London Borough of Hammersmith & Fulham
Cabinet, Monday 6 July 2026 at 7.00pm

Hammersmith Bridge Restoration Programme

Noted Executive 1 paper

AI summaryHammersmith & Fulham Cabinet backs a phased repair bid to the DfT's £1bn Structures Fund and approves £1.5m a year from 2026/27 to keep the bridge safe.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBid to DfT Structures Fund to be submitted
Money£1.5m a year from 2026/27Revenue budget for safety, monitoring, inspection
What happens nextBid submission by 3 AugustStructures Fund awards expected autumn 2026
Who it affectsAll wards, pedestrians, cyclists, river usersBridge remains substandard and at risk of full closure

What was decided

Cabinet endorsed phased repair as the council's current strategic approach, focused on keeping the bridge open to pedestrians, cyclists and river traffic rather than restoring it for motor vehicles. Report P13

The Executive Director of Place, with the Cabinet Member for Climate Emergency and Travel, was authorised to approve the Structures Fund bid, decide any local funding contribution and complete the procurement strategy. Report P14, P15, P16

An annual revenue budget of £1.5m from 2026/27 was approved for ongoing statutory and safety obligations, unless external funding removes or reduces this requirement. Report P17

Why

The DfT/TfL funding settlement of 1 June 2021 imposed a one-thirds split, but the council has spent £54m to date and is owed a further £22.9m by the DfT and TfL that it is still trying to recover. Report P2, P5, P6, P27

The recent medium-term financial settlement means the council cannot fund bridge repair from its own resources, and the only available government route is the £1bn Structures Fund, which requires completion by 31 March 2030. Report P7, P9, P30

The bridge is officially substandard, likely to need full closure in the short to medium term without major investment, and the Structures Fund is described as the only funding option available. Report P7, P9, P35

What happens next

Submit the full Structures Fund bid by 3 August 2026, with awards expected in autumn 2026 and all funded works to be completed by March 2030. Report P115, P117

Continue discussions with the DfT and TfL on recovering £22.9m of contributions for stabilisation and related costs already incurred, with a further Cabinet report to follow. Report P18, P27

Any future move to allow motor vehicles on the bridge will require fresh Cabinet approval, based on an objective transport and traffic flow assessment. Report P14

The money

  • £1bn DfT Structures Fund for repair of roads, bridges, flyovers and tunnels Report P9, P30
  • £54m Council spend on the bridge from April 2019 closure to end of 2025/26 Report P2, P23
  • £300m Updated estimate for full restoration allowing motor vehicles Report P4
  • £1.5m Annual revenue budget from 2026/27 for monitoring, inspection and maintenance of the substandard bridge Report P8, P17
  • £128m High-level budget estimate in the council's pre-application to the Structures Fund, including pedestal casings and optimism bias Report P30, P115
  • £200,000 Estimated one-off cost of specialist consultants to prepare the full bid, to be met from existing capital programme or corporate contingencies Report P38, P121
  • £22.9m Further contribution the council says is due from the DfT and TfL based on forecast total spend of £58.34m Report P27, P28
  • £15.96m Contributions received to date from the DfT and TfL (excluding pre-stabilisation TfL spend) Report P27
  • £10m Cost of removing the cast iron pedestal casings, funded by TfL; reinstatement remains a future liability Report P29, P108
  • £120,000 a year Storage cost for the removed pedestal casings Report P109, P125
  • £4.7m DfT funding confirmed on 25 March 2025 to repair seized central hanger bearings, including £1.5m reimbursement of the hanger bypass system Report P112

Options considered

  • Chosen: Submit a phased repair bid to the DfT's £1bn Structures Fund, with completion required by March 2030. Only available government funding route; full restoration cannot be completed within the fund's deadline Report P9, P30, P94, P13
  • Rejected: Pursue full restoration to allow motor vehicles, estimated at around £300m. Cannot be completed by 31 March 2030 Structures Fund deadline; council cannot fund its share without a road user charge; would require separate Cabinet approval Report P4, P30, P14, P93
  • Rejected: Continue without any major repair programme and only meet ongoing inspection and safety costs. Bridge is likely to need full closure on safety grounds in the short to medium term Report P7, P37

