Barclay Close, London SW6 5QG, Walham Green, 2025/02125/FR3
DecidedPlanning1 paper
AI summaryHammersmith and Fulham Planning Committee authorises the council itself, as applicant, to redevelop a car park at Barclay Close with three new affordable three-storey houses, subject to 31 conditions and a legal agreement.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedDirector of Planning authorised to grant, subject to legal document and conditions
MoneyNot stated
What happens nextNot stated
Who it affectsNot stated
What was decided
The committee resolved to authorise the Director of Planning and Property to grant permission on completion of a satisfactory legal document and subject to the 31 listed conditions. Report P5, P75
The application is a Regulation 3 scheme where the London Borough of Hammersmith and Fulham is itself the developer, proposing three three-storey single family dwellinghouses with associated parking, access, landscaping, public realm and dropped kerb removal. Report P5, 3.1, 3.2
All three units will be affordable, with one for social rent and two for shared ownership, each having four bedrooms, with all built to M4(2) accessible and adaptable standard. Report 3.2, 6.7, 6.23, 6.24
Why
Officers concluded the scheme makes efficient use of a small 0.107 hectare site near Fulham Broadway and Parsons Green, is of high quality design that does not harm nearby Conservation Areas, and would not unacceptably harm neighbours' amenity subject to conditions. Report 1.1, P75, P76, 6.5
All units exceed London Plan space standards, with two 4-bed 6-person units at 120.3 sqm and one 4-bed 7-person unit at 137.7 sqm, and 86 percent of assessed rooms meet the BRE daylight target. Report P160, 6.14, 6.16
Although there is no policy requirement for affordable housing on a three-unit scheme, the report says providing 100 percent affordable family-sized homes is a significant benefit in meeting identified borough housing need. Report 6.9, 6.10, 6.11, 4.19
What happens next
A satisfactory legal document must be completed, with the new development to be secured as car-free so future occupiers cannot apply for parking permits. Report P5
Pre-commencement and pre-occupation conditions require submission and approval of matters including materials, air quality and dust management plans, a ventilation strategy, land contamination assessments, a drainage strategy, a Construction Logistics Plan, a Construction Management Plan, a Biodiversity Gain Plan and a Habitat Management and Monitoring Plan. Report P9, P14, P17, P32, P33, P35, P37, P38, P40, P48, P52, P56, P66, P70
Habitat creation and enhancement works under the Biodiversity Gain Plan must be completed before occupation, with monitoring reports submitted for 30 years after completion, and the development must begin within three years of the permission. Report P6, P68, P73, P74
Options considered
Chosen: Grant planning permission subject to conditions and a legal agreement (officer recommendation). Scheme complies with the NPPF, London Plan, Local Plan and Planning Guidance SPD on housing, design, amenity, transport, energy, flood risk, air quality and land contamination, and would contribute to affordable family housing supply. Report P5, P76
Rejected: Refuse the application. No reasons were identified in the report that would justify refusal; design, amenity, highways, contamination, flooding and air quality matters are addressed by conditions. Report P76, 6.1, P140
Implications
Environment and climate: The development is in Flood Zone 3 and the borough-wide Air Quality Management Area, requiring a Drainage Strategy limiting surface water discharge to no more than 2.5 litres per second for storm events up to 1 in 100 years plus 40 percent climate change, an Air Quality Dust Management Plan, a Ventilation Strategy with NO2 and PM filtration, Air Source Heat Pumps and rooftop PV panels. Report 1.4, P14, P15, P17, P20, P24, P26, P56, P57
Legal: Potentially contaminative past or present land uses are understood to be at or near the site, requiring staged preliminary risk assessment, site investigation, quantitative risk assessment, remediation method statement, verification report and possible long-term monitoring before commencement. Report P32, P33, P35, P37, P38, P40
Equalities: All three houses will be built to Building Regulations M4(2) accessible and adaptable standard, with level thresholds, generous circulation space and ground-floor WCs capable of future adaptation, although full M4(3) wheelchair compliance is not feasible on the site. Report 3.2, 6.23, 6.24
Other: A Biodiversity Gain Plan and Habitat Management and Monitoring Plan are required to deliver at least 10 percent biodiversity net gain, with habitat creation and enhancement completed before occupation and maintained for 30 years. Report P66, P68, P70, P73, P74
Other: The development will be secured as car-free via a legal agreement, with the new parking provided on site including a blue badge space, secure cycle storage and an electric vehicle charging point of at least 7 kW. Report P41, P43, P64
Who and where
Existing residents of the Barclay Close estate and 17 objectors from 10 nearby addresses Report P82, 4.7, 4.8, P108, P109, P110, P111, P112
Future occupiers of the three new affordable family houses Report 3.1, 3.2, P75
Existing users of the 12-space tarmacked car park on the site, which will be redeveloped Report 1.1, P108
Neighbouring properties including the Mission Hall and Fulham Court, where impacts on light, outlook, privacy and construction disturbance were raised Report 1.2, P110, P111, 4.10, 4.13
Timeline
4th August 2025: Application form received Report P78
21.08.25, 19.08.25, 26.08.25, 28.08.25: Consultation responses from Environment Agency, Historic England, Transport for London and Historic England Report P80, 4.3, 4.4, 4.5
17.09.25 to 10.10.25: 17 objection letters received from 10 separate addresses during neighbour consultation Report P82, 4.7, 4.8
20.01.2026: Planning and Development Control Committee resolves to authorise grant of permission subject to conditions and legal agreement Report P5
Within 3 years of permission: Development must commence, otherwise permission expires under standard section 91(1)(a) TCPA 1990 condition Report P6, P7
For 30 years after completion of development: Created and enhanced habitats under the approved Biodiversity Gain Plan and Habitat Management and Monitoring Plan must be managed, maintained and monitored Report P68, P74
Plain English for the jargon
Regulation 3 application: A planning application made by a local authority for development on its own land, decided by its own planning committee.
