That the application be approved as set out in the report, subject to: a an additional condition requiring the provision of landing/resting areas, e.g. benches, on the primary street within the development; b the developer be requested to install tactile crossing points as part of compliance with condition 32; c the inclusion of an Overage Clause within the Section 106 agreement to be assessed on completion of the development; and d that authority be delegated to officers to agree suitable solar panels for plots 1 to 5 and 90 to 99 (i.e. those properties where permitted development rights have been removed in respect of solar panels. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
At the 16th June 2025 Development Control Meeting it was resolved that the application be deferred to allow additional information to be provided in respect of the following matters to enable further consideration of this planning application:-
1. The viability assessment and review in respect of the proposed reduced provision of affordable housing and other contributions on the site;
2. Air quality matters, including up to date emissions data and an explanation of the conclusion from Environmental Health; and,
3. Drainage and flood risk matters, including in relation to the structural condition of the Nun Brook Culvert.
Members will be updated on these matters in the relevant report subject headings below.
In summary, the applicant’s Financial Viability Assessment (FVA) dated August 2024 and recently provided Executive Summary with Supporting Letter have been placed on the public file for the planning application alongside the Council’s Independent Appraisal of the applicant’s findings, accompanied by a property mix appraisal.
An Air Quality Assessment (AQA) Addendum dated July 2025 has also been received and provides additional information in relation to the Hogshaw Roundabout AQA, the assessment carried out by the Council to inform the Fairfield Road AQMA and an update on the latest available air quality information for the area. Additional mitigation as a result of the scheme is not deemed necessary and therefore it is not considered appropriate to undertake damage cost calculations or undertake to provide additional mitigation to those measures identified within the Travel Plan and / or as required under Building Regulations as concluded by the report. These matters have been concurred with by the Council’s Environmental Health Officer following consultation and therefore no further work in the form of a planning condition has been requested in these regards.
In terms of drainage and flood risk matters, a Culvert Stability Appraisal alongside CCTV footage of the existing culvert has been submitted to the Council and has been considered by the LLFA (Lead Local Flood Authority). It demonstrates the current culvert condition is satisfactory and if the recommendations of the appraisal are followed, the risk of any negative effect of the culvert both during and following construction would be mitigated as confirmed by the LLFA.
In relation to other matters, the applicant has provided a revised Energy and Sustainability Report dated July 2025 together with a Solar Photo Voltaic (PV) Layout (H8797-BAH-XX-XX-DR-UD-203075), with roof solar PV panels included on updated house types for all scheme plots.
The updated revised planning application form has confirmed the correct gross site area as 5.605 hectare (ha) to correctly reflect the previously amended red edge, which has accommodated the relocated attenuation basin which allowed for the greater retention of trees.
SUMMARY OF RECOMMENDATION
APPROVE with conditions and s106 legal agreement.
1. REASON FOR COMMITTEE DETERMINATION
1.1This application has been brought before the Development Control Committee as the proposal constitutes major development exceeding 1.0 hectare (ha) and is locally controversial.
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.