London Borough of Hammersmith & Fulham
Cabinet, Monday 16 October 2023 at 7.00pm

Capital Programme Monitor & Budget Variations, 2023/24 (First Quarter)

Noted Executive 1 paper

Cabinet noted this item on Monday 16 October 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

To note the net increase in forecast capital expenditure of £10.7m for 2023/24. 2. To approve the updated four-year capital programme for 2023-2027 of £653m as detailed in Appendix 1. 3. To approve £4,890,000 additional budget with regards to Hammersmith Bridge stabilisation works, funded from General Fund borrowing. 4. To approve £3,389,000 additional budget for Clean Air Neighbourhoods scheme, funded from Transport for London (TfL), Section 106 and parking reserve contributions. 5. To approve £176,000 additional budget in relation to Business Intelligence (BI) development work, funded from General Fund borrowing. 6. To approve the additional budget in relation to the self-financing schemes as noted in Appendix 4. 7. To note the potential risks regarding the General Fund Programme, as summarised in paragraphs 18-23. 8. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 24-28. 9. To note prudential indicators presented in Appendix 5, as per Prudential Code requirements.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitor & Budget Variations, 2023/24 (First Quarter)Report 494 KB Copy on its way

At this meeting

Whole meeting

On this subject at Hammersmith & Fulham

Search all
  1. Capital Programme Monitor & Budget Variations, 2023/24 (First Quarter)This decision
  2. Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)Noted
  3. Capital Programme Outturn 2025/26Noted
  4. Capital Programme Monitor and Budget Variations 2025/26 (Quarter 3)Noted
  5. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  6. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies