Cabinet, Monday 12 October 2020 at 6.30pm

Capital Programme Monitor & Budget Variations, 2020/21 (First Quarter)

Approved Executive 1 paper

Cabinet approved this item on Monday 12 October 2020. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

To approve the proposed budget variations to the capital programme totalling £36.4m (summarised in Table 1 and detailed in Appendix 2). 2. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 26, 27 and 28. 3. To delegate the allocation of the HRA Asset Management and Compliance Programme unallocated budget to the Strategic Director of the Economy, in consultation with the Director of Finance.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

This report provides a financial update on the council’s capital programme and requests approval for budget variations to the capital programme.

Recommendations

1. To approve the proposed budget variations to the capital programme totalling £36.4m (summarised in Table 1 and detailed in Appendix 2).

2. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 26, 27 and 28.

3. To delegate the allocation of the HRA Asset Management and Compliance Programme unallocated budget to the Strategic Director of the Economy, in consultation with the Director of Finance.

Wards Affected: All

H&F Priorities

The capital programme contains schemes and projects which are directly linked to the Council’s Business Plan 2018-22 and which deliver across the Council’s priorities.

Our Priorities Summary of how this report aligns to the H&F Priorities  Being All capital investment decisions are required to be underpinned by a ruthlessly robust business plan that sets out any expected financial return financially alongside the broader outcomes including economic and social efficient benefits.

This report provides detailed analysis of the Council’s capital programme financial position and highlights any potential risks and their impact on the Council’s resources. Financial Impact

1. This report is wholly of a financial nature. The headline movements are:  a net increase in the 4-year capital programme of £0.5m to £521.8m.  a net decrease in forecast 2020-21 expenditure of £36.4m (24.9% of the approved budget) largely due to the rephasing of expenditure to future years. The variations are detailed in Appendix 2.

2. Covid-19 is impacting on the previously approved capital programme:  expected grant funding allocations of £2.1m from Transport for London (TfL) are no longer assumed due to the impact of Covid-19 on TfL. TfL are expected to run a revised bidding process.  a switch in funding of £0.246m for column replacement works from parking income to borrowing. This is due to the adverse impact of Covid-19 on parking revenue income  a number of schemes have experienced delays due to social distancing restrictions.  The pandemic, and the potential for an economic downturn, may affect the expected costs, market and viability of schemes. This will be kept under review and mitigating actions will be considered as necessary.

3. Headline General Fund (GF) borrowing is forecast to increase by £69.9m over the next four years to support capital investment. This would result in an estimated additional revenue budget outgoing of £3.37m per annum by 2024-25. General Fund capital receipts can reduce future borrowing and/or protect use of reserves. The council’s property transformation strategy is reviewing all its assets in a systematic way as part of asset management best practice. As part of this review surplus assets may be identified for sale that can support the capital programme.

4. The Housing Revenue Account 2020-21 borrowing requirement (CFR) is forecast to increase by £22.1m to £237.9m. By the end of 2023-24 the HRA CFR is forecast to be £278.5m as detailed in paragraph 20 of the report.

Legal Implications There are no direct legal implications in relation to this report. Legal advice will be sought for each Procurement within the programme and will comply with the Council’s Contract Standing Orders and the Public Contract Regulations.

Contact Officer(s):

Name: Andrew Lord Position: Head of Strategic Planning and Monitoring Telephone: 020 8753 2531 Email: [email protected] Verified by Emily Hill, Director of Finance

Name: Adesuwa Omoregie Position: Head of Law Telephone: 0208 753 2297 Email: [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitor & Budget Variations, 2020/21 (First Quarter)Report 508 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
SC
Councillor Stephen CowanChair, present
SF
Councillor Sue FennimoreCommittee Member, present
BC
Councillor Ben ColemanCommittee Member, present
AC
Councillor Adam ConnellCommittee Member, present
LC
Councillor Larry CulhaneCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
LH
Councillor Lisa HomanCommittee Member, present
SM
Councillor Sue MacmillanCommittee Member, present
MS
Councillor Max SchmidCommittee Member, present

On this subject at Hammersmith & Fulham

Search all
  1. Capital Programme Monitor & Budget Variations, 2020/21 (First Quarter)This decision
  2. Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)Noted
  3. Capital Programme Outturn 2025/26Noted
  4. Capital Programme Monitor and Budget Variations 2025/26 (Quarter 3)Noted
  5. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  6. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies