Guildford Town Centre and Shalford Clean Air Zone Feasibility Study

Noted Executive 4 papers

AI summaryGuildford Borough Council's Executive has noted a Clean Air Zone feasibility study for Guildford Town Centre and Shalford and decided not to pursue a Clean Air Zone, instead pursuing partnership work with Surrey County Council on alternative air quality measures.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFindings to be reported to Defra
MoneyNot stated
What happens nextReport back within six monthsWith a revised Air Quality Action Plan
Who it affectsGuildford Town Centre and Shalford AQMAsIncluding Park Street hotspot

What was decided

The Executive noted the Clean Air Zone Feasibility Study and its conclusion that a Clean Air Zone is not viable due to high costs and limited benefits. Report P8, 1.5, P82, P87

Findings will be reported in full to Defra, and the Executive will pursue the recommended option of working in partnership with Surrey County Council and any devolved representative authority. Report P9, P10

The draft Air Quality Action Plan, dated August 2022, will be revised to reflect the study outcomes, with a further report back to the Executive within six months. Report P11, P12

Why

The study concludes that a Clean Air Zone scored well for nitrogen dioxide reductions but promotion of travel choices and policies like emissions-based parking ranked higher on cost-effectiveness and quicker implementation. Report P82

The Council must meet its statutory duties on air quality and submit Air Quality Annual Status Reports under Part IV of the Environment Act 1995, as amended by the Environment Act 2021. Report 3.3, 3.4

Park Street remains above legal limits despite significant reductions, and additional air quality assessments by Air Pollution Services Ltd have been earmarked for financial year 2026/27 after a 2025/26 funding delay. Report P70, 3.5

What happens next

Officers will engage Surrey County Council and partner agencies to develop a package of measures to cut traffic emissions, improve park and ride, and promote sustainable transport. Report 4.2, 4.3

A revised Air Quality Action Plan will be prepared and presented back to the Executive, with the formation of the West Surrey authority expected to help the process. Report 4.4, 4.5

The Overview and Scrutiny Committee considered the draft report on 16 June 2026; any comments will be set out for the Executive before finalisation. Report P14, 13.1

The money

  • £22,745 Cost of Stage 1 Clean Air Zone feasibility consultancy by Buro Happold Report P130
  • £71,245 Cost of Stage 2 economic feasibility consultancy by Buro Happold Report P130
  • £2,893 Annual cost of the sustainable transport package for staff, retained until 1 February 2027 Report P131
  • £5-£7,000 Estimated cost of additional Air Quality Action Plan work, dependent on options modelled Report P132

Options considered

  • Chosen: Pursue 'Promotion of Travel Choices' and Guildford Borough Council policies (chosen). Ranked higher than a Clean Air Zone on cost-effectiveness and speed of implementation; a Clean Air Zone scored well on air quality impact but had significant capital and operating costs and revenues from fees were not sufficient. Report 11.1, P82, P79
  • Rejected: Pursue the Clean Air Zone concept by asking Surrey County Council to formally assess viability under its Transport Act 2000 powers. Lack of supporting evidence, costly exercise that may delay other improvements, and a charging regime could disadvantage certain groups and the business community; no funding allocated. Report 11.2, P125, P126, P128

Implications

  • Financial: No new funding allocated for the recommended partnership work; some GBC measures have not been costed. Report P123, P128, P134
  • Legal: Council must continue to meet its statutory air quality duties under Part IV of the Environment Act 1995 until functions transfer to the West Surrey authority on 1 April 2027. Report 8.2, P135, P136
  • Equalities: Equalities Comprehensive Impact Assessment found the proposals will not have a disproportionately adverse impact on people with protected characteristics. Report P145
  • Climate: The recommendation to pursue other improvements instead of a Clean Air Zone is judged, on balance, a suitable option in climate change and sustainability terms. Report P158
  • Risk: Some measures, including park and ride upgrades and active travel infrastructure, depend on Surrey County Council plans; behavioural change may be slow. Report 10.3, P120
  • Other: Shalford Air Quality Management Area may be revoked once 2025 monitoring data, including the effect of a 20 mph zone, is bias-adjusted. Report P86, 10.4

Who and where

  • Residents, workers and visitors in Guildford Town Centre Air Quality Management Area, declared 2021 Report 1.1, 6.1
  • Residents and road users in The Street, Shalford Air Quality Management Area, declared 2019 Report 1.1, 6.1
  • Guildford Borough Council office staff, who use 124 council parking spaces Report P73
  • Local businesses and delivery operators, particularly drivers of diesel light goods vehicles with below 60% ULEZ compliance Report P38, P71
  • Stakeholders including Shalford Community Council, Experience Guildford, Zero Carbon and Holy Trinity Amenity Group Report 9.4

Timeline

  • 2019: The Street, Shalford Air Quality Management Area declared Report 1.1, 6.1
  • 2021: Guildford Town Centre Air Quality Management Area declared Report 1.1, 6.1
  • August 2022: Draft Air Quality Action Plan produced Report 6.2, P11
  • 2023: Surrey County Council carried out Automatic Number Plate Recognition survey Report 6.3
  • September 2024: Stage 1 Buro Happold Desktop Review completed Report 9.5, 15.1
  • August 2025: Stage 2 Buro Happold Adoption of Clean Air Zone report completed Report 15.2
  • 10 March 2026: The Surrey (Structural Changes) Order 2026 came into effect, paving the way for the West Surrey authority Report 8.1
  • 16 June 2026: Overview and Scrutiny Committee considered draft report Report 13.1
  • 25 June 2026: Executive resolved on the recommendations
  • 1 April 2027: Vesting Day: functions transfer to West Surrey Council Report 8.1
  • 2026/27: Air Pollution Services Ltd earmarked to complete further air quality assessments Report 3.5
  • Within six months: Revised Air Quality Action Plan to be reported back to the Executive Report P12

Plain English for the jargon

  • Air Quality Management Area (AQMA): An area declared by a council where national air quality objectives are not being met, requiring an action plan.
  • Clean Air Zone (CAZ): A defined area where targeted measures, which may include charging, aim to reduce vehicle emissions and improve air quality.
  • Ultra Low Emission Zone (ULEZ): A London scheme requiring vehicles to meet specified emission standards or pay a daily charge.
  • Low Emission Zone (LEZ): An area where polluting vehicles are restricted or charged, typically targeting heavier vehicles.
  • Nitrogen dioxide (NO2): A pollutant from road traffic that the AQMAs in Guildford and Shalford were declared for exceeding.
  • Part IV of the Environment Act 1995: The legal framework for Local Air Quality Management, requiring councils to review, assess and act on air quality.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX20

Resolved

Note the contents of the Clean Air Zone Feasibility study report, its conclusions and recommendations; 2. To report the findings in full to the Department for Environment, Food and Rural Affairs (Defra); 3. To pursue the recommended option of working in partnership with Surrey County Council (SCC) and or any devolved representative authority; 4. To revise the draft Air Quality Action Plan, dated August 2022, to reflect the outcomes of the economic feasibility study following engagement and discussion with SCC on the shortlisted actions/measures; and 5. To report back on the revised draft Air Quality Action Plan within six months. Reason(s): 1. The studies carried out by Buro Happold consultants on the Economic Feasibility of a Clean Air Zone are part of the Air Quality Action Plan for Guildford Town Centre and Shalford Air Quality Management Areas. 2. The details of both reports will be presented at the Overview and Scrutiny Committee by the author Professor Margarethe Theseira with officers in attendance. 3. To ensure the Council meets its statutory duties in relation to air quality and the submission of Air Quality Annual Status Reports under the Environment Act 1995. 4. The report aims to provide the Committee with an update on progress of air quality projects and other statutory air quality priorities in fulfilment of Part IV of the Environment Act 1995 Local Air Quality Management, as amended by the Environment Act 2021. 5. Whilst the study is a large part of the Air Quality Action Plan for Guildford Town Centre, the final plan requires some additional air quality assessments which the original consultants Air Pollution Services Ltd have been earmarked to complete in the financial year 2026/27. This was delayed due to the lack of funding available in 2025/26. Other options considered and rejected by the Executive: Option 2: Pursue the Clean Air Zone concept by requesting that Surrey County Council formally assess the viability, under their Transport Act 2000 powers. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1Air Quality Management Areas (AQMAs) relating to annual exceedances of a major pollutant nitrogen dioxide were declared in 2021 for Guildford town centre gyratory system and 2019 for The Street (A281), Shalford. Road traffic is the primary source of emissions, with private cars being the major contributor. Guildford Town’s Air Quality Action Plan had an action to carry out an economic feasibility study of a Clean Air Zone which was extended to Shalford as the arterial A281 road serves the town centre. 1.2 This report outlines the work carried out by a consultant Professor Margarethe Theseira, Buro Happold Ltd to assess the economic feasibility of adopting a Clean Air Zone in an area covering both AQMAs. Support was provided by officers from both Guildford Borough Council and Surrey County Council covering highways, car parking, planning and environmental services. 1.3 The studies were carried out in conjunction with stakeholder meetings for Members, Shalford Community Council and local interested parties within Guildford including Experience Guildford, Zero Carbon and Holy Trinity Amenity Group 1.4 The feasibility exercise consisted of a desk top study followed by an appraisal of several options, which were condensed into three shortlisted options which were assessed against 12 criteria including air quality impact and costs:

• Promotion of Travel Choices • Clean Air Zone implementation • Policies for cleaner vehicles and emission based charging

1.5The report concludes that a Clean Air Zone is not recommended owing to limited benefits plus high costs of implementation.

1.6The report offers strategic guidance for air quality improvement through various policies and future actions such as: targeted interventions in identified hotspot areas for localised issues (Park Street), actions to achieve travel behaviour changes, Council’s policies on fleet upgrade, active travel incentivisation for staff, workplace parking levies, enhancing park and ride schemes to improve their usage and schemes for upgrading local delivery vehicles etc. Guildford Town Centre and Shalford Clean Air Zone Feasibility Study

1.7On consideration of this report the respective Air Quality Action Plans will be updated to reflect any new measures proposed by officers.

1.8The detailed reports from Buro Happold can be viewed in full via the links in 16.0 Background Papers.

Recommendations

2.1That the Executive resolves to:

2.1.1 Note the contents of the Clean Air Zone Feasibility study report, its conclusions and recommendations

2.1.2 To report the findings in full to the Department for Environment, Food and Rural Affairs (Defra)

2.1.3 To pursue the recommended option of working in partnership with Surrey County Council (SCC) and or any devolved representative authority.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Guildford Town Centre and Shalford Clean Air Zone Feasibility StudyReport 178 KB DownloadRead as text
PDF
Item 04: Appendix 1 Final Guildford LEZAppendix 3.3 MB Download
PDF
Item 04: Appendix 2 Guildford and Shalford Feasibility ReportAppendix 4.1 MB Download
PDF
Item 04: Appendix 3 Economic Feasibility Study EIA2Appendix 124 KB Download

At this meeting

Whole meeting

Who was there

7 of 8 attended
JM
Councillor Julia McShaneChairperson, present
VK
Councillor Vanessa KingVice-Chairperson, present
PB
Councillor Phil BellamyCommittee Member, present
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Guildford Town Centre and Shalford Clean Air Zone Feasibility StudyThis decision
  2. Review of Guildford Town Centre Public Space Protection OrderApproved
  3. Guildford Town Centre Views Supplementary Planning DocumentApproved
  4. Unlocking Guildford - Blackwater Valley Hotspots and Guildford Town Centre ApproachesApproved
  5. Guildford Town Centre Regeneration StrategyApproved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open