Development Control Committee, Monday 3 November 2025 at 1.30pm

Update Sheet

Noted Planning 2 papers

AI summaryHigh Peak Development Control Committee noted updates on nine applications, including a maintained refusal recommendation for a Buxton aparthotel, new noise conditions for a Fairfield site, and corrected 50-year wording for a New Mills battery scheme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee received updates covering nine applications
Money£204,250 and £250,000Unaccounted timber window and natural stone costs
What happens nextVerbal updates at meetingOfficers to address bats and location plan for aparthotel
Who it affectsApplicants and residentsAcross nine application sites in High Peak

What was decided

The committee received the update sheet covering nine applications on 3 November 2025. Report P1, P2, P3

For the Waterswallows Road site, officers recommended replacing the existing Noise Management Plan condition with four new conditions covering sound levels, reversing alarms, fixed plant, and construction hours. Report P26, P18, P19, P20, P21, P22

For the Buckingham Hotel aparthotel, officers maintained the recommendation to refuse planning permission. Report P94, P82, P91

Why

Two further objections were received for the Harpur Hill site raising concerns about on-street parking during football matches and the proposed use of the SUDS area for site offices and storage. Report P5, P6, P7, P8

Environmental Health provided further comments on the Waterswallows Road site, identifying unenforceable elements in the original Noise Management Plan and setting out replacement conditions. Report P16, P17

Conservation, viability, and highway concerns remained for the Buckingham Hotel, with the independent viability assessor finding it unlikely the scheme could be made viable, and additional unaccounted costs identified. Report P49, P53, P54, P62, P67

What happens next

Officers will provide verbal updates at the meeting on the implications of the bats assessment and the red edge location plan for the Buckingham Hotel application. Report P85, P93

The committee will consider the corrected wording for the Marsh Lane battery storage condition, changing the lifespan from 35 to 50 years, with no change to the original recommendation. Report P104, P106, P117

The money

  • £204,250 Additional cost of timber windows not included in the applicant's viability appraisal for the Buckingham Hotel Report P62
  • £250,000 Additional cost of natural stone not included in the applicant's viability appraisal for the Buckingham Hotel Report P62

Options considered

  • Chosen: Note the update sheet
  • Chosen: Maintain refusal recommendation for the Buckingham Hotel aparthotel. Scheme fails sustainability and viability tests and causes heritage harm Report P94, P82, P91, P49
  • Chosen: Replace the noise condition with four new conditions at Waterswallows Road. Environmental Health identified unenforceable elements in the original Noise Management Plan Report P26, P16

Implications

  • Legal: The Buckingham Hotel scheme is considered to fail the first test of Regulation 55 of the Conservation of Habitats and Species Regulations 2019, as it is not considered sustainable development under the National Planning Policy Framework. Report P81, P82, P83
  • Financial: The independent viability assessor found it highly unlikely further information would demonstrate the aparthotel is viable, with additional unaccounted costs of £204,250 and £250,000 identified. Report P91, P62
  • Climate: Natural England confirmed the Buckingham Hotel development would not have significant adverse impacts on designated sites, subject to a planning condition for a vortex separator. Report P74, P88, P89
  • Risk: Objections to the Marsh Lane battery scheme extension cite safety concerns and lack of agreement with Network Rail, though the original permission requires such an agreement before any work begins. Report P111, P116
  • Other: A typo in the Marsh Lane condition was corrected, changing the operational lifespan from 35 to 50 years to match the intended wording. Report P104, P105, P106

Who and where

  • Residents of the Harpur Hill estate and football match attendees Report P5, P6, P7, P11
  • The applicant for the Buckingham Hotel aparthotel Report P30, P31, P33
  • A neighbour at the Buckingham Hotel site on St Johns Road Report P36, P69
  • Buxworth Residents Group Report P108, P109
  • Network Rail in relation to the Marsh Lane battery site Report P111, P116
  • Derbyshire County Council as the future adopter of the Harpur Hill access road Report P12

Timeline

  • 24 October 2025: Applicant's rebuttal submitted for the Buckingham Hotel Report P32, P33
  • 29 October 2025: Applicant's letter regarding 12-week delay in receiving the viability report Report P30, P31
  • 30 October 2025: Conservation Officer further comments and viability consultant assessment on the Buckingham Hotel Report P41, P55
  • 31 October 2025: Independent Viability Consultant, Local Highway Authority, and Natural England responses received for the Buckingham Hotel Report P52, P66, P73
  • 3rd November 2025: Development Control Committee meeting Report P1

Plain English for the jargon

  • EBITDA: Earnings Before Interests, Taxes, Depreciation, Amortization, a financial measure used in viability assessments
  • BS4142:2014: British Standard method for rating industrial and commercial sound at residential receptors
  • SUDS: Sustainable Urban Drainage System, a drainage feature that manages rainwater runoff
  • BCIS: Building Cost Information Service, a construction cost data source used for viability testing
  • TPO: Tree Preservation Order, which protects specific trees from being cut down or damaged
  • S73 application: An application under Section 73 of the Town and Country Planning Act to vary or remove conditions on an existing permission
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/53

Resolved

That the update sheet be noted.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Development Control Committee

3rd November 2025

HPBC DEVELOPMENT CONTROL COMMITTEE

UPDATES REPORT

ITEM 1 – HPK/2023/0488 – Land at Burlow Road and Heathfield Nook Road, Harpur Hill

Two additional letters of objection has been received stating:

Parking – People living on the estate roads already park partially over the pedestrian walkway forcing pedestrian onto the road. The existing parking spaces are too narrow, therefore the parking for this development should be improved. Low level wooden vehicle barriers should be provided to prevent people parking on grass verges.

The area experiences significant parking difficulties, particularly during football matches, the absence of any designated parking results in congestion, double parking which poses a safety risk. The provision of a facility on the sports field, including a car park does not appear to be included in the current proposal.

Location of site office, storage – Barratts have recently said that they will be using the SUDS area for these activities. Object to this as it will involve the loss of biodiversity. Perhaps Barrats can use the area for the new community facilities instead.

Works have commenced on site with the delivery of materials, new office/storage containers, which strongly suggests that preparatory works are underway.

Officer comment

The above concerns with respect to on street parking during match days is noted. However as set out in the committee report, when the community facilities on the adjacent Haslin playing fields are delivered, this will include parking facilities. Therefore, any on street parking problems will be for a temporary period. The new facilities on the playfields will need to be the subject of a separate planning application, whereby local residents will be consulted.

Although parking may occur on the estate roads, there are no street parking restrictions, and therefore any safety concerns should be directed to Derbyshire County Council, who will be adopting the main access road or the Police.

The location of site offices, accommodation and storage facilities will be subject to an appropriate condition as set out in the committee report.

Although works appear to have commenced at the site, the developer has responded that they are only breaking up the existing surface of the former compound area, and have not commenced any works in connection with this planning application.

ITEM 2 – HPK/2024/0275 – Land at Waterswallows Road, Fairfield, Buxton Further Comments from Environmental Health

Paragraph 7.77 of the Committee Report refers to the fact that some of the elements containing within the Noise Management Plan requested by Environmental Health are not enforceable and that further comments would be sought from this consultee to understand whether this would impact their position. Further comments have been received as follows:

“Following further review of the noise impact assessments in relation to the previously proposed conditions, the following conditions are required to ensure nearby residential receptors are not impacted by noise from the proposed activities. It should be noted that the assessment undertaken focused primarily on night-time noise impacts and took account of specified parameters which included vehicle movements, and therefore the sound limit should suffice. It is up to the operator to manage this whether by a formal noise management plan or not.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
update sheet /53Appendix to 119 KB Download
PDF
Update SheetReport 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
RM
Councillor Robert McKeownChair, present
SE
Councillor Simon EvansVice-Chair, absent
AB
Councillor Alan BarrowCommittee Member, present
CF
Councillor Charlotte FarrellCommittee Member, present
SG
Councillor Stewart GardnerCommittee Member, present
LG
Councillor Linda GroobyCommittee Member, present
AH
Councillor Adrian HopkinsonCommittee Member, present
IH
Councillor Ian HuddlestoneCommittee Member, apologies
DL
Councillor David LomaxCommittee Member, present
PR
Councillor Peter RobertsCommittee Member, present
GS
Councillor Gillian ScottCommittee Member, present
JT
Councillor Jean ToddCommittee Member, apologies

All 21 on the meeting page

On this subject at High Peak

Search all
  1. Update SheetThis decision
  2. Update SheetNoted
  3. Update SheetNoted
  4. Update SheetNoted
  5. Update SheetNoted
  6. Update SheetNoted

More from High Peak Development Control Committee

All decisions
MeetingDecisionOutcome
10 Aug 2026 Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. Approved Open
10 Aug 2026 Update SheetThat the update sheet be noted. Noted Open
10 Aug 2026 Planning ApplicationsThat the report be noted. Noted Open
10 Aug 2026 HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... Approved Open
10 Aug 2026 HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... Approved Open