AGREED UNANIMOUSLY BY THE CABINET MEMBERS PRESENT: 1. To note the net forecast decrease in 2021/22 capital expenditure of £29.7m (18.9% of the approved budget). The variations are detailed in Appendix 2. 2. To approve the updated four-year capital programme 2021-2025 of £473.4m as detailed in Appendix 1. 3. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 22-24.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
This report provides a financial update on the council’s capital programme and requests approval for budget variations to the capital programme.
Recommendations
1. To note the net forecast decrease in 2021/22 capital expenditure of £29.7m (18.9% of the approved budget). The variations are detailed in Appendix 2.
2. To approve the updated four-year capital programme 2021-2025 of £473.4m as detailed in Appendix 1.
3. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 22-24.
Wards Affected: All
The capital programme contains schemes and projects which are directly linked to the Council’s Business Plan 2018-22 and which deliver across the Council’s priorities.
Our Values Summary of how this report aligns to the H&F Values Being All capital investment decisions are required to be underpinned ruthlessly by a robust business plan that sets out the full costs and risks financially and any expected financial return alongside the broader efficient outcomes including economic and social benefits.
Officers are responsible for monitoring and delivering projects within approved budgets and reporting variances.
This report provides detailed analysis of the Council’s capital programme financial position and highlights any potential risks and their impact on the Council’s resources. Financial Impact
This report is wholly of a financial nature.
The headline movements this quarter are: forecast capital expenditure over the next 4 years is £15.2m lower than forecast in quarter 1. This is mainly due to the reprofiling of budgets beyond the current 4 year programme for Education City (£16.7m) and Edith Summerskill (£5.5m). The programme also reflects £6m for Hammersmith Bridge stabilisation works approved in August 2021. a net decrease in forecast 2021/22 expenditure of £29.7m. The variations are detailed in Appendix 2.
Covid-19 is impacting the previously approved capital programme: a number of schemes have experienced delays due to social distancing restrictions. the pandemic, and the potential for an economic downturn, may affect the expected costs, market for and viability of schemes – this will be kept under review and mitigating actions will be considered as necessary.
The 2021/22 Headline General Fund (GF) borrowing requirement (CFR) is forecast to increase by £50.3m over the next four years to support capital investment. This would result in an estimated additional revenue budget outgoing of £2.6m per annum by 2025/26.
The Housing Revenue Account 2021/22 borrowing requirement (HRA CFR) is forecast to increase by £25.9m to £258.9m. By the end of 2024/25 the HRA CFR is forecast to be £341.8m.
Legal implications
There are no direct legal implications in relation to this report. Legal advice will be sought for each Procurement within the programme and will comply with the Council’s Contract Standing Orders and the Public Contract Regulations.
Contact Officers:
Name: Andrew Lord Position: Head of Strategic Planning and Monitoring Telephone: 020 8753 2531 Email: [email protected] Verified by Emily Hill, Director of Finance
Name: Adesuwa Omoregie Position: Assistant Director, Legal Services Telephone: 02087532297 Email: [email protected] Background Papers Used in Preparing This Report
The following documents disclose important facts on which the report is based and have been relied upon in preparing the report: Capital Programme 2021-25 (published February 2021)
CAPITAL PROGRAMME 2021-22 – Q2 OVERVIEW
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.