Capital Programme Monitor & Budget Variations, 2021/22 (Outturn)

Agreed Executive 1 paper

Cabinet agreed this item on Monday 5 September 2022. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

AGREED UNANIMOUSLY BY THE CABINET MEMBERS: 1. To approve the proposed budget variations to the capital programme as summarised in Table 1 and detailed in Appendix 2. 2. To approve £1.75m additional capital budget for the Civic Campus commercial property cinema site fit out, as detailed in the paragraphs 10-13 of the report. 3. To note the capital outturn for the year.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

This report provides a summary of the Council’s capital programme outturn for the financial year 2021/22 and requests approval for budget variations to the capital programme.

Recommendations

1. To approve the proposed budget variations to the capital programme as summarised in Table 1 and detailed in Appendix 2.

2. To approve £1.75m additional capital budget for the Civic Campus commercial property cinema site fit out, as detailed in the paragraphs 10-13 of the report.

3. To note the capital outturn for the year.

Wards Affected: All

The capital programme contains schemes and projects which are directly linked to the Council’s Business Plan 2018-22 and which deliver across the Council’s priorities.

Our Values Summary of how this report aligns to the H&F Values Being All capital investment decisions are required to be underpinned ruthlessly by a robust business plan that sets out the full costs and risks financially and any expected financial return alongside the broader efficient outcomes including economic and social benefits.

Officers are responsible for monitoring and delivering projects within approved budgets and reporting variances.

This report provides detailed analysis of the Council’s capital programme financial position and highlights any potential risks and their impact on the Council’s resources. Financial Impact

This report is wholly of a financial nature. The headline movements are:  a net increase in the 4-year capital programme of £142.51m to £615.75m.  a net decrease in forecast 2021/22 expenditure of £21.2m (18.2% of the approved budget at the third quarter). The variations are detailed in Appendix 2.

Covid-19 and the wider economic circumstances are impacting the previously approved capital programme:  a number of schemes have experienced delays due to social distancing restrictions  supply of materials, rising inflation, pressures in the labour market as a result of the pandemic, Brexit and the war in Ukraine, may affect the expected costs, market and viability of schemes – this will be kept under review and mitigating actions will be considered as necessary  the originally approved capital budget has been significantly reduced due to the loss of Transport for London (TfL) grants and the resulting removal of those capital schemes.

The 2021/22 Headline General Fund (GF) borrowing requirement (CFR) is £128.91m and is forecast to increase by £53m over the next four years to support capital investment. This would result in an estimated additional revenue budget outgoing of £3m per annum by 2025/26.

The Housing Revenue Account 2021/22 CFR is £256.97m, this is an increase of £23.92m in comparison to 2020/21.

Andrew Lord (Head of Strategic Planning and Investment), 10 June 2022 and verified by Sukvinder Kalsi, Director of Finance, 24 August 2022.

There are no direct legal implications in relation to this report. Legal advice will be sought for each Procurement within the programme and will comply with the Council’s Contract Standing Orders and the Public Contract Regulations.

Adesuwa Omoregie, Assistant Director of Legal Services, 20 June 2022

Background Papers Used in Preparing This Report

The following documents disclose important facts on which the report is based and have been relied upon in preparing the report:  Capital Programme 2021-25 (published February 2021) CAPITAL PROGRAMME 2021/22 – OUTTURN OVERVIEW

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitor & Budget Variations, 2021/22 (Outturn)Report 506 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 14 attended
SC
Councillor Stephen CowanChair, present
BC
Councillor Ben ColemanCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
SH
Councillor Sharon HolderCommittee Member, present
RH
Councillor Rebecca HarveyCommittee Member, present
BK
Councillor Bora KwonCommittee Member, present
RR
Councillor Rowan ReeCommittee Member, present
AS
Councillor Alex SandersonCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present
PQ
Councillor Patricia QuigleyOther Attendee, present
AP
Councillor Adrian Pascu-TulbureOther Attendee, present

All 14 on the meeting page

On this subject at Hammersmith & Fulham

Search all
  1. Capital Programme Monitor & Budget Variations, 2021/22 (Outturn)This decision
  2. Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)Noted
  3. Capital Programme Outturn 2025/26Noted
  4. Capital Programme Monitor and Budget Variations 2025/26 (Quarter 3)Noted
  5. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  6. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies