London Borough of Haringey
Cabinet, Tuesday 10 February 2026 at 6.30pm

Pride in Place Funding

Decided Executive 1 paper

AI summaryHaringey Cabinet accepts £1.5 million Pride in Place grant from MHCLG and approves a shortlist of ten capital projects across the borough, with all funding to be spent by March 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided
Money£1.5 million capital grant
What happens nextProject delivery from March 2026First monitoring report due 16 February 2026; final spend deadline March 2027.
Who it affectsResidents across three constituencies

What was decided

Cabinet agreed to accept the £1.5 million grant from the Ministry of Housing, Communities and Local Government under Contract Standing Order 21.01. Report P2

Cabinet added £1.5 million to the General Fund capital programme to fund the shortlisted projects set out in the report. Report P3, 6.9

Cabinet delegated authority to the Corporate Director of Culture, Strategy and Communities to vary schemes and budgets within the overall grant. Report P4, 4.6

Why

The council is ranked the 6th most deprived borough in London and the funding addresses priorities raised by residents through Shaping Tottenham and Shaping Wood Green. Report 6.2, 4.1, 6.3

Unspent money would have to be repaid to MHCLG, and approval in February 2026 was needed to start spending in time for the March 2027 deadline. Report 4.3, 5.2

The first £750k has been in a holding account since October 2025 when the Memorandum of Understanding was signed, and approval releases it for allocation. Report 4.5, 6.5, 8.4

What happens next

Project delivery is scheduled to begin in March 2026, overseen by the Placemaking Culture and Communities Board. Report P39, 6.15

The first monitoring report is due on 16 February 2026, with further reports in May, October 2026 and June 2027. Report P39

Individual project managers will work with the Procurement service on compliant delivery routes, using term contractors or existing frameworks where appropriate. Report 6.12, 6.14

The money

  • £1.5m Total Pride in Place grant from MHCLG Report P2, 6.5
  • £750k First tranche received October 2025 on signing of the MOU Report 6.5, 4.5
  • £750k Second tranche for financial year 2026/27 Report 6.5
  • £100,000 Indicative allocation for borough-wide tree replacement project Report P27
  • £200,000 Indicative allocation for paddling pool upgrades at three parks Report P28
  • £310,000 Indicative allocation for Lymington Avenue improvements in Wood Green Report P29
  • £150,000 Indicative allocation for children's play area at Hornsey and Ducketts Common Report P30
  • £100,000 Indicative allocation for Hornsey rail bridge artworks and lighting Report P31
  • £220,000 Indicative allocation for Tottenham DIY Skate Park Report P32
  • £200,000 Indicative allocation for Somerford Grove public realm Report P32
  • £160,000 Indicative allocation for Lordship Recreation Ground nature play area Report P33
  • £60,000 Indicative allocation for Bruce Castle Park ancient tree protection Report P34

Options considered

  • Chosen: Accept the grant and approve the project shortlist. Enables delivery of council and stakeholder priorities and avoids risk of repayment to MHCLG. Report 3.1, 4.1, 4.3
  • Rejected: Take no action. Funding would have to be repaid to MHCLG and projects would not be delivered. Report 5.1
  • Rejected: Delay the decision to a later date. Would risk missing the March 2027 spending deadline. Report 5.2
  • Rejected: Fund the projects through council borrowing. The council is not in a financial position to fund the projects itself. Report 5.3

Implications

  • Financial: £1.5 million added to the General Fund capital programme, fully grant funded with no revenue element; project management, design fees and surveys can be capitalised. Report 6.5, 8.1, 6.13
  • Legal: Grant is accepted under the Localism Act 2011, Local Government Act 1972 sections 111 and 151; the MOU is not legally binding but unspent funds after 31 March 2027 must be repaid. Report 8.4, 8.5, 8.6
  • Legal: The award does not fall within the Subsidy Act 2022 definition and any contracts must comply with the Procurement Act 2023 and the council's Contract Standing Orders. Report 8.7
  • Equalities: Decision expected to have a positive impact on protected characteristic groups and to advance equality, with engagement planned through local networks including seldom heard groups. Report 8.11, 8.12, 8.13, 8.14, 6.23
  • Risk: Key risks are the March 2027 spending deadline, competing priorities, and limited time for further engagement, mitigated by Cabinet approval, dividing the fund across constituencies, and drawing on prior Shaping Tottenham and Shaping Wood Green engagement. Report 6.10, P36
  • Staffing: Delivery will be overseen by the Placemaking Culture and Communities Board with individual project governance routes agreed with the PMO team. Report 6.15

