AGREED UNANIMOUSLY BY THE CABINET MEMBERS PRESENT: 1. To approve a new capital budget of up to £3.5m in 2022/23 to progress concept design and associated works leading to the strengthening and restoration works to be initially funded by Council borrowing (increase to the Capital Financing Requirement). 2. To approve the procurement approach set out in paragraph 4 given the specialist nature of the works. 3. To approve the appointment of the preferred technical experts to complete the work for the amounts set out in paragraph 4, subject to a client held contingency being used where required.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Hammersmith Bridge (the Bridge) was re-opened to pedestrians, cyclists and river traffic on 17 July 2021 following a significant period of closure. This decision was taken (with the advice of the Case for Continued Safe Operation (CCSO)) after the completion of extensive investigations by London Borough of Hammersmith & Fulham (LBHF) engineers that included the introduction of a pioneering temperature control scheme.
In order to maintain expeditious progress, the Council commissioned independent external advice on the design solutions for the stabilisation of Hammersmith Bridge and the preferred option was approved by the Leader of the Council on 16 August 2021. Cabinet on 6 December 2021 approved the stabilisation project, which should be completed in 2022.
Progress must be maintained for the full re-opening of the Bridge to all motorised traffic - in line with the Strategic Transport aspirations of the Department for Transport, Transport for London and the Council. In this regard, there are essential works on the concept design and technical ground investigations that need to be completed during the year whilst the stabilisation works are progressing. This will ensure that the future project to strengthen the Bridge can be undertaken with greater expediency, effectiveness and minimisation of technical risks.
This report sets out the details of this work and proposals for the commencement of the work through preferred external technical experts and suppliers. This expenditure will be incorporated as part of the overall expenditure for the full restoration of the Bridge.
Recommendations
1. To approve a new capital budget of up to £3.5m in 2022/23 to progress concept design and associated works leading to the strengthening and restoration works to be initially funded by Council borrowing (increase to the Capital Financing Requirement). 2. To approve the procurement approach set out in paragraph 4 given the specialist nature of the works.
3. To approve the appointment of the preferred technical experts to complete the work for the amounts set out in paragraph 4, subject to a client held contingency being used where required.
Wards Affected: All
Our Values Summary of how this report aligns to the H&F Values Building shared prosperity The commencement of this preparatory work will continue to promote the confidence of residents and businesses that are based in the Borough and will support continued future economic growth
Doing things with local residents, not to The projects to stabilise and strengthen them the Bridge are being undertaken with extensive public engagement through public meetings and media
Being ruthlessly financially efficient The completion of this preparatory work will minimise future financial risks by providing greater certainty of the technical matters to restore the Bridge. In line with government announcements, this is expected to be two thirds funded by DfT and TfL
Taking pride in H&F The work will eventually lead to the full restoration of a historic asset that is much valued and appreciated by residents
Rising to the challenge of the climate The current diversion of traffic (with and ecological emergency greater consequential carbon emissions will be reduced) as will long term levels of traffic through a potential future road charge for users of the Bridge
Financial Impact
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.