PTAL 4: Public Transport Accessibility Level 4 on a 0 to 6b scale, indicating good access to public transport, here within 400m of Fulham Broadway and Parsons Green District Line stations.
M4(2) and M4(3): Building Regulations accessibility standards: M4(2) for accessible and adaptable dwellings, M4(3) for wheelchair user dwellings.
Biodiversity Net Gain: A requirement under Schedule 7A of the Town and Country Planning Act 1990 for developments to deliver at least a 10 percent increase in biodiversity value, maintained for at least 30 years.
Air Quality Management Area (AQMA): An area designated by a local authority where air quality objectives are not being met, requiring mitigation for new development.
CIL: Community Infrastructure Levy, a charge on new development to fund local infrastructure, listed as a material consideration.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
RESOLVED That the Director of Planning and Property be authorised to grant permission upon the completion of a satisfactory legal document and subject to the conditions listed in the report. That the Director of Planning and Property, after consultation with the Assistant Director of Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Heads of Terms of the legal document or proposed conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Reg. No: Case Officer: 2025/02125/FR3 Tom Scriven Date Valid: Conservation Area: 14.08.2025 Committee Date: 20.01.2026 Applicant: London Borough Of Hammersmith And Fulham C/O Agent Description: Redevelopment of the site comprising the erection of 3no. three storey single family dwellinghouses, with associated parking, access and servicing, landscape, public realm, removal of dropped kerb and associated works. Drg Nos: Application Type: Full Regulation 3 - LBHF is Developer Officer Recommendation: That the Committee resolve that the Director of Planning and Property be authorised to grant permission upon the completion of a satisfactory legal agreement and subject to the conditions listed below; That the Committee resolve that the Director of Planning and Property, after consultation with the Assistant Director of Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Heads of Terms of the legal agreement or conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion. Conditions:
1) The development hereby permitted shall not commence later than the expiration of 3 years beginning with the date of this planning permission.
Condition required to be imposed by section 91(1)(a) of the Town and Country Planning Act 1990 (as amended by section 51 of the Planning and Compulsory Purchase Act 2004).
2) The development hereby permitted shall be carried out in complete accordance with the following approved drawing numbers, other than where those details are altered pursuant to the conditions of this planning permission: Landscape Ground Floor GA BAR-PRP-ZZ-00-DG-L-02000 Rev P01 Landscape Ground Floor GA BAR-RP-ZZ-00-DG-L-02010 Rev P01 Proposed Site Plan BAR-PRP-ZZ-ZZ-DG-A-08302 Rev P01 Proposed Ground Floor BAR-PRP-ZZ-00-DG-A-08000 Rev P02 Proposed First Floor BAR-PRP-ZZ-01-DG-A-08001 REV P02 Proposed Second Floor BAR-PRP-ZZ-01-DG-A-08002 REV P02 Proposed Elevations BAR-PRP-ZZ-ZZ-DG-A-08100 REV P05 Proposed Site Sections BAR-PRP-ZZ-ZZ-DG-A-08210 REV P02 Proposed Sections BAR-PRP-ZZ-ZZ-DG-A-08220 REV P02 To ensure full compliance with the planning application hereby approved and to prevent harm arising through deviations from the approved plans.
3) Prior to commencement of the relevant part of the works, details of the external facing materials (including manufacturer's specifications, photographs and/ or a physical sample) shall be submitted to, and approved in writing by the Council.
The development shall be carried out and completed in accordance with the approved details. The development shall be permanently retained in accordance with the approved details.
To ensure a satisfactory external appearance, in accordance with Policies DC1, DC4 and DC8 of the Local Plan (2018).
4) The development hereby approved shall be carried out in accordance with the approved Arboricultural Impact Assessment Report (Ref:SHA 1709) and in particular the Tree Protection Plan set out in Appendix 3 of the document. The tree protection measures shall be carried out in full for the duration of the construction works.
To ensure that retained trees are suitably protected and to prevent harm during the course of construction, in accordance with Policies DC1, DC8, OS2 and OS5 of the Local Plan 2018.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Development Control Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.