AGREED UNANIMOUSLY BY THE CABINET MEMBERS: 1. That Appendix 1 to this report is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) and information in respect of which a claim to legal professional privilege could be maintained in legal proceedings, as set out in paragraphs 3 and 5 of Schedule 12A of the Local Government Act 1972 (as amended). 2. To approve the Procurement Strategy for the full restoration of Hammersmith Bridge. 3. To approve the overall procurement timetable and proposed evaluation framework (set out in Sections 7 and 10 in the Detailed Analysis of the Report). 4. To note the financial matters set out in the Financial Impact Section of the Report.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Hammersmith Bridge (a Grade II* listed building) is one of the oldest suspension bridges in the world and is a unique part of our national engineering heritage. It re- opened to pedestrians, cyclists and river traffic on 17 July 2021. The bridge is currently closed to vehicular traffic and the Council is working to deliver and secure funding for a solution that will ensure its reopening and its future maintenance.
In order to maintain expeditious progress, the Council commissioned independent external advice on the design solutions for the stabilisation of Hammersmith Bridge and the preferred option was approved by the Leader of the Council on 16 August 2021.The contract for the stabilisation project was awarded by Cabinet on 6 December 2021. Further essential works leading to the full restoration of the Bridge were approved by Cabinet (March 2022) and the work has now been commissioned.
All the above costs and those historically incurred in ensuring the continued safe operation of the Bridge and developing the future restoration will be included in the overall project and are expected to be funded equally by The Department for Transport (DfT), Transport for London (TfL) and LBHF.
It is important that progress is maintained and the Council has set out the following aspirations and plans with regard to the future:
that the Bridge is fully restored at the earliest opportunity (and made accessible to all users including motorised traffic whilst also promoting the Climate Change Agenda) that the future governance arrangements support efficient and sustainable operation, maintenance and stewardship of the Bridge for the benefit of future generations (this could include the potential operation of the bridge through an independent trust or another mechanism) provides an equitable funding solution for LBHF residents with construction costs (after expected contributions from DfT and TfL) and operational costs met through the proceeds from a road user charging scheme or toll order (in this report, for convenience, reference is made to charges) – ensuring that the costs of the restoration and ongoing maintenance are funded by those who benefit directly from using the Bridge. An initial report setting out the potential future Delivery Models and considerations was presented to Cabinet in July 2021. This report develops this further and sets out the Procurement Strategy for the full restoration of the Bridge to deliver the aspirations set out above (the delivery options are detailed and appraised in the report).
Recommendations
1. That Appendix 1 to this report is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) and information in respect of which a claim to legal professional privilege could be maintained in legal proceedings, as set out in paragraphs 3 and 5 of Schedule 12A of the Local Government Act 1972 (as amended).
2. To approve the Procurement Strategy for the full restoration of Hammersmith Bridge.
3. To approve the overall procurement timetable and proposed evaluation framework (set out in Sections 7 and 10 in the Detailed Analysis of the Report).
4. To note the financial matters set out in the Financial Impact Section of the Report.
Wards Affected: All
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.