to continue to progress a programme of work to determine its future, with the next step being the commissioning of independent expert advice to appraise options and review the viability of different operating models.

1.2An options appraisal, undertaken by our independent expert, Blue Horizon Ventures (BHV), accompanies this report and marks the conclusion of the first phase of work identified.

1.3Blue Horizon’s report confirms that:

• Based on condition surveys, the internal and external fabric of The Electric Theatre is fundamentally sound. Some remedial, compliance, and recertification work is required, alongside investment to improve standards of user experience.

• A hybrid cultural operating model, combining community use with strong commercial programming, has been identified as being the most effective option.

• Governance will need to balance the division of risk and subsidy, to ensure the optimum operating model.

• All hybrid operating models are likely to require some level of subsidy; however, a balance would need to be struck between financial support and the Council’s strategic objectives.

• Further market testing is required to establish if a hybrid/ cultural model is feasible.

• Commercial/ alternative use options should be explored alongside the hybrid model, to test Best Value.

1.4As a result, it is recommended that market testing and engagement is undertaken to establish the best operating model for The Electric Theatre, and how the balance between 2 The Electric Theatre: Options appraisal and next steps

community/ cultural aspirations and financial/ strategic objectives may be delivered. Commercial/ alternative uses would also be considered as part of this exercise as well as further information gathering to support the market testing exercise followed by a comprehensive procurement process.

1.5These actions align with our Corporate Strategy priorities of being an inclusive borough and a resilient and well-managed council, as well as supporting delivery of our Best Value duty.

Recommendations

2.1That the Executive resolves to:

• Note the information shared in the accompanying ‘Electric Theatre Options Appraisal’ report from independent experts Blue Horizon Ventures.

• Agree that the hybrid/ cultural operating model is the most appropriate operating model for The Electric Theatre.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Electric Theatre OA Report FINAL PublicAppendix 1 727 KB Download
PDF
TET Governance ModelsAppendix 2 177 KB Download
PDF
Electric Theatre Benchmark Venues March 26Appendix 3 1.4 MB Download
PDF
The Electric Theatre: Options appraisal and next stepsReport 131 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
JM
Councillor Julia McShaneChairperson, present
VK
Councillor Vanessa KingVice-Chairperson, present
PB
Councillor Phil BellamyCommittee Member, present
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. The Electric Theatre: Options appraisal and next stepsThis decision
  2. The Electric Theatre - Engagement and Next StepsNoted
  3. Rodboro Buildings – Electric Theatre through road and parkingApproved
  4. Future of the Electric TheatreAgreed
  5. The Electric TheatreNoted
  6. The Electric Theatre - Working GroupDecided

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open