Implications

  • Financial: Council cannot fund bridge repair from its own resources; medium-term financial settlement makes the General Fund position more difficult and a successful bid is needed to avoid a future funding gap. Report P7, P21, P22
  • Financial: Any Structures Fund award is unlikely to cover the full £128m; a local contribution is expected, and any cost overruns on the approved scheme fall to the council as highway authority. Report P30, P118, P120
  • Legal: Under the Highways Act 1980 the council is responsible for maintaining the bridge, so the £1.5m annual revenue budget supports compliance with its statutory duty. Report P40
  • Risk: High financial risk that maintenance and repair costs continue to rise, with pressure on other council service budgets; mitigations include cost ceilings, secondary cost strategies and an exit strategy. Report P134, P135
  • Risk: High reputational risk that bridge management attracts adverse national coverage, partly driven by dissatisfaction originating outside the borough or directed at TfL and the DfT. Report P136
  • Risk: Operational risk that the maintenance programme becomes overly complex; a new organisational structure is in place, supported by a risk register, change management and communications plan. Report P137
  • Equalities: No equalities assessment is highlighted in the report; the decision is presented as a strategic funding matter affecting all wards. Report P19
  • Climate: Future procurement of repair works will consider carbon emissions and broader environmental impact as part of the council's climate and ecological emergency response. Report P20

Who and where

  • All wards of the London Borough of Hammersmith & Fulham Report P19
  • Pedestrians, cyclists and river users of Hammersmith Bridge Report P1, P13, P58
  • Residents and businesses in H&F and neighbouring boroughs reliant on the crossing Report P20
  • The Department for Transport and Transport for London as potential funders Report P5, P6, P18
  • Motorists, whose return to the bridge would require fresh Cabinet approval and an objective travel and traffic assessment Report P14

Timeline

  • April 2019: Bridge closed to motor vehicles after pedestal micro-fractures were identified Report P49
  • 13 August 2020: Bridge fully closed and evacuated after pedestal micro-fractures widened during a heatwave Report P50
  • 1 June 2021: DfT and TfL funding settlement imposed a one-thirds cost split on the council Report P5, P62
  • 17 July 2021: Bridge reopened to pedestrians and cyclists on a temporary basis Report P58
  • October 2024: Emergency hanger bypass system installed to reduce risk of deck failure Report P84
  • 30 January 2025: Hammersmith Bridge Taskforce reconvened by the Minister for Local Transport Report P88
  • February 2025: Stabilisation works to the pedestals completed Report P85
  • 25 March 2025: DfT confirmed £4.7m for central hanger bearing repairs Report P112
  • 17 April 2025: Bridge main deck fully reopened to pedestrians and cyclists following DfT-funded resurfacing Report P1, P85
  • June 2025: Government announced £1bn Structures Fund as part of its 10-Year Infrastructure Strategy Report P113
  • April 2026: DfT formally opened the Structures Fund application process Report P115
  • 2026/27: Approved annual revenue budget of £1.5m for monitoring, inspection and maintenance begins Report P17
  • 25 May 2026: LBHF submitted a pre-application to the Structures Fund for works estimated at £128m Report P115
  • 3 August 2026: Deadline for full Structures Fund submissions Report P115
  • Autumn 2026: Structures Fund award decisions expected Report P117
  • 31 March 2030: Latest date for Structures Fund-supported programmes to be completed Report P9, P30, P117

Plain English for the jargon

  • Structures Fund: A £1bn DfT fund announced in June 2025 to support repair of major highway structures such as roads, bridges, tunnels and flyovers, with works required to complete by 31 March 2030.
  • CS470: The bridge assessment code that applies to substandard highway structures and requires enhanced monitoring, inspection and, in this case, limits on the number of users on the bridge at one time.
  • Substandard structure: A bridge that does not meet current strength or condition standards and needs extra monitoring, inspection and sometimes access restrictions to remain in safe use.
  • Phased repair: An approach that prioritises the most life-expired and high-risk elements of the bridge, aimed at keeping it open to pedestrians, cyclists and river traffic rather than restoring it for motor vehicles.
  • Outline Business Case (OBC): The required business case document submitted to the DfT to unlock funding under the June 2021 one-thirds settlement; LBHF's OBC was withdrawn before decision and is not expected to progress to full restoration at this time.
  • Road User Charging Scheme (RUCS) or toll: A proposed mechanism for the council to recover its one-third share of restoration costs from bridge users; Cabinet agreed in November 2023 to prepare the legal instruments for such a scheme, which cannot be used under a phased repair approach that excludes motor vehicles.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

To note the Governments Spending Review settlement secured a £1bn Structures Fund to repair run down roads, bridges and other infrastructure across the country. This is the only funding option available at this time to repair Hammersmith Bridge and if a bid were successful, it would provide a phased repair approach focused on the most critical life-expired elements of the structure, with the immediate aim of keeping the bridge open and safeguarding access for pedestrians, cyclists and river traffic. To endorse phased repair as the Council’s current strategic approach for Hammersmith Bridge, with the immediate objective of safeguarding continued access for pedestrians, cyclists and river traffic while minimising the Council’s future liabilities. Cabinet approval is required before any actions are taken to pursue funding to achieve strengthening that would permit motor vehicles to use the bridge. Any consideration about strengthening must be taken based on an objective assessment of transport need including traffic flow information and build on the bridge’s active travel success. To authorise the Executive Director of Place, in consultation with the Cabinet Member for Climate Emergency and Travel, to approve the Bid for phased repair through the Structures Fund. To delegate to the Executive Director of Place in consultation with the Cabinet Member to determine what, if any, local funding should form part of the bid. To delegate to the Executive Director of Place in consultation with the Cabinet Member the completion of a procurement strategy to enable delivery of any successful bid to the Structures Fund. To approve an annual revenue budget of £1.5m from 2026/27 to meet the Council’s ongoing statutory and safety obligations for monitoring, inspection and maintenance of Hammersmith Bridge as a substandard structure, unless and until external funding is secured that removes or materially reduces this requirement. To note the continuing discussions with the DfT and TfL regarding recovery of contributions previously expected from those parties in respect of stabilisation and related bridge costs already incurred or committed by the Council, and to require a further report to Cabinet on the outcome of those discussions.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

This report updates Cabinet on the current position of the Hammersmith Bridge Restoration Project. Following the successful completion of the Phase One stabilisation programme, the bridge main deck fully reopened to pedestrians and cyclists in April 2025.

The Council has spent £54m on the bridge from its full closure in April 2019 to the end of the financial year 2025/26. This includes the stabilisation works, ongoing safe operation of the bridge, and essential programme works in preparation for full restoration of the bridge.

To put that sum into context, Ministry of Housing, Communities and Local Government figures detail how between 2010 to 2021 all London councils spent a total of just £100m on the maintenance and repair of all London road and river bridges. Even then, most of that money was eventually paid by Transport for London (TfL) or the Government.

The Hammersmith Bridge restoration works are extensive. They essentially require a brand-new bridge to be built as all of the Grade II* listed heritage structure needs to be replaced or strengthened or restored. The cost of a full restoration of Hammersmith Bridge to allow its use for motor vehicles is now estimated to be £300m.

An unprecedented three-way equal split was imposed on the Council by the Department for Transport (DfT) in the TfL financial settlement of 1 June 2021, whereby each party should contribute one-third towards the bridge’s repair.

The Council’s position – in line with this one-thirds principle – is that it is still owed money due from TfL, primarily, and DfT towards the £54m that has been spent on the restoration project.

Furthermore, the significant impact of the most recent medium-term financial settlement from Government on the Council’s General Fund from 2026/27 means that there are no options within Council funds for repair of the bridge. The 139-year-old bridge, however, remains officially designated as a substandard structure that requires further major repairs in order to remain safely open for pedestrians, cyclists and river traffic below. Without significant investment, the bridge is likely to have to fully close again on safety grounds in the short to medium term.

In the meantime, the Council faces annual costs of approximately£1.5m from 2026/27 to meet its ongoing statutory and safety obligations for monitoring, inspection and routine maintenance of the bridge as a substandard structure.

In these difficult circumstances, the DfT has stated that the bridge would be a “good candidate for investment” from the Government’s new £1bn Structures Fund for repair of major structures including roads, bridges, flyovers and tunnels. The Structures Fund criteria states that the latest date for programmes to reach completion is 31 March 2030, which precludes full restoration.

Following discussions with the DfT, it is recommended that the Council submits a bid for a phased repair focused on the most critical life-expired elements of the structure, with the immediate aim of keeping the bridge open and safeguarding access for pedestrians, cyclists and river traffic. Last year the DfT indicated its preference to the Council for a phased repair approach to ensure that the structure remains accessible to pedestrians and cyclists.

The report asks the Cabinet to confirm the strategic direction to be taken in restoring the bridge and sets out the policy to build on Hammersmith Bridge’s active travel record and base future decisions about motor traffic returning to the bridge on objective travel and traffic flow information.

Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hammersmith Bridge Restoration ProgrammeReport 184 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
SC
Councillor Stephen CowanChair, present
AS
Councillor Alex SandersonCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, apologies
RR
Councillor Rowan ReeCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present
BK
Councillor Bora KwonCommittee Member, apologies
HB
Councillor Hannah BulmerCommittee Member, present
LH
Councillor Lisa HomanCommittee Member, present
ZQ
Councillor Zarar QayyumCommittee Member, present
NT
Councillor Nicole TrehyCommittee Member, present

On this subject at Hammersmith & Fulham

Search all
  1. Hammersmith Bridge Restoration ProgrammeThis decision
  2. Hammersmith Bridge - toll order and road user charging schemeNoted
  3. Hammersmith Bridge – Essential Work Leading to Strengthening and Restoration ProjectAgreed
  4. Procurement Strategy for the Delivery of Full Restoration and Strengthening of Hammersmith BridgeAgreed
  5. Hammersmith Bridge - Essential Work Leading to Strengthening and Restoration ProjectAgreed
  6. Hammersmith Bridge - Stabilisation Project ApprovalAgreed

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies