To note the net increase in forecast capital expenditure of £4.9m for 2023/24. 2. To approve the updated four-year capital programme for 2023-2027 of £706.7m as detailed in Appendix 1. 3. To approve £16.984m additional pre-financing with regards to Hammersmith Bridge stabilisation (£7.927m) and pre-restoration (£9.057m) works, funded from the General Fund borrowing. Much of this will be reclaimed from TfL and Government. 4. To approve £0.5m additional budget with regards to Mund Street refurbishment costs, funded from the General Fund borrowing. 5. To approve £0.54m additional budget for Avonmore predevelopment costs, funded from the General Fund borrowing. 6. To note the potential risks regarding the General Fund Programme, as summarised in paragraphs 25-29. 7. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 30-33. 8. To note prudential indicators presented in Appendix 5, as per Prudential Code requirements.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
The Council’s overall financial strategy includes significant capital investment in the infrastructure of the Borough and this in turn supports the delivery of the Council’s key priorities and strategies e.g. Building Homes & Communities.
All capital programmes are complex and involve considerable local community engagement, procurement, and planning considerations. The forecast capital budget for 2023/24, as at third quarter, is £232.2m and includes:
£61.3m investment in the existing council homes to ensure compliance and building affordable new homes for residents £28.3m investment in provision of new affordable housing £19.2m pre-financing of works to ensure the continuing safety of Hammersmith Bridge and progressing the stabilisation works. Much of this will be reclaimed from TfL and the Government. £10.5m investment in road maintenance and infrastructure schemes including £4.9m investment in waste collection and disposal equipment and £3m in Clean Air Neighbourhoods scheme as part of our Climate and Ecology Strategy £5.4m divestment in local supported housing £4.5m investment in civic accommodation including decarbonisation initiatives £4.2m investment in maintaining schools including £0.4m investment on window replacement and decarbonisation schemes £3.3m investment in social care capital projects including disabled facilities adaptations works £2.3m investment in parks, leisure, and community safety
Work is also continuing to complete the Civic Campus development that will re-open the historic town hall to the public and regenerate an important part of the Borough, providing a vibrant entertainment, arts, business, education, and social destination featuring world-class architecture.
The details of the capital programme for the financial year 2023/24 (including the financing of this spend) and the future programme are set out in the report. RECOMMENDATIONS
1. To note the net increase in forecast capital expenditure of £4.9m for 2023/24.
2. To approve the updated four-year capital programme for 2023-2027 of £706.7m as detailed in Appendix 1.
3. To approve £16.984m additional pre-financing with regards to Hammersmith Bridge stabilisation (£7.927m) and pre-restoration (£9.057m) works, funded from the General Fund borrowing. Much of this will be reclaimed from TfL and Government.
4. To approve £0.5m additional budget with regards to Mund Street refurbishment costs, funded from the General Fund borrowing.
5. To approve £0.54m additional budget for Avonmore predevelopment costs, funded from the General Fund borrowing.
6. To note the potential risks regarding the General Fund Programme, as summarised in paragraphs 25-29.
7. To note the potential risks regarding the Housing Capital Programme, as summarised in paragraphs 30-33.
8. To note prudential indicators presented in Appendix 5, as per Prudential Code requirements.
Wards Affected: All
The capital programme contains schemes and projects which are directly linked to the Council’s priorities.
Our Values Summary of how this report aligns to the H&F Values Being ruthlessly financially All capital investment decisions are required to be efficient underpinned by a robust business case that sets out the full costs, funding and risks and any expected financial return alongside the broader outcomes including economic and social benefits.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.