What was decided
Cabinet approved disposal of 9 open market sale units at 100 Woodside Avenue, on the terms and sales strategy set out in the report, and delegated authority to the Delivery Director and s151 Officer to complete each sale. Report P2, P3
Cabinet approved the increased budget for the scheme, with the figure set out in the Exempt Part of the report. Report P4
Why
The sale receipts will cross-subsidise the 32 new council homes in the scheme, supporting the council's wider target of 3,000 new council homes by 2031. Report 4.1, 4.2, 9.1, 9.2
Officers revised the lease terms from 125-year leases on flats to 999-year leases to improve marketability, ahead of expected leasehold reform legislation in 2026. Report 4.2, 7.2, 7.3, 7.4
Construction has been delayed by around 22 months due to complex underground sewer and water main replacement work and related legal costs. Report 4.5, 6.4
What happens next
The appointed sales and marketing agent will launch the homes, with Haringey residents and key workers given exclusive early access for 6 weeks before wider London and UK marketing. Report 7.12, 7.13, 7.14
All disposals will be managed through the council's Disposal Board, and the council will retain and manage the estate common parts under a service charge regime covering all residents. Report 7.9, 7.11, 7.15, 11.10
Options considered
- Rejected: Do not sell the 9 homes on the open market and keep them for affordable housing. Would affect the financial viability of the whole 41-home scheme and remove the cross-subsidy for the 32 council homes Report P10
- Rejected: Sell the 7 flats on 125-year leases as originally approved in 2022. Considered less marketable ahead of expected leasehold reform and harder for buyers to obtain mortgages Report 4.2, 7.2, 7.3, 7.4
Implications
- Financial: Finance confirms the proposed sales strategy will impact positively on the Housing Revenue Account and the revised budget can be contained within the HRA. Report 11.11, P64
- Legal: The disposals fall within the General Housing Consents 2013 (paragraph A3.1.1) as sales at market value, so specific Secretary of State consent under section 32 of the Housing Act 1985 is not required. Report 4.3, 11.3, 11.6, 11.16
- Equalities: The development includes 10% fully wheelchair accessible and adaptable homes, and homes can be adapted under the council's Bespoke Housing Policy. Report 11.16
- Climate: The scheme is designed to achieve a 90% improvement on building regulations for fuel and power, with Passivhaus principles, solar panels, and Block A having potential to achieve Passivhaus certification. Report 6.3, 10.1, 10.2, 10.4
- Risk: Future leasehold and commonhold reform legislation may enhance the statutory rights of long-leasehold purchasers, though officers say this is not a legal impediment to the disposal. Report 7.2, 11.7, 11.8, 11.9
Who and where
- Prospective buyers of the 9 market sale homes, prioritising Haringey residents and key workers in the first 6 weeks Report 7.12, 7.13
- Future council tenants of the 32 affordable homes at 100 Woodside Avenue in Muswell Hill Report 4.1, 6.1
- Existing residents and freeholders on the wider estate, who will be subject to the new service charge regime Report 7.9, 7.10
Timeline
- September 2022: Works commenced on site Report 6.1
- 8 November 2022: Cabinet approved appointment of main works contractor and disposal of the 9 market sale units on original lease terms Report 4.2, 6.1, 6.2
- 3 March 2025: Government White Paper published, signalling leasehold reform and a draft Leasehold and Commonhold Reform Bill Report 7.2, 11.7
- 10 February 2026: Cabinet approved revised sales strategy and increased budget Report P2, P4
- Early 2026: Draft Leasehold and Commonhold Reform Bill expected Report 7.2
- Second half of 2026: Anticipated completion of construction Report 6.1
Plain English for the jargon
- HRA: Housing Revenue Account, the ring-fenced account councils use for income and spending on council housing
- General Housing Consents 2013: Government consents allowing councils to dispose of housing land at market value without needing individual Secretary of State approval
- Passivhaus: A building standard focused on very high energy efficiency and low carbon emissions
- Build over agreement: Approval needed from the sewer or water company before building over or close to existing underground infrastructure
- JCT contract: A standard form of construction contract issued by the Joint Contracts Tribunal