London Borough of Hammersmith & Fulham
Cabinet, Monday 9 January 2023 at 7.00pm

Capital Programme Monitor & Budget Variations, 2022/23 (Second Quarter)

Noted Executive 1 paper

Cabinet noted this item on Monday 9 January 2023. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

To note the net forecast decrease in forecast 2022/23 capital expenditure of £17m. The variations are detailed in Appendix 2. 2. To approve the updated four-year capital programme 2022-2026 of £695.6m as detailed in Appendix 1. 3. To approve an additional budget of £0.300m for the Farm Lane predevelopment costs (as described in Appendix 6) funded from General Fund borrowing. 4. To approve an additional budget of £1.435m for asset management and compliance programme costs related to pre-agreed and void works funded from the Housing Revenue Account (HRA) borrowing as des cribed in paragraph 14. 5. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 16-19.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

This report provides a financial update on the council’s capital programme and requests approval for budget variations to the capital programme.

Recommendations

1. To note the net forecast decrease in forecast 2022/23 capital expenditure of £17m. The variations are detailed in Appendix 2.

2. To approve the updated four-year capital programme 2022-2026 of £695.6m as detailed in Appendix 1.

3. To approve an additional budget of £0.300m for the Farm Lane predevelopment costs (as described in Appendix 6) funded from General Fund borrowing.

4. To approve an additional budget of £1.435m for asset management and compliance programme costs related to pre-agreed and void works funded from the Housing Revenue Account (HRA) borrowing as described in paragraph 14.

5. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 16-19.

Wards Affected: All

The capital programme contains schemes and projects which are directly linked to the Council’s priorities.

Our Values Summary of how this report aligns to the H&F Values Being All capital investment decisions are required to be underpinned ruthlessly by a robust business plan that sets out the full costs and risks financially and any expected financial return alongside the broader efficient outcomes including economic and social benefits. Officers are responsible for monitoring and delivering projects within approved budgets and reporting variances.

This report provides detailed analysis of the Council’s capital programme financial position and highlights any potential risks and their impact on the Council’s resources.

Financial Impact

This report is wholly of a financial nature.

Budget Council approved a four- year capital programme for 2022/23 to 2025/26 of £577.1m. The programme now stands at £695.6m. The increase of £118.5m is mainly due to:  the carry forward of unspent budgets of £42.8m from 2021/22 to future years  the inclusion of a budget, as agreed by July 2022 Council, of £58.6m for the Hartopp and Lannoy development.  inclusion of a budget, as agreed by July 2022 Council, of £7.5m for progression and delivery of LBHF’s development gateway 2 and 3 for Barclay Close, Jepson House, Becklow Gardens and the Grange sites  inclusion of £5m of a budget, as per agreed TfL and s106 funding, for various infrastructure and transport schemes  Other variations of £4.6m as detailed in Appendix 2.

The economic outlook is uncertain with supply constraints and labour shortages, driven by the war in Ukraine, Covid and Brexit, leading to higher prices for works and materials and pressure on wages. The September inflation rate, as measured by the Consumer Price Index, is 10.1% with the Bank of England (BoE) forecasting that it will peak at just under 11% in the last 3 months of 2022. The BoE expect it to remain at very elevated levels throughout much of 2023, before falling to 2% two years ahead. As part of their policy response to the increase in inflation the BoE have increased the interest base rate to 3% with further increases likely. The upturn in inflation represents a significant financial risk to the capital programme as it impacts on budgeted costs, contractor performance, potential receipts and scheme viabilities. This risk needs to be kept under review with mitigating actions taken as necessary.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitor & Budget Variations, 2022/23 (Second Quarter)Report 571 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 12 attended
SC
Councillor Stephen CowanChair, present
BC
Councillor Ben ColemanCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
SH
Councillor Sharon HolderCommittee Member, present
RH
Councillor Rebecca HarveyCommittee Member, present
BK
Councillor Bora KwonCommittee Member, present
RR
Councillor Rowan ReeCommittee Member, present
AS
Councillor Alex SandersonCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present
VB
Councillor Victoria Brocklebank-FowlerOther Attendee, present
PQ
Councillor Patricia QuigleyOther Attendee, present

On this subject at Hammersmith & Fulham

Search all
  1. Capital Programme Monitor & Budget Variations, 2022/23 (Second Quarter)This decision
  2. Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)Noted
  3. Capital Programme Outturn 2025/26Noted
  4. Capital Programme Monitor and Budget Variations 2025/26 (Quarter 3)Noted
  5. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  6. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies