That the application be approved as set out in the report. Members noted that the requirement for hedgehog/wildlife permeability between plots and eradication of any Japanese Knotweed on the site would be dealt with in conditions 10, 18 and 19 of the conditions set out in the report; 2. That the Arboriculturalist be requested to re-assess the remaining trees on the site once the development has concluded and determine whether a new TPO was required; 3. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete vary or add conditions/informative/planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of this committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date: 28th September 2023
Application No: HPK/2023/0025 Location Land south of Hollin Cross Lane, Glossop, SK13 8JH Proposal Demolition of redundant buildings including partial demolition of modern extensions to Redcourt and redevelopment of site to provide 24 dwellings (Use Class C3) including the retention and conversion of Redcourt for together with access, parking and landscaping (resubmission of application reference HPK/2020/0334).. Applicant Glossop Eden Ltd Agent Eden Land Planning Ltd Parish/Ward Howard Town Date registered: 27/01/2023 If you have a question about this report please contact: Rachael Simpkin [email protected] 01538 395400 extension 4122
REFERRAL
The above planning application is a major development and is locally contentious.
1.0SUMMARY OF RECOMMENDATION
APPROVE, subject to planning conditions and s106 agreement.
2.0DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The 2.0 hectare site is comprised of a steep wooded valley slope which runs down towards Long Clough Brook. The site has significant mature tree coverage of different species of trees. The site is covered by a group Tree Preservation Order (TP061).
2.2The vacant application site was previously a facility owned and operated by St Christopher’s Trust offering supported living and residential care, which now takes place in the adjacent residential care facility. It is occupied by the building known as Redcourt, which hosted the former facility. A vacant ancillary gym building is located in the southern part of the site. All other structures have been previously demolished and cleared from the site except an area of hardstanding / building foundation.
2.3The site falls within the St. James Conservation Area and is positioned close to St. James’ Church, a Grade II Listed Building (together with separately Listed Lytch Gate and funerary monument). Redcourt is a non-designated heritage asset and is located within the Conservation Area.
2.4The main access into the site is via Hollin Cross Lane to the north and there is also a disused gateway from Slatelands Road to the west. It is bound to the north by Hollin Cross Lane and residential dwellings off Slatelands Road to the northwest corner of the site. St. James Church and residential streets bound the site to the east. Long Clough Brook flows alongside the southern and southwestern site boundaries of the site whereby levels appreciably fall towards the brook.
2.5For the purposes of the Adopted Local Plan, the application site also falls within the Built up Area Boundary of Glossop within c.600 metres of the town centre. The part of the site adjacent to the brook falls within Flood Zones 2 and 3, whilst the remaining area falls within Flood Zone 1.
3.0DESCRIPTION OF THE PROPOSAL
3.1Following the dismissed appeal in relation to refused planning permission ref. HPK/2020/0334, this resubmitted scheme comprises of 24 properties (previously 23), proposing the partial demolition and conversion of Redcourt into 4 dwellings and 20 new build properties expressed as two development parcels. The current scheme proposes the following minor amendments when compared to the appeal scheme (HPK/2020/0334):
Conversion of one semi-detached unit to two no. one bedroom apartments (units 23 and 24) Provision of one additional car parking space to serve plot 24 Revised boundary treatments plan to provide hedgerows in public areas.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.