London Borough of Hammersmith & Fulham
Cabinet, Monday 13 October 2025 at 7.00pm

Capital Programme Monitor and Budget Variations 2025/26 (Quarter 1)

Noted Executive 1 paper

AI summaryCabinet approved an updated £679.8m four-year capital programme for 2025-2029, including £105.2m of new investment funded partly by borrowing. The 2025/26 forecast spend is £280.7m, up £13.4m on the £267.3m revised budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFour-year programme 2025-2029 set at £679.8m
Money£679.8mTotal four-year capital programme to 2028/29
What happens nextFurther monitoringBudget variations to be reported in later quarters
Who it affectsAll wardsBorough-wide capital investment programme

What was decided

Cabinet noted the £280.7m forecast for 2025/26 capital expenditure, a net rise of £13.4m on the £267.3m revised budget set at 2024/25 outturn. Report P7

Cabinet approved £105.2m of additional investment across the revised four-year programme, including new borrowing, with detail in Appendix 1. Report P8, P68

Cabinet approved the updated £679.8m four-year capital programme for 2025-2029, a net increase of £105.2m on the £574.6m forecast at 2024/25 outturn. Report P9, P32

Why

The programme supports the Corporate Plan priorities, including affordable housing, transport infrastructure, public realm, school maintenance, CCTV and the Civic Campus regeneration. Report P1, P2, P3, P5

Each capital investment must be backed by a business case covering cost, funding, risk and broader economic and social benefits. Report P12

The report aligns with the council's values of being financially efficient, building shared prosperity, creating a compassionate council and addressing the climate and ecological emergency. Report P13

What happens next

Finance officers will continue to monitor the capital programme and report further variations in later quarters of 2025/26. Report P21, P37

Departments will work with finance to manage VAT partial exemption risk on capital projects, which could cost over £3m per year if breached. Report P64

Further borrowing needed for the programme will be considered alongside the revenue budget and medium-term financial strategy. Report P16, P39, P40

The money

  • £280.7m Forecast 2025/26 capital expenditure Report P7, P25
  • £267.3m Revised 2025/26 capital budget at 2024/25 outturn Report P7, P25
  • £13.4m Net increase in 2025/26 forecast over revised budget Report P7, P27
  • £105.2m Total additional investment across the four-year programme Report P8, P32, P68
  • £679.8m Updated four-year capital programme for 2025-2029 Report P9, P32, P34
  • £574.6m Forecast four-year programme as at outturn 2024/25 Report P9, P32
  • £949m Forecast CFR at end of 2025/26 Report P47
  • £1.16bn Forecast CFR at end of 2028/29 Report P47

Options considered

  • Chosen: Note the £280.7m 2025/26 forecast and £13.4m increase over the revised budget. Reflects updated programme position at quarter one Report P7
  • Chosen: Approve £105.2m of additional investment including new borrowing. Fund new projects such as Avonmore Redevelopment, CCTV and highways schemes Report P8, P30, P68
  • Chosen: Approve the updated £679.8m four-year capital programme for 2025-2029. Reflects new additions and rephasing across the four-year period Report P9, P32

Implications

  • Financial: Borrowing-funded additions will increase the council's Capital Financing Requirement and need to be considered alongside the revenue budget and medium-term financial strategy. Report P16, P39, P40, P47
  • Risk: Risks identified include slower housing development sales, lower Right to Buy receipts, the Civic Campus scheme, cost inflation, and high interest rates on borrowing. Report P49, P50, P51, P52, P53
  • Financial: VAT partial exemption risk on capital projects could cost the council over £3m per year if breached. Report P64
  • Legal: No direct legal implications; legal advice will be sought on individual procurections, with compliance with Contract Standing Orders and Financial Regulations. Report P18
  • Equalities: No direct equalities implications; recommendations do not directly affect groups with protected characteristics under the Equality Act 2010. Report P54
  • Climate: Investments support the council's Climate and Ecology Strategy and net zero borough target by 2030, including decarbonisation and public realm works. Report P13, P5
  • Other: Procurements must comply with Construction (Design and Management) Regulations and the Building Safety Act 2022 requirements. Report P58, P59, P60

Who and where

  • All wards across the borough Report P10
  • Council tenants and housing applicants through new affordable housing and refurbishment Report P3, P5, P33
  • School pupils through maintenance, decarbonisation and SEN sufficiency schemes Report P5, P30, P70
  • Disabled and vulnerable residents through aids, adaptations and Disabled Facilities Grant Report P5, P30, P70
  • Road users and residents through transport and public realm improvements Report P5, P30, P70
  • Council contractors and suppliers delivering capital works Report P18, P55

Timeline

  • 2025/26: Forecast capital spend of £280.7m Report P7, P25

Plain English for the jargon

  • Capital Financing Requirement (CFR): The council's outstanding debt for borrowing used to fund capital programmes.
  • Minimum Revenue Provision (MRP): The amount local authorities must set aside each year from revenue to repay outstanding capital debt.
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending.
  • Section 106 / CIL: Planning obligations and Community Infrastructure Levy paid by developers to fund local infrastructure.
  • Avonmore Redevelopment: Approved project to redevelop Avonmore Primary School with new homes, approved at Full Council on 21 May 2025.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

That Cabinet noted the overall forecast of £280.7m for 2025/26 capital expenditure which is a net increase of £13.4m in comparison to the revised budget of £267.3m at 2024/25 outturn. That Cabinet approved a total additional investment of £105.2m across the revised four year programme, including new additional borrowing, the details of this investment are set out in Appendix 1. That Cabinet approved the updated four-year capital programme for 2025-2029 of £679.8m, as detailed in the report. This is a net increase of £105.2m in comparison to the forecast four-year programme as at outturn 2024/25 (£574.6m).
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

The Council’s Corporate Plan for 2023-26 sets out the Council’s strategy for delivering on the ambitions and vision to transform its services and spend and invest money to help protect high quality essential services for its residents.

A key value is Building Shared Prosperity, and the Council’s overall financial strategy includes significant capital investment in the infrastructure of the Borough and this in turn supports the delivery of the Council’s key priorities and strategies. These are:

• build a better future for children and young people • foster inclusive, sustainable economic growth for everyone • build more affordable, accessible, safe and sustainable housing • deliver high quality housing services • Ensuring our borough is a safer, stronger, kinder borough to live in, work and visit through expansion of our CCTV infrastructure to prevent and deter crime.

All capital programmes are complex and involve considerable local community engagement, procurement, and planning considerations. The 2025/26 capital programme is forecast to spend £280.7m as at quarter one. Some major areas of spend major areas of spend with the 2025/26 budget is:

• £86.3m maintaining the existing council homes to ensure compliance and building affordable new homes for residents; • £75m investment in acquiring and building new affordable housing and supported accommodation in the Borough; • £14.7m investment in transport infrastructure; • £14.4m spend on public realm and protection and climate change initiatives; • £4.6m investment in school maintenance and decarbonisation schemes and SEN sufficiency provision; • £3.4m ensuring the safety of Hammersmith Bridge and progressing the stabilisation work; and • £1m investment in disabled facilities adaptation works and social care capital projects. Work is also continuing to complete the Civic Campus development that will re-open the iconic town hall to the public, which will rejuvenate and regenerate an important part of the Borough, providing a vibrant entertainment, arts, business, education, and social destination featuring world-class architecture.

The details of the forecast capital programme for the financial year 2025/26 (including the financing of the programme for the year) and the future years are set out in the report.

Recommendations

1. To note the overall forecast of £280.7m for 2025/26 capital expenditure which is a net increase of £13.4m in comparison to the revised budget of £267.3m at 2024/25 outturn.

2. To approve a total additional investment of £105.2m across the revised four year programme, including new additional borrowing, the details of this investment are set out in Appendix 1

3. To approve the updated four-year capital programme for 2025-2029 of £679.8m, as detailed in the report. This is a net increase of £105.2m in comparison to the forecast four-year programme as at outturn 2024/25 (£574.6m).

Wards Affected: All

The capital programme contains schemes and projects which are directly linked to the Council’s priorities.

Our Values Summary of how this report aligns to the H&F Values Being ruthlessly financially All capital investment decisions are required to efficient be underpinned by a robust business case that sets out the full costs, funding and risks and any expected financial return alongside the broader outcomes including economic and social benefits.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitor and Budget Variations 2025/26 (Quarter 1)Report 422 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SC
Councillor Stephen CowanChair, present
AS
Councillor Alex SandersonCommittee Member, present
FC
Councillor Florian Chevoppe-VerdierCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
RH
Councillor Rebecca HarveyCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
BK
Councillor Bora KwonCommittee Member, apologies
ZQ
Councillor Zarar QayyumCommittee Member, present
RR
Councillor Rowan ReeCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present

On this subject at Hammersmith & Fulham

Search all
  1. Capital Programme Monitor and Budget Variations 2025/26 (Quarter 1)This decision
  2. Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)Noted
  3. Capital Programme Outturn 2025/26Noted
  4. Capital Programme Monitor and Budget Variations 2025/26 (Quarter 3)Noted
  5. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  6. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open