Development Control Committee, Monday 3 November 2025 at 1.30pm

HPK/2025/0296 - Land at Marsh Lane, New Mills

Approved Planning 1 paper

AI summaryHigh Peak Borough Council's Development Control Committee approved a variation to condition 23 for a battery storage facility at Land at Marsh Lane, New Mills, setting revised timescales for removal of equipment and restoration to agricultural land.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedwith revised wording of condition 23
MoneyNot stated
What happens nextDelegated authority for wording changesHead of Development Services, with the Chair
Who it affectsDeveloper and siteBattery storage site at Marsh Lane, New Mills

What was decided

The application was approved as set out in the report, subject to the revised wording of condition 23 as set out in the update sheet. Report P1

The Head of Development Services was given delegated authority to make wording changes to the decision, in consultation with the Chair, provided the changes do not exceed the substantive nature of the Committee's decision. Report P3

Why

The recommendation followed careful consideration of all the issues raised through the application process and thorough discussion with the applicants. Report P4

The case officer sought solutions to secure a development that improves the economic, social and environmental conditions of the area, in line with paragraph 187 of the National Planning Policy Framework. Report P4

What happens next

The Head of Development Services can make minor changes to conditions, informatives, planning obligations or reasons prior to the decision being issued, in consultation with the Chair. Report P3

Options considered

  • Chosen: Approve variation to condition 23 of HPK/2023/0193 with revised wording. Careful consideration of issues raised and discussion with applicants Report P1, P4
  • Chosen: Delegate authority to Head of Development Services for wording changes. To allow flexibility before the decision is issued Report P3

Implications

  • Legal: A planning condition is varied to set a 35 year operational limit, with alternative triggers for earlier removal of battery equipment and structures. Report P1, P2
  • Environment: After removal, the site must be restored to an agricultural field in line with a scheme approved under condition 22. Report P2
  • Risk: Delegated authority is limited to changes that do not exceed the substantive nature of the Committee's decision. Report P3

Who and where

  • The developer of the battery storage facility Report P1, P2
  • The Local Planning Authority Report P2
  • Land at Marsh Lane, New Mills Report P1, P2

Timeline

  • Within 35 years of operational use, or 12 months of cessation, or 6 months of permanent cessation of construction, whichever is sooner: Batteries, transformer units, inverters, associated structures and fencing must be dismantled and removed from the site. Report P2
  • No later than 28 days following cessation of operational use: The developer must notify the Local Planning Authority in writing. Report P2
  • No later than six months following the cessation of power production: The site must be restored to an agricultural field in accordance with the scheme approved under condition 22. Report P2
  • A period of 24 months with no substantial development anywhere on the site: This is taken as a permanent cessation for the purposes of the condition. Report P2

Plain English for the jargon

  • NPPF: National Planning Policy Framework, the national planning policy document for England.
  • Local Planning Authority: The council body responsible for determining planning applications, here High Peak Borough Council.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/61

Resolved

That the application be approved as set out in the report, subject to the revised wording of condition 23 as set out in the update sheet; and 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/informatives/planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Development Control Committee

HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE

Date 3 November 2025

Application HPK/2025/0296 No: Location Land at Marsh Lane, New Mills Proposal Application to vary Condition 23 in relation to HPK/2023/0193 Applicant Renewables Ltd (Innova) Agent Evan Williams, ADAS Planning Parish/ward New Mills East / New Mills Date registered 13th Aug 2025 If you have a question about this report please contact: James Stannard, Tel. 01298 28400 extension 4298, [email protected]

SUMMARY OF RECOMMENDATION

Approve

1. REASON FOR COMMITTEE DETERMINATION

1.1This application has been brought before the Development Control Committee owing to the fact that it relates to a previous Major application relating to the same site that also generated significant public interests, that was considered and determined by Committee.