Revenue Outturn Report 2025/26

Noted Executive 1 paper

AI summaryHammersmith & Fulham Cabinet noted the 2025/26 outturn, with a General Fund underspend of £0.375m and a Housing Revenue Account underspend of £0.6m, both transferred to general balances. The Dedicated Schools Grant High Needs Block cumulative deficit stood at £0.301m after planned mitigations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThree items noted: underspends and DSG deficit
Money£0.375m GF, £0.6m HRABoth transferred to general balances
What happens nextProvisional, subject to auditHigh Needs Stability Grant confirmation in Autumn 2026
Who it affectsAll wardsCouncil-wide revenue position

What was decided

Noted the General Fund underspend of £0.375m and the Housing Revenue Account underspend of £0.6m for 2025/26. Report P10

Noted transfer of the net underspend balances for both the General Fund and the Housing Revenue Account to their respective general balances. Report P10

Noted the increase of the Dedicated Schools Grant High Needs Block deficit and the remaining cumulative deficit of £0.301m. Report P10, P30

Why

The council remained within its overall budget despite continued cost pressures in adult social care, children's services and temporary accommodation, using budgeted central contingencies and prior year collection fund surpluses to mitigate emerging service pressures. Report P3, P4, P6

HRA general balances rose to £6.486m, above the council's minimum target of £5m, strengthening financial resilience. Report P7, P26

What happens next

The outturn position is provisional and remains subject to external audit, with business rate entries to be finalised by the end of June in line with the government timetable. Report P9, P35, P39

The Department for Education is expected to confirm potential significant extra funding through the High Needs Stability Grant in Autumn 2026 to address the retained DSG deficit. Report P28

The money

  • £0.375m General Fund underspend for 2025/26, transferred to general balances Report P1, P10, P21
  • £0.6m Housing Revenue Account underspend, transferred to HRA general balances Report P1, P10, P25
  • £0.301m Remaining cumulative deficit on the DSG High Needs Block after stability grant coverage Report P10, P30
  • £7.882m Cumulative DSG deficit on the balance sheet at end of 2025/26 Report P28, P30
  • £7.581m DSG stability grant coverage anticipated Report P30
  • £5.787m DSG High Needs overspend after mitigations in 2025/26 Report P30
  • £6.486m HRA general balance as of 31 March 2026 Report P26
  • £14.6m Increase in General Fund balances and earmarked reserves during 2025/26 Report P33, P34
  • £6.0m Planned spending from General Fund earmarked reserves in 2025/26 (6.9%) Report P8
  • £10.3m Provision for inflation pressures in the 2025/26 budget Report P5
  • £12.3m Provision for service growth in the 2025/26 budget Report P5
  • £5.127m Original savings programme target for 2025/26 Report P24

Options considered

  • Chosen: Note outturn and transfer underspends to general balances. Standard year end process to strengthen financial resilience Report P7, P10

Implications

  • Financial: HRA general balance closed the year at £6.486m, above the council's £5m minimum target and considered reasonable by external auditors. Report P7, P26
  • Financial: Savings delivery was 83.2% of target, with Finance and Corporate Services achieving 60.3% and an organisational review of senior chief officer structures deferred to 2026/27. Report P24, P69
  • Equalities: No direct negative impact on groups with protected characteristics is anticipated from the budget adjustments in this report. Report P36
  • Risk: Underlying overspends remain in demand-led services, with ongoing risks from rising costs, demographic change and continued cost of living pressures. Report P6, P38, P39
  • Legal: There are no legal implications arising from this report. Report P16
  • Other: Additional costs of £0.362m in Corporate Services related to the cyber security incident in November 2025. Report P62

Who and where

  • All wards within the London Borough of Hammersmith and Fulham Report P11
  • Adults receiving social care, particularly those with learning disabilities, mental health needs and physical support needs Report P48, P49
  • Children looked after, care leavers and children with special educational needs and disabilities Report P42, P45
  • Households in temporary accommodation and homelessness prevention services Report P54
  • Council tenants and leaseholders on the Housing Revenue Account Report P66
  • Maintained schools, with a £0.396m deficit on their in-year position Report P45

Timeline

  • 2025/26: Financial year covered by the outturn report Report P1
  • 26th May 2026: Report prepared by James Newman, Assistant Director Finance and Deputy s151 officer Report P15
  • End of June 2026: Government timetable for finalisation of business rate entries Report P39
  • 3rd June 2026: Legal implications verified by Glen Egan, Assistant Director Legal Services Report P17
  • 4th June 2026: Risk implications certified by Jules Binney, Risk and Assurance Manager Report P39
  • 6th July 2026: Cabinet meeting at which the outturn was noted
  • Autumn 2026: Department for Education expected to confirm High Needs Stability Grant funding to address retained DSG deficit Report P28

Plain English for the jargon

  • General Fund: The main council fund for day to day services, funded by council tax, business rates and government grants.
  • Housing Revenue Account (HRA): A separate ringfenced account for income and spending on council housing.
  • Dedicated Schools Grant (DSG): Government funding for schools, split into Schools Block, Early Years Block and High Needs Block.
  • High Needs Block: DSG funding for pupils with special educational needs and disabilities, often overspent due to rising demand.
  • General balances: Unallocated reserves held to manage financial risk and unexpected costs.
  • Earmarked reserves: Reserves set aside for specific planned projects or one off spending.
  • DSG safety valve: A recovery plan agreed with the Department for Education to clear accumulated High Needs Block deficits.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED To note the General Fund underspend of £0.375m, and an underspend of £0.6m on the Housing Revenue Account for 2025/26. To note the transfer of the net underspend balances for both the General Fund and Housing Revenue Account to their respective general balances (as set out in paragraph 3 and 6 of the report). To note the increase of the Dedicated Schools Grant High Needs Block deficit and the remaining cumulative deficit of £0.301m.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

This report sets out the revenue outturn position for the Council across the General Fund and Housing Revenue Account (HRA) for the 2025/26 financial year. Overall, the council has been able to deliver underspends for both the General Fund (£0.375m) and the HRA (£0.6m) which will contribute towards general balances and improve financial resilience in the medium term.

At a time when councils across the country are taking money out of reserves to balance the books, it is proof of the ruthless financial efficiency with which Hammersmith and Fulham Council is run that we are adding an extra £0.4m to general balance reserves.

The strategic operating environment in 2025/26 continued to be a challenging one although there were signs of recovery with inflation falling close to the 2% target by the Bank of England, and interest rates slowly reducing. There continued to be cost pressures arising from sustained and elevated demand, legislative changes and acuity of need. These pressures have been experienced across core statutory services in the People Dept (Adult Social Care and Children’s Services) and Housing Solutions (temporary accommodation). This has been worsened by the needs of an ageing population and the ongoing cost of living crisis.

Despite these challenges, the council remained within its budget, utilising budgeted central contingencies to mitigate emerging service pressures and prior year collection fund surpluses.

The Council’s budget for 2025/26 was set with the following priorities: • preserve front line services valued by residents/businesses/visitors • ensure the continued delivery of key council priorities (e.g. free home care, weekly collection of waste) • increase investment in services including fly tipping, food waste collection, continuation of free school breakfasts, temporary accommodation, care packages for disabled children and family hubs and measures for supporting residents during the cost-of-living crisis and through the Council Tax Support Scheme • maintain the financial resilience of the council (and thus the continued provision of services in the future) There was provision for inflation pressures of £10.3m plus provision for growth of £12.3m in services (including Homelessness prevention, Adult Social Care, Children and Young People’s services and waste collection).

Although a net underspend has been delivered, underlying overspends remain, especially in front line and demand led services due to demographic change and the long term national economic conditions. Whilst provision for growth and inflation has been included in many of these budgets for 2025/26, there remain significant ongoing risks of rising costs and demand and complexity of that demand that will need to be managed to achieve a balanced outturn for 2025/26.

The provisional HRA outturn will contribute a further £0.6m to HRA general balances and thereby resulting in balances of £6.5m at the year-end on the HRA (the Council aims towards a minimum target of £5m). This level of general balances is considered reasonable by our external auditors given the overall levels of income and expenditure on the HRA.

The Council carried out planned spending of £6.0m from General Fund earmarked reserves (6.9%) in 2025/26. This is money set aside in previous years specifically for one-off expenditure on particular projects or programmes which have no direct impact on day-to-day expenditure and has already been factored into the Council’s financial strategy.

The outturn position is provisional and is subject to audit. The review continues of the balance sheet and final entries cannot yet be confirmed for business rates.

Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revenue Outturn Report 2025/26Report 395 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
SC
Councillor Stephen CowanChair, present
AS
Councillor Alex SandersonCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, apologies
RR
Councillor Rowan ReeCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present
BK
Councillor Bora KwonCommittee Member, apologies
HB
Councillor Hannah BulmerCommittee Member, present
LH
Councillor Lisa HomanCommittee Member, present
ZQ
Councillor Zarar QayyumCommittee Member, present
NT
Councillor Nicole TrehyCommittee Member, present

On this subject at Hammersmith & Fulham

Search all
  1. Revenue Outturn Report 2025/26This decision
  2. Revenue Outturn Report 2024/25Noted
  3. Provisional Revenue Outturn Report 2023/24Noted
  4. Provisional Revenue Outturn Report 2022/23Noted
  5. 2021/22 Provisional Revenue Outturn ReportAgreed
  6. 2019/20 General Fund Revenue Outturn ReportAgreed

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies