Procurement strategy for Phase 2 of the 'Preparing for net-zero' programme

Agreed Executive 1 paper

Cabinet agreed this item on Monday 18 July 2022. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

AGREED UNANIMOUSLY BY THE CABINET MEMBERS: That Cabinet approves the proposed procurement strategy to access the REFIT framework via a mini-competition which would allow the Council to award contract for the supply and installation of decarbonisation measures at H&F non-domestic sites (in the region of 39 proprieties) for a contract value of up to £8m.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

Responding to the Council’s aspiration to become a net-zero borough by 2030, work is underway to deliver retrofit projects to decarbonise the Council’s non-domestic portfolio. Public funding is now sought to enable an ambitious programme of decarbonisation (retrofit) works.

The strategy recommends accessing the RE:FIT framework which - co-owned and managed by the GLA and Local Partnerships – enables the appointment of a decarbonisation contractor to complete energy assessments, the results of which will be essential for the Council’s application to the Government’s Public Sector Decarbonisation Scheme (PSDS) in September 2022. The framework will also enable the Council to appoint the same Contractor to deliver and install the identified decarbonisation measures, although there will no obligation to proceed with the ‘works’ phase under the RE:FIT framework at this stage.

The Council will apply for an estimated total of £8m grant income which, if successful, would cover 100% of the project costs of the buildings put forward in the application, avoiding Council borrowing and investment. Should less than 100% funding be achieved, the Council will need to decide between staying within the financial envelope of grant funding offered, meeting any shortfall in project costs (£2.5m provision made in the approved 2022-23 Corporate Planned Maintenance Capital Budget) or turning down the grant funding and doing nothing. A detailed contract award report will be produced upon the funding being approved and will provide detailed assessments of potential financial risks and benefits of the scheme.

Recommendations

1. That Cabinet approves the proposed procurement strategy to access the REFIT framework via a mini-competition which would allow the Council to award contract for the supply and installation of decarbonisation measures at H&F non-domestic sites (in the region of 39 proprieties) for a contract value of up to £8m.

Wards Affected: All

Our Values Summary of how this report aligns to the H&F Values Building shared The installation of low carbon technologies in public prosperity buildings will allow residents across the borough to benefit from greener and more efficient buildings

Creating a This project, directly contributing to the Council’s efforts to compassionate tackle climate change, demonstrates compassion by council taking action to protect the future health of H&F’s people and environment

Doing things with This activity is part of a strategy which has been informed local residents, not to and scrutinised by the resident-led ‘Climate Strategy them Implementation Group’

Being ruthlessly Use of this framework is critical for a successful application financially efficient to PSDS; securing grant funding offers H&F a financially efficient route to decarbonising its non-domestic portfolio.

In addition, the framework has other financial benefits, including: (1) free consultant support for the initial stage of property analysis and benchmarking, (2) competitively priced IGPs

Taking pride in H&F The development of decarbonisation proposals will enable the Council to lead by example in delivering a cleaner and greener borough

Rising to the The development of decarbonisation proposals (and challenge of the subsequent delivery of low-carbon technologies) will climate and significantly reduce the Council’s scope 1 and 2 emissions, ecological emergency thereby directly helping H&F to combat the C&EE

Financial Impact

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement strategy for Phase 2 of the 'Preparing for net-zero' programmeReport 253 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 13 attended
SC
Councillor Stephen CowanCommittee Member, present
BC
Councillor Ben ColemanCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
SH
Councillor Sharon HolderCommittee Member, present
RH
Councillor Rebecca HarveyCommittee Member, present
BK
Councillor Bora KwonCommittee Member, present
RR
Councillor Rowan ReeCommittee Member, present
AS
Councillor Alexander SandersonCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present
AD
Councillor Andrew DinsmoreOther Attendee, present
ZQ
Councillor Zarar QayyumOther Attendee, present

All 13 on the meeting page

On this subject at Hammersmith & Fulham

Search all
  1. Procurement strategy for Phase 2 of the 'Preparing for net-zero' programmeThis decision
  2. Procurement Strategy for Community Reablement and HomecareNoted
  3. Procurement Strategy for Edward Woods Towers External Facade and Window Replacement WorksNoted
  4. Procurement Strategy for Housing Repairs 2027Noted
  5. Procurement Strategy for the Recommissioning of H&F 0-19(25) Public Health Nursing Services and a New Maternity in the Community ServiceApproved
  6. Local Electric Vehicle Infrastructure (LEVI) Procurement StrategyNoted

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies