Hammersmith Bridge - Essential Work Leading to Strengthening and Restoration Project

Agreed Executive 1 paper

Cabinet agreed this item on Monday 7 March 2022. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

AGREED UNANIMOUSLY BY THE CABINET MEMBERS PRESENT: 1. To approve a new capital budget of up to £3.5m in 2022/23 to progress concept design and associated works leading to the strengthening and restoration works to be initially funded by Council borrowing (increase to the Capital Financing Requirement). 2. To approve the procurement approach set out in paragraph 4 given the specialist nature of the works. 3. To approve the appointment of the preferred technical experts to complete the work for the amounts set out in paragraph 4, subject to a client held contingency being used where required.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

Hammersmith Bridge (the Bridge) was re-opened to pedestrians, cyclists and river traffic on 17 July 2021 following a significant period of closure. This decision was taken (with the advice of the Case for Continued Safe Operation (CCSO)) after the completion of extensive investigations by London Borough of Hammersmith & Fulham (LBHF) engineers that included the introduction of a pioneering temperature control scheme.

In order to maintain expeditious progress, the Council commissioned independent external advice on the design solutions for the stabilisation of Hammersmith Bridge and the preferred option was approved by the Leader of the Council on 16 August 2021. Cabinet on 6 December 2021 approved the stabilisation project, which should be completed in 2022.

Progress must be maintained for the full re-opening of the Bridge to all motorised traffic - in line with the Strategic Transport aspirations of the Department for Transport, Transport for London and the Council. In this regard, there are essential works on the concept design and technical ground investigations that need to be completed during the year whilst the stabilisation works are progressing. This will ensure that the future project to strengthen the Bridge can be undertaken with greater expediency, effectiveness and minimisation of technical risks.

This report sets out the details of this work and proposals for the commencement of the work through preferred external technical experts and suppliers. This expenditure will be incorporated as part of the overall expenditure for the full restoration of the Bridge.

Recommendations

1. To approve a new capital budget of up to £3.5m in 2022/23 to progress concept design and associated works leading to the strengthening and restoration works to be initially funded by Council borrowing (increase to the Capital Financing Requirement). 2. To approve the procurement approach set out in paragraph 4 given the specialist nature of the works.

3. To approve the appointment of the preferred technical experts to complete the work for the amounts set out in paragraph 4, subject to a client held contingency being used where required.

Wards Affected: All

Our Values Summary of how this report aligns to the H&F Values Building shared prosperity The commencement of this preparatory work will continue to promote the confidence of residents and businesses that are based in the Borough and will support continued future economic growth

Doing things with local residents, not to The projects to stabilise and strengthen them the Bridge are being undertaken with extensive public engagement through public meetings and media

Being ruthlessly financially efficient The completion of this preparatory work will minimise future financial risks by providing greater certainty of the technical matters to restore the Bridge. In line with government announcements, this is expected to be two thirds funded by DfT and TfL

Taking pride in H&F The work will eventually lead to the full restoration of a historic asset that is much valued and appreciated by residents

Rising to the challenge of the climate The current diversion of traffic (with and ecological emergency greater consequential carbon emissions will be reduced) as will long term levels of traffic through a potential future road charge for users of the Bridge

Financial Impact

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hammersmith Bridge: Essential Work Leading to Strengthening and Restoration ProjectReport 162 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
SC
Councillor Stephen CowanChair, present
SF
Councillor Sue FennimoreCommittee Member, present
BC
Councillor Ben ColemanCommittee Member, present
AC
Councillor Adam ConnellCommittee Member, present
LC
Councillor Larry CulhaneCommittee Member, apologies
WH
Councillor Wesley HarcourtCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
LH
Councillor Lisa HomanCommittee Member, present
MS
Councillor Max SchmidCommittee Member, apologies
SH
Councillor Sharon HolderCommittee Member, present
KN
Katia NealeSecretary, expected

On this subject at Hammersmith & Fulham

Search all
  1. Hammersmith Bridge - Essential Work Leading to Strengthening and Restoration ProjectThis decision
  2. Hammersmith Bridge Restoration ProgrammeNoted
  3. Hammersmith Bridge - toll order and road user charging schemeNoted
  4. Hammersmith Bridge – Essential Work Leading to Strengthening and Restoration ProjectAgreed
  5. Procurement Strategy for the Delivery of Full Restoration and Strengthening of Hammersmith BridgeAgreed
  6. Hammersmith Bridge - Stabilisation Project ApprovalAgreed

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies