Cabinet, Tuesday 10 February 2026 at 6.30pm

High Road West - Next Steps

Decided Executive 2 papers

AI summaryHaringey Cabinet approves procurement of 61 new council homes at High Road West Phase 1A, after taking the scheme back from Lendlease, and delegates the choice of route to market to the Chief Procurement Officer.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided61 council homes at High Road West Phase 1A
MoneyTotal sum in exempt reportGLA Affordable Housing Grant £70,312,000 already drawn down
What happens nextCompetitive tender via LCP FrameworkSubject to Cabinet approval after tender
Who it affectsLove Lane Estate residentsSecure tenants, leaseholders, temporary accommodation households

What was decided

Cabinet approved the commencement of a procurement exercise for 61 new council homes at High Road West Phase 1A under Contract Standing Order 2.01 b). Report 3.1, P2

Cabinet delegated to the Chief Procurement Officer the choice of the appropriate route to market, in compliance with the Council's Contract Standing Orders. Report 3.1, P2, 9.17, 9.18

Why

The step re-starts the High Road West scheme after Phase 1A was removed from the Development Agreement with Lendlease in December 2025, allowing the Council to direct deliver council homes and rehouse Love Lane residents in line with the Landlord Offer endorsed in the 2021 resident ballot. Report 4.1, 6.7, 6.4

Financial appraisals supported by an independent cost consultant show the scheme is viable and offer value for money, and the Council must use its drawn-down GLA grant within its funding milestones. Report 4.3, 6.3

What happens next

Officers will run a single stage JCT Design and Build tender, return the scheme to Cabinet for approval once a successful bidder is identified, and consult the remaining 26 secure Love Lane tenants on Ground 10A in summer 2026. Report 6.15, 6.20, 6.45

The works contract will also cover demolition of 100 Whitehall Street (Whitehall Lodge hostel) and the 2-32 Whitehall Street block, and the Council will implement the confirmed Compulsory Purchase Order before 20 March 2027. Report 4.4, 4.5, 6.46

The money

  • £70,312,000 GLA Affordable Housing Grant already drawn down for the scheme Report 6.3
  • £21,200,000 GLA Mayor's Land Fund for land assembly cashflow Report 6.3
  • £500,000 Threshold above which Cabinet approval to commence procurement is required under CSO 2.01 b) Report 4.4, 9.17

Options considered

  • Chosen: Proceed with direct Council delivery of Phase 1A via procurement. Allows rehousing of around half of Love Lane residents into 100% council home scheme with planning permission and uses already drawn-down GLA grant. Report 3.1, 4.1, 4.3, 6.7
  • Rejected: Do not proceed with direct delivery of Phase 1A. Would leave no route to a 100% council home scheme, delay Landlord Offer commitments, and leave a partially demolished site with anti-social behaviour plus a Whitehall Lodge building needing major investment. Report P8, 5.1

Implications

  • Financial: The contract sum is set out in the exempt report; the Council must meet GLA grant milestones on the £70,312,000 Affordable Housing Grant already drawn down. Report 3.1, 4.1, 6.3
  • Legal: Procurement must comply with CSO 2.01 b) and 7.02; the Director of Legal and Governance raises no legal objection. Confirmed CPO must be implemented by 20 March 2027. Report 9.17, 9.18, 9.21, 6.46
  • Equalities: Decision is expected to advance the public sector equality duty, with positive impact on women, young people, lower socio-economic groups and BAME residents who are over-represented in temporary accommodation. Report 9.22, 9.25, 9.26
  • Climate: Phase 1A is designed to Passivhaus principles with a 70% carbon improvement over the 2021 building regulations baseline, plus living roofs, solar PV, and Biodiversity Net Gain features. Report 8.1, 8.2
  • Risk: CPO powers expire on 20 March 2027; route forward for subsequent phases with Lendlease is still under negotiation. Report 4.1, 6.46, 6.47
  • Staffing: The Council has an in-house project team to run the quality assessment, with Procurement moderating and a Cost Consultant independently reviewing costs. Report 6.18, 6.19

Who and where

  • Secure and non-secure tenants on the Love Lane Estate, including the remaining 26 secure tenants Report 6.4, 6.45
  • Love Lane Estate resident leaseholders Report P16
  • Residents of the Headcorn and Tenterden Estate, who neighbour the Phase 1A site Report 6.13
  • Households in Haringey temporary accommodation, including those to be re-housed from 100 Whitehall Street (Whitehall Lodge) Report 4.4, 4.5, 6.9
  • Applicants on the Haringey housing register, including families needing 3 and 4-bed homes Report 9.25
  • Construction and supply chain workers, with the wider Scheme projected to create around 1,214 construction jobs and 1,202 supply chain jobs Report 6.2

Timeline

  • July and August 2021: Love Lane Estate resident ballot held; majority back the regeneration proposals Report 6.4
  • August 2022: Planning Sub Committee grants hybrid consent including detailed consent for Phase 1A Report 6.6
  • July 2023: Non-Material Amendment to the Phase 1A planning consent approved Report 4.2
  • 20 March 2024: Press notice confirming the High Road West Phase A Compulsory Purchase Order Report 6.46
  • December 2025: Council and Lendlease agree to remove Phase 1A from the Development Agreement for direct Council delivery Report 6.7
  • Summer 2026: Ground 10A consultation planned with the remaining 26 secure Love Lane tenants Report 6.45
  • 20 March 2027: Deadline for using the confirmed CPO powers Report 6.46