Who and where

  • Residents across all three Haringey constituencies, particularly in the east of the borough where deprivation is concentrated Report 6.2, 6.3
  • Friends of parks groups, including Friends of Lordship Rec, Friends of Bruce Castle Park, Friends of Ducketts Common and Friends of Parks groups Report P27, P28, P30, P33, P34
  • Wood Green BID, The Mall traders, Turnpike Lane Traders Association and local businesses on Lymington Avenue Report P29, P31
  • Skateboarder group, Harris Academy Tottenham and a Tottenham grassroots skating group using the under croft Report P32
  • Children, families and SEND families using paddling pools and play areas across the borough Report P28, P30
  • Seldom heard and minoritised groups reached through resident associations, voluntary and community sector organisations, youth hub cohorts and the Haringey Youth Panel Report 6.23, 6.24
  • Visitors for London Borough of Culture 2027 and UEFA Euros 2028 Report 6.3

Timeline

  • October 2025: Memorandum of Understanding signed and first £750k payment received Report P39, 6.5
  • November 2025: Project shortlist created Report P39
  • December 2025: MPs engaged on the project shortlist Report P39
  • February 2026: Cabinet approval of funding allocation and shortlist; first monitoring report due 16 February 2026 Report P39
  • March 2026: Project delivery begins; outputs and monitoring approach agreed Report P39
  • May 2026: Second monitoring report submitted Report P39
  • July 2026: Second £750k payment received Report P39
  • October 2026: Third monitoring report submitted Report P39
  • March 2027: All projects delivered; final MHCLG funding deadline Report P39, 8.6
  • June 2027: Final monitoring report submitted Report P39

Plain English for the jargon

  • MHCLG: Ministry of Housing, Communities and Local Government, the UK government department providing the Pride in Place Impact Fund.
  • Pride in Place Impact Fund: A £150 million national fund announced in the 2025 Spending Review for 95 selected areas, aimed at addressing deprivation and building resilient communities.
  • MOU: Memorandum of Understanding, the non-legally binding agreement signed with MHCLG in October 2025 covering the grant.
  • CSO 21.01: Contract Standing Order rule requiring Cabinet approval to accept third party grants of £500,000 or more.
  • Haringey Deal: The council's approach to working in partnership with residents to build stronger relationships and address local priorities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item409

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Recommendations

3.1Cabinet is recommended to:

i. Accept the grant of £1.5m from the MHCLG in accordance with Contract Standing Order (CSO) 21.01 (Cabinet approval required to accept 3rd party grants of £500,000 and above);

ii. Increase the approved General Fund capital programme by £1.5m to deliver the schemes as set out in section 6 of this report; and

iii. Delegate authority to the Corporate Director of Culture, Strategy & Communities to vary the schemes and budgets within the overall grant received.

Reasons for decision

4.1This investment provides a unique opportunity to enable the Council to deliver not only on its own corporate priorities, but also the priorities of local people and stakeholders. These priorities have been identified and developed through extensive engagement as part of Shaping Tottenham and Shaping Wood Green, in alignment with the principles outlined within the Haringey Deal.

4.2As well as making physical improvements within the borough, delivery against these priorities will build on prior engagement, further strengthen the relationships the Council holds with local people, amplify the needs and voices of the seldomly heard, and enhance levels of civic pride across the whole borough.

4.3Approval to accept the grant will enable the Council to begin the process of project delivery and start spending the funding. As the funding has a deadline of March 2027, it is essential that spend can begin as soon as possible to enable this deadline to be met. 4.4. It is likely that unspent monies will need to be repaid back to the funder, and approval to accept the funding in February 2026 will reduce the risk of this happening in March 2027.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pride in Place FundingMinutes 413 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 19 attended
TE
Taryn EvesCouncil Staff, expected
AO
Councillor Ajda OvatCommittee Member, present
PA
Councillor Peray AhmetChair, present
EA
Councillor Emily ArkellCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, present
DC
Councillor Dana CarlinCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
LD
Councillor Lucia das NevesCommittee Member, present
RG
Councillor Ruth GordonCommittee Member, present
SW
Councillor Sarah WilliamsCommittee Member, present
IA
Councillor Ibrahim AliCommittee Member, present
AD
Andy DonaldOfficer, expected

All 19 on the meeting page

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies