What was decided
Cabinet approved the preparation and submission of a hybrid planning application for the Station Road sites, covering a detailed application for the Western End (40 Cumberland Road and 48 Station Road) and an outline application for the Eastern End (River Park House, Alexandra House, 38 Station Road, 5 River Park Road and the adjacent car park). Report P2, 3.1
Cabinet approved procurement of a multi-disciplinary professional team and associated commissions, with an upper cost limit of £4,180,000, of which £2,270,000 is funded by the Housing Revenue Account and £1,910,000 by the General Fund. Report P3
Cabinet delegated appointment of the multi-disciplinary team to the Director of Culture, Strategy and Communities following the competitive procurement exercise, and added the Western End to the Housing Delivery Programme at Gateway 0. Report P4, P5
Why
The Station Road sites have been designated for mixed-use redevelopment since 2017 and are identified as a key placemaking area in the Shaping Wood Green vision and the Wood Green Central site allocation in the draft Local Plan, supporting new homes, town centre uses, jobs and a new public square. Report 4.1, 4.2, 4.3, 4.4
Once the new Civic Centre completes in early 2027, the buildings will be vacated, creating an opportunity to deliver a once-in-a-generation transformation of the town centre, meet the financial requirements of the Civic Centre Business Case, and avoid leaving buildings empty. Report 4.5, 4.6, P12, 4.9
Officers tested a range of delivery options and found that dividing the site into a Western End for council housing delivered by the Council's Housing Delivery team, and an Eastern End kept flexible for future decision making, best meets the Council's objectives. Report 4.8, P14, P15, P16
What happens next
A multi-disciplinary design team will be appointed in late Spring 2026 through a competitive procurement exercise, with the hybrid planning application submitted in Summer 2027 and a planning decision expected in Spring 2028. Report 6.10, P47, 4.11, 4.12
The Eastern End delivery route will be the subject of a further Cabinet decision at a later date, and a steering group including local ward councillors will inform the next stage of design proposals. Report P15, 6.13
The money
- £4,180,000 Upper cost limit for design team and hybrid planning application workstreams Report P3, 6.8, P41
- £2,270,000 Funded from the Housing Revenue Account Report P3, 6.9
- £1,910,000 Funded from the General Fund via the Wood Green Central budget Report P3, 6.9
- £4,801k Gross cost of the Civic Centre as set out in the November 2024 business case Report 9.3, P67
- £3,570k Net cost of the Civic Centre as set out in the November 2024 business case Report 9.3
- £697k Residual net revenue pressure for 2028/29 after release of Eastern End budgets and capital receipt Report 9.9, P74
- £771k Estimated reduction in pressure by 2030/31 from new social homes cutting temporary accommodation costs Report 9.10, P74
Options considered
- Rejected: Do nothing. Vacated buildings would remain a maintenance, security and business rates cost, and the Civic Centre Business Case assumes income from the sites Report P20, 5.1
- Rejected: Externally lease Alexandra House, 48 Station Road and 40 Cumberland Road as office space. Commercial advice indicates weak demand for lower quality office space in Wood Green and the target rental income in the Civic Centre Business Case is unlikely to be met Report P22, 5.2, 5.4
- Rejected: Dispose of the Station Road sites to the market. Would not secure placemaking outcomes and risks poor land value, land-banking and loss of ability to lever in grant for council homes Report P25, 5.5, 5.6
- Rejected: Procure a development partner to develop the whole site. Relying on a single partner increases delivery risk and forfeits the opportunity for the Council Housing Delivery Team to deliver new council homes quickly Report P28, 5.7, 5.8
Implications
- Legal: The Council can prepare and submit the hybrid planning application under section 2 of the Localism Act 2011, and the procurement recommendations comply with Contract Standing Orders 2.01(b) and 2.01(c). Report 9.20, 9.21, 9.22, 9.24, 9.25
- Equalities: The decision is considered to have a neutral equalities impact at this design stage, with a full Equalities Impact Assessment to be carried out as proposals develop. Report 9.29, 9.30, P89
- Climate: The decision is for design work only and will not directly reduce carbon emissions, but feasibility of retaining existing buildings will be studied and any new buildings will be designed to modern energy use standards. Report P54, 8.1
- Risk: There is a risk that some Council services may need to remain in 48 Station Road until 2028, which would delay the appropriation of the Western End to the HRA. Report 6.11
- Other: An Economic Impact Assessment by Avison Young in May 2025 found the redevelopment approach could have a positive effect on the town centre through construction jobs, new homes, increased spend and improved public spaces. Report 6.7
Who and where
- Residents of Haringey, particularly in Wood Green, who may benefit from new council homes, town centre uses and public spaces Report 4.2, 4.3, 4.4, 6.7
- Existing 'meanwhile use' tenants at 5 River Park Road (Blue House Yard) and 40 Cumberland Road, who will be communicated with during the planning process Report 6.13
- Local ward councillors, who will be represented on a project steering group Report 6.13
- Council staff currently based in the Station Road buildings, due to relocate to the new Civic Centre and other locations in early 2027 Report 4.5, 6.4
Timeline
- Feb 2026: Cabinet decision on next steps Report P47, 6.10
- Late Spring 2026: Appoint a Design Team Report P47, 6.10
- Early 2027: Relocation of Council's accommodation to the Civic Centre Report 4.5, 6.4, P47
- Summer 2027: Submit hybrid planning application Report P47, 6.10
- Spring 2028: Determination period, Section 106 agreement and planning permission received Report P47, 4.12
- Summer/Winter 2028: Demolition and contractor procurement for Western End Report P47, 6.10
- Summer 2029: Start construction of council homes on the Western End Report P47, 6.10
Plain English for the jargon
- Hybrid planning application: A planning application that combines a detailed application for part of a site with an outline application for the rest, setting principles while leaving detailed design to be agreed later.
- Housing Revenue Account (HRA): The Council account that holds rental income from council housing and funds the building and management of council homes.
- Section 106 (S106): A legal agreement between a developer and the local planning authority, used to make development acceptable by requiring contributions such as affordable housing or infrastructure.
- Gateway 0: The first stage in the Council's Housing Delivery Programme approval process, used to add a scheme to the programme before further work.