Plain English for the jargon

  • DA (Development Agreement): Agreement with Lendlease setting out the phased delivery of the High Road West Scheme, under which Phase 1A has now been removed.
  • CPO (Compulsory Purchase Order): Legal power to acquire land and property interests needed for the scheme; the Phase A CPO was confirmed by the Secretary of State.
  • Ground 10A: Statutory ground under the Housing Act 1985 allowing a court to order possession of a secure tenancy for redevelopment reasons.
  • CSO (Contract Standing Order): The Council's internal rules governing procurement; CSO 2.01 b) sets the £500,000 Cabinet approval threshold.
  • JCT Design and Build Contract: Standard form of building contract where the contractor takes on the design responsibility.
  • Passivhaus: A standard for energy-efficient building design aimed at very low energy use and high comfort.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item407

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet – 10 February 2026

Item number: 18

Title: High Road West Scheme – Next Steps

Report authorised by: Taryn Eves, Corporate Director of Finance & Resources

Lead Officers: Robbie Erbmann, Delivery Director Abigail Stratford, Director of Placemaking & Community Development

Ward(s) affected: Bruce Castle

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration

1.1In 2017, following a competitive procurement process, the Council entered into a Development Agreement (“DA”) with Lendlease to deliver the High Road West Scheme (“the Scheme”) in north Tottenham. In recent years the Scheme has progressed through a number of milestones, including the grant of a hybrid planning application for the site, a positive resident ballot on the Love Lane Estate, and confirmation of a compulsory purchase order for Phase A, comprising the southern half of the site.

1.2Delivery is currently stalled, due to difficult market conditions which have increased the budget needed to deliver the Scheme. The Council has been working with Lendlease to explore ways to address these challenges and find a viable route to unlock delivery. Furthermore in May 2025, Lendlease announced that they had entered into a conditional agreement to create a joint venture partnership with the Crown Estate to deliver its UK development projects. If a viable route is found, and subject to a future decision by Cabinet, then the Scheme may be delivered by that partnership. The negotiations with Lendlease on these matters are ongoing.

1.3The Council's highest priority through the current review of the Scheme has been to build new Council homes for Love Lane Estate residents as quickly as possible. In this context, the Council and Lendlease have reached an agreement to remove Phase 1A from the DA and in turn enable the Council to direct deliver the site, which comprises the first 61 council homes within the Scheme, as part of its council house-building programme. This report seeks authority for the Council to procure a contractor to deliver the council homes, which if approved, means that construction works at the site could re-start later this year. This would provide a route to rehousing around half of the residents on the Love Lane Estate. 2. Cabinet Member Introduction

2.1We’ve long been committed to delivering transformational change for residents in north Tottenham, including providing much-needed new homes for those on the Love Lane Estate. Our landlord offer sets out clear guarantees: secure and non-secure tenants on the Love Lane Estate will be offered a high-quality, modern, council-owned home within the High Road West redevelopment area that meets their needs. The recommendations in this report represent a major step forward in fulfilling those commitments, while we continue to explore a viable route for the next phase of the High Road West scheme.

2.2The new council homes at Phase 1A will be built to the high quality seen on our sites across the borough and will support our efforts to build at least 3,000 new council homes at council rents by 2031. We are building homes that will last, with great insulation standards, great interior and exterior design standards and a strong mix of family and individual homes. We make sure homes are as well- insulated and energy-efficient as possible, because we want homes that aren’t just affordable to rent but affordable to run.

2.3Phase 1A will have four fully wheelchair-accessible 2-bedroom flats, twenty 1- bedroom flats, ten 2-bedroom flats, twenty-three 3-bedroom family homes and four 4-bedroom family homes. Proposals also include a shared communal garden with play space for children and private amenity space for each home, including private balconies and gardens for the ground floor homes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site Plan, Floorplans and 3D Impressions-High Road West Phase 1A_25-12-16Appendix 1 2.5 MB Download
PDF
High Road West: Next StepsMinutes 260 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 19 attended
TE
Taryn EvesCouncil Staff, expected
AO
Councillor Ajda OvatCommittee Member, present
PA
Councillor Peray AhmetChair, present
EA
Councillor Emily ArkellCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, present
DC
Councillor Dana CarlinCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
LD
Councillor Lucia das NevesCommittee Member, present
RG
Councillor Ruth GordonCommittee Member, present
SW
Councillor Sarah WilliamsCommittee Member, present
IA
Councillor Ibrahim AliCommittee Member, present
AD
Andy DonaldOfficer, expected

All 19 on the meeting page

On this subject at Haringey

Search all
  1. High Road West - Next StepsThis decision
  2. Proposed Red Route on A105 High Road Wood GreenAgreed
  3. Application for a Review of a Premises Licence - Dulce Pecado, 263 High Road, London N15 4RR (TOTTENHAM CENTRAL)Noted
  4. Report for approval of the contract for Phase 1(a) of the High Road West Scheme, demolition of 2-32 Whitehall Street, and the management plan for the Love Lane estate.Decided
  5. Application for a new premises licence at stadium lounge, restaurant & wine bar ltd, 783 high road, tottenham, london n17 8ah (nothumberland park)Agreed
  6. Canning Crescent 176 High Road, Wood Green, N22 8JT Refurbishment Works - Increase of project budget and variation of construction works contractApproved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open