That approval be granted subject to: ( i ) the completion of a Section 106 Agreement as set out in the report; (ii) the conditions as set out in the report; (iii) the additional conditions as set out in the update sheet; and (iv) authority be delegated to the Operations Manager-Development Services to further negotiate with the applicant regarding the specific layout of the affordable housing 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Operations Manager – Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of the committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 20th January 2020
Application HPK/2019/0280 No: Location Land Between 15 and 23 Batham Gate Road, Peak Dale Proposal 27 residential dwellings and new access road Applicant Southworth Construction Agent RPS Design Group Ltd Parish/ward Wormhill and Green Date registered 27th June 2019 Fairfield Parish / Limestone Peak Ward If you have a question about this report please contact: Mark Ollerenshaw, Tel. 01538 395400 extension 4921, [email protected]
REFERRAL
This application has been brought before the Development Control Committee because it is a major development.
1. SUMMARY OF RECOMMENDATION
Approve, subject to the completion of a Section 106 Agreement and conditions.
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The site comprises 0.84 hectares of grazing land within the built up area boundary of Peak Dale. The site lies within the landscape character type ‘Plateau Pastures’ which is generally an open and unwooded landscape defined by dry stone walls and pasture. The site itself is of open character; gently sloping improved grassland which is semi-enclosed by residential properties and the Church. The western edge of the site is more elevated and visually prominent.
2.2The site takes access from Batham Gate Road through a field gate. It has a frontage with Batham Gate Road which extends to some twenty five metres and lies between existing residential development which forms a part of a street scene of ribbon development stretching along this part of Batham Gate Road.
2.3The north eastern boundary of the site is bounded by existing residential development on Church Avenue and Holy Trinity Church. The land to the south and west is open countryside. The site is mainly bounded by traditional limestone walling and there is a line of electricity power cables crossing the site. There are no trees within the site although there are few on the site boundary where it adjoins residential properties.
3. DESCRIPTION OF THE PROPOSAL
3.1This is a full planning application for the erection of 27 new dwellings served by a new access road on land between 15 and 23 Batham Gate Road, Peak Dale.
3.2The application follows on from a previous consent for the same number of dwellings, ref. HPK/2015/0174, which was granted on 21st July 2015 subject to conditions and a Section 106 Agreement securing affordable units and contributions towards play space and public open space. A subsequent application for Variation of Condition 2 to make minor changes to approval HPK/2015/0174 (ref. HPK/2018/0106) was brought to Development Control Committee in May 2018 and was approved by the Committee subject to conditions and completion of a Deed of Variation to the original S106 Agreement. However, the original consent HPK/2015/0174 then lapsed in July 2018 as a lawful commencement on site had not been made within 3 years of the permission. Therefore, the decision notice for the Variation of Condition 2 application could not be issued as that would have been subject to the same 3 year time limit for commencement as the original consent.
3.3In addition, it should be noted that the site was subject to a Temporary Stop Notice in February 2018 whereby the carrying out of excavations, removal of topsoil and engineering operations were considered to cause significant risk to known archaeological remains on the site.
3.4The layout of the current scheme and scale of the buildings remains the same as previously approved. Minor changes have however been made to the detailed design of the properties, including fenestration and construction materials. It is proposed to construct the new properties in reconstituted stone with Marley Eternit Edgemere Interlocking slate, instead of locally sourced random stone and natural slate as previously approved in 2015. It is noted that the revised materials were subsequently agreed by the Committee during the consideration of the 2018 variation application. .
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.