AGREED UNANIMOUSLY BY CABINET: 1. To approve the proposed budget variations to the capital programme totalling £9.1m (summarised in Table 1 and detailed in Appendix 2). 2. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 26, 27 and 28. 3. To approve budget amendments of £1,016,000, funded from borrowing, to complete transport and parks schemes for which expected TfL grants and section 106 contributions are no longer available (see Appendix 2 for detail). 4. To approve funding from borrowing of £455,000 for previously approved transport schemes for which S106 and TfL funding contributions are no longer available.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
This report provides a financial update on the council’s capital programme and requests approval for budget variations to the capital programme.
Recommendations
1. To approve the proposed budget variations to the capital programme totalling £9.1m (summarised in Table 1 and detailed in Appendix 2).
2. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 26, 27 and 28.
3. To approve budget amendments of £1,016,000, funded from borrowing, to complete transport and parks schemes for which expected TfL grants and section 106 contributions are no longer available (see Appendix 2 for detail).
4. To approve funding from borrowing of £455,000 for previously approved transport schemes for which S106 and TfL funding contributions are no longer available.
Wards Affected: All
H&F Priorities
The capital programme contains schemes and projects which are directly linked to the Council’s Business Plan 2018-22 and which deliver across the Council’s priorities. Our Priorities Summary of how this report aligns to the H&F Priorities Being All capital investment decisions are required to be underpinned by a ruthlessly robust business plan that sets out any expected financial return financially alongside the broader outcomes including economic and social efficient benefits.
This report provides detailed analysis of the Council’s capital programme financial position and highlights any potential risks and their impact on the Council’s resources.
Financial Impact
1. This report is wholly of a financial nature. The headline movements are: a net decrease in the 4-year capital programme of £26.6m to £495.2m. a net decrease in forecast 2020-21 expenditure of £9.1m (8.3% of the approved budget) largely due to the rephasing of expenditure to future years. The variations are detailed in Appendix 2.
2. Covid-19 is impacting on the previously approved capital programme: expected grant funding allocations of £25m from Transport for London (TfL) for future years are no longer assumed due to the impact of Covid-19 on TfL. TfL are expected to run a revised bidding process. a number of schemes have experienced delays due to social distancing restrictions. the pandemic, and the potential for an economic downturn, may affect the expected costs, market and viability of schemes – this will be kept under review and mitigating actions will be considered as necessary.
3. Headline General Fund (GF) borrowing is forecast to increase by £71.2m over the next four years to support capital investment. This would result in an estimated additional revenue budget outgoing of £4.2m per annum by 2024-25. General Fund capital receipts can reduce future borrowing and/or protect use of reserves. The council’s property transformation strategy is reviewing all its assets in a systematic way as part of asset management best practice. As part of this review surplus assets may be identified for sale that can support the capital programme.
4. The Housing Revenue Account 2020-21 borrowing requirement (CFR) is forecast to increase by £14m to £229.7m. By the end of 2023-24 the HRA CFR is forecast to be £277m as detailed in paragraph 20 of the report.
Legal implications
There are no direct legal implications in relation to this report. Legal advice will be sought for each Procurement within the programme and will comply with the Council’s Contract Standing Orders and the Public Contract Regulations.
Contact Officer(s): Name: Andrew Lord Position: Head of Strategic Planning and Monitoring Telephone: 020 8753 2531 Email: [email protected] Verified by Emily Hill, Director of Finance
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies