River Hamble Harbour Management Committee, Friday 8 June 2018 at 10.00am

Harbour Works Consent Application – Swanwick Shore Road Car Park River Wall Replacement

Approved Committee 4 papers

River Hamble Harbour Management Committee approved this item on Friday 8 June 2018. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

That the River Hamble Harbour Management Committee recommends to River Hamble Harbour Board that it grants Harbour Works Consent for the proposal set out in Section 4 of this report and subject to the following conditions: a. That the proposal to the sea wall be built in accordance with the details, plans and method set out in Appendix 1a and Appendix 1b. b. That the method statement is to be submitted to and approved by the Harbour Master in advance of construction. c. That the applicant should ensure that only coatings and treatments that are suitable for use in the marine environment are used in accordance with best environmental practice. That all reasonable precautions will be undertaken to ensure no pollutants enter the waterbody. d. That all equipment, temporary structures, waste and/or debris associated with the activities is to be removed upon completion of the works. e. That the development must be completed within 3 years from the date of the approval granted by the Harbour Board.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to River Hamble Harbour Management Committee

MP269.7-FN-03 Swanwick Shore Road Car Park

MARINA PROJECTS LTD: FILE NOTE Premier Marinas Ltd Swanwick Shore Road Car Park Refurbishment Revision 01 – 05/04/2018

1. INTRODUCTION

Premier Marinas Ltd are responsible for the upkeep and maintenance of the Swanwick Shore Road Car Park, found to the East of Swanwick Marina and as shown in Figure 1.

Figure 1 - Swanwick Shore Road Car Park

The car park is of relatively simple layout, comprising marked spaced on a tarmac area, with an informal tender storage area at the Western End. The car park plays an important part in servicing use of the adjacent slipway that is popular for a number of different river users.

The frontage of the car park has, to all intents and purposes failed through age, where the frontage no longer retains or protects the material from the action of the tide – fine material is lost through the wall/revetment with significant voids appearing underneath the tarmac.

Premier Marinas therefore propose to address the car park frontage and complete a low- key refresh of the car park area to make it more appealing and in keeping with the

1 MP269.7-FN-03 Swanwick Shore Road Car Park

surroundings. Better regulation of the parking spaces and dinghy/tender storage will improve usability.

2. PROPOSED WORKS

Premier Marinas propose to conduct work on the car park in accordance with the drawing attached in support of this application, Hamill Davies Drawing 14-2310-102.

Within this drawing there are three main areas of work;

▪ Removal of all of the existing frontage structure and its replacement with gabions (wired cages), filled will inert clean material (such as Maccarferri stone – Figure 2) and backed by a geotextile membrane to protect the car park from tidal scour. Within the top of the gabions a continuous bench rail set on square posts cut from reclaimed timber piles will be installed. During the excavation of the existing frontage and placement of the gabions the voids will be backfilled with type 6N granular material which is retained by the membrane. ▪ Once the gabions are filled and the voids backfilled the existing surface will be scarified and resurfaced with a tarmac overlay, with lines repainted. It is proposed that 1x disabled space is marked within the hatched access area. ▪ The dinghy park area will be tidied up and block paving installed to provide a formalised dingy storage area. This dinghy park will be surrounded by key clamp low level railing to which tenders can be locked. It is proposed that the existing anchor feature is retained and placed on the boundary of car park and dinghy area as an interest feature.

3. METHODOLOGY

Whilst detailed methodology will be confirmed once a contractor is appointed post consenting Premier Marinas will ensure that all works will be conducted from the land without the need to access or utilise the foreshore for access by mechanical plant. The existing frontage will require excavation, with debris removed from site for disposal or recycling as appropriate. A levelled grade will be created through a thin layer of graded stone on which to commence the new wall construction.

Gabions will arrive empty, before they are placed, wired together and then filled appropriately with material following best practice guidelines and manufacturer’s instructions. The void behind the wall be filled and material compacted in layers as the wall is increased in height.

2 MP269.7-FN-03 Swanwick Shore Road Car Park

As the gabions are filled the reclaimed timber posts can be set into them, after which the bench rail can be secured. With the gabions and geotextile in place the excavated area behind will be backfilled to meet existing material before the surface is scarified and new tarmac placed between the new edging stones.

It is proposed that works will take place during standard 8am – 8pm hours, with an estimated duration of 2 weeks.

4. IMPACTS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendeix 1aReport 234 KB DownloadRead as text
PDF
Appendix 1bAppendix 1b 324 KB Download
PDF
Appendix 2Appendix 2 182 KB Download
PDF
Harbour Works Consent Application: Swanwick Shore Road Car Park River Wall ReplacementReport 107 KB Download

At this meeting

Whole meeting

Who was there

12 of 24 attended
SW
Councillor Seán WoodwardChairman, present
RH
Councillor Roger HuxstepVice-Chairman, present
FB
Councillor Fred BirkettCommittee Member, apologies
MC
Councillor Mark CooperCommittee Member, absent
RC
Councillor Rod CooperCommittee Member, present
TC
Councillor Tonia CraigCommittee Member, present
PH
Councillor Pal HayreCommittee Member, present
RK
Councillor Rupert KyrleCommittee Member, present
SP
Councillor Stephen PhilpottCommittee Member, present
LQ
Councillor Lance QuantrillCommittee Member, present
AG
Councillor Andrew GibsonConservative Deputy
RB
Rupert Boissier River Hamble Boatyard and Marina Operators AssociationCo-opted Member, present

All 24 on the meeting page

On this subject at Hampshire

Search all
  1. Harbour Works Consent Application – Swanwick Shore Road Car Park River Wall ReplacementThis decision
  2. Harbour Works Consent Application - Quay Wall Refurbishment & Pontoon Works at Riverside BoatyardApproved
  3. Harbour Works Consent Application - Quay Wall Refurbishment & Pontoon Works at Riverside BoatyardApproved
  4. Harbour Works Consent Application - Minor rearrangement of walkway pontoon and installation of two finger pontoons at Prince Philip Yacht HavenApproved
  5. Harbour Works Consent Application - Minor rearrangement of walkway pontoon and installation of two finger pontoons at Prince Phillip Yacht HavenApproved
  6. Harbour Works Consent Application - Retention of existing jetty (retrospective application) and installation of new ecological enhancements at Highfield, SO31 7DFApproved

More from Hampshire River Hamble Harbour Management Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Marine Director and Harbour Master's Report and Current IssuesThe River Hamble Harbour Management Committee supported the contents of this report to the Harbour Board. Decided Open
18 Sep 2026 Environmental UpdateThe River Hamble Harbour Management Committee noted and supported the remainder of this report. Noted Open
18 Sep 2026 Annual Review of Business PlanThe River Hamble Harbour Management Committee recommended that the River Hamble Harbour Board supports the contents o... Decided Open
18 Sep 2026 Forward Plan for Future MeetingsThe River Hamble Harbour Management Committee noted the report. Noted Open
12 Jun 2026 Marine Director and Harbour Master's Report and Current IssuesRESOLVED The River Hamble Harbour Management Committee supported the contents of this report to the Harbour Board. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies