Down Lane Park - Phase 2a:Community Hub - Permission to initiate tender action for a Construction Works Contract

Decided Executive 1 paper

AI summaryHaringey Cabinet approves starting the tender for a new community hub at Down Lane Park in Tottenham Hale, replacing the existing pavilion.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedTo appoint a design and build contractor for Phase 2a
MoneyNot stated in main reportContract value over £500,000 CSO threshold; details in Part B Exempt
What happens nextTender process to beginVia London Construction Programme Framework or DPS
Who it affectsDown Lane Park and Tottenham HaleReplaces pavilion and park depot buildings

What was decided

Cabinet approved the start of a tendering process for a construction works contractor to deliver the new Phase 2a hub building at Down Lane Park. Report 3.1, 3.2

The contract will be procured on a single stage design and build basis using the London Construction Programme General Framework or DPS. Report 4.4

Why

A Principal Contractor is needed to take over design and build from RIBA 4 for the new community hub, part of the wider Tottenham Hale regeneration programme. Report 4.1, 4.2

The new hub replaces the existing Voluntary Community Sector offer in the pavilion, which is being demolished to make way for new sports courts in Phase 3. Report 4.3

The scheme aims to address anti-social behaviour, street drinking and drug taking, and improve drainage, landscaping and play facilities. Report 6.3, 6.2

What happens next

Strategic procurement will work with the service to run the tender and secure social value in line with council priorities. Report P33

Finance comments and further financial detail are set out in Appendix 1 Part B Exempt Information. Report P29, 10.1

The money

  • £500,000 CSO threshold above which Cabinet must approve procurement Report P37

Options considered

  • Chosen: Use the London Construction Programme General Framework or DPS, single stage design and build. Soft market engagement gave positive feedback; compliant with CSO 7.02 and 8.01 Report 4.4, P32, P38
  • Rejected: Do nothing. Part of the works are funded by S106 monies from surrounding developments Report 5.1
  • Rejected: Deliver in house. No current council resource with the capacity, specialist expertise or qualifications Report 5.3
  • Rejected: Invite open tenders via Contracts Finder. Would result in a protracted tender period and delay delivery Report 5.4
  • Rejected: Use an alternative public sector DPS. Would not be compliant with CSO 8.02 given the LCP framework is suitable Report 5.5

Implications

  • Financial: Part of the scheme is funded by S106 monies from surrounding developments; full cost detail is in Part B Exempt Appendix 1. Report 5.1, P29
  • Legal: Procurement will follow the Council's Contract Standing Orders and applicable procurement legislation; no legal reasons prevent approval. Report P36, P38, P39
  • Equalities: The council has considered its Public Sector Equality Duty; the new facility is intended to benefit all residents and the selected contractor must uphold the duty. Report P41, P44, P45, P46
  • Climate: The new building will target BREEAM Very Good, with input from the Head of Carbon Management during feasibility. Report 8.1, 8.2
  • Other: Project will contribute to the Corporate Delivery Plan 2024 to 2026 outcomes on climate, voluntary sector, safer communities, culture and place shaping. Report 7.1, 7.2, P21, P22, P23, P24

Who and where

  • Down Lane Park users and Tottenham Hale residents Report 4.2, 6.2
  • Local voluntary and community sector groups using the current pavilion Report 4.3, 6.5
  • Council parks team, who will get new office and welfare facilities Report 6.5
  • Visitors and users of the new sports courts planned in Phase 3 Report 4.3

Timeline

  • Since 2019: Masterplan for Down Lane Park has been developed Report 6.1
  • Phase 1 and 2b complete: Landscaping and playground to middle and north of park delivered Report 6.1
  • 11th July 2023: Wider masterplan tabled at Cabinet Report 6.1
  • 2026-02-10: Cabinet asked to approve commencement of tender for Phase 2a Report 3.1, 3.2

Plain English for the jargon

  • DPS: Dynamic Purchasing System, a type of public sector framework for buying works or services
  • CSO: Contract Standing Orders, the council's rules for procuring contracts
  • S106: Section 106 planning obligations, contributions from developers towards local infrastructure
  • VCS: Voluntary and Community Sector
  • BREEAM Very Good: A standard rating from the Building Research Establishment Environmental Assessment Method for sustainable buildings
  • RIBA 4: Stage 4 of the Royal Institute of British Architects' plan of work, covering technical design before construction
  • LCP: London Construction Programme, a public sector construction framework
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item398

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Recommendations

3.1For Cabinet pursuant to Contract Standing Orders 2.01(b) to:

3.2Approve the commencement of a tendering process for a construction works contractor to deliver the phase 2a new hub building within Down Lane Park.

Reasons for decision

4.1The appointment of Principal Contractor to take over the design and build of the project from RIBA 4 is required for Phase 2A, the construction of a new community Hub building as part of the Down Lane Park Improvement scheme which is being delivered as part of the wider Tottenham Hale regeneration programme.

4.2This project will comprehensively upgrade Down Lane Park, as a core component of the wider Tottenham Hale regeneration programme whilst addressing current challenges and issues such as anti-social behaviour. It will deliver a new vision for the park, to provide a high quality central green space at Tottenham Hale which caters for the future requirements of all the area’s residents and visitors.

4.3Phase 2a as part of the wider scheme will replace the existing Voluntary Community Sector (VCS) offer currently in the Pavillion building which is being demolished to make way for new sports courts in the Phase 3 works. A purpose-built new Community hub and parks depot building will be located on the old Parks depot building and will also include a new entrance into the hub from Park View Road.

4.4It is proposed to procure a contractor on a single-stage, design & build form of contract using the London Construction Programme General Framework or DPS. Soft market engagement has been undertaken to ascertain interest and availability within the market, with positive feedback of the proposed approach.

5. Alternative options considered.

5.1Do nothing - The council could decide not to tender the scheme. However, part of these works are part funded by S106 monies from the surrounding developments.

5.3In-house – There is currently no resource within the Council that has the capacity, specialist expertise or qualifications to deliver this service.

5.4Invite open tenders via Contracts Finder. This would result in a protracted tender period and would delay delivery of the project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Down Lane Park: Phase 2a:Community Hub: Permission to initiate tender action for a Construction Works ContractMinutes 304 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 19 attended
TE
Taryn EvesCouncil Staff, expected
AO
Councillor Ajda OvatCommittee Member, present
PA
Councillor Peray AhmetChair, present
EA
Councillor Emily ArkellCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, present
DC
Councillor Dana CarlinCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
LD
Councillor Lucia das NevesCommittee Member, present
RG
Councillor Ruth GordonCommittee Member, present
SW
Councillor Sarah WilliamsCommittee Member, present
IA
Councillor Ibrahim AliCommittee Member, present
AD
Andy DonaldOfficer, expected

All 19 on the meeting page

On this subject at Haringey

Search all
  1. Down Lane Park - Phase 2a:Community Hub - Permission to initiate tender action for a Construction Works ContractThis decision
  2. Tottenham Hale Placemaking: co-designed transformation plans for Down Lane ParkNoted
  3. Park Hire Applications made by Cogger Nationwide Amusement to host funfairs in White Hart Lane Recreation Ground and Down Lane Park in 2022Noted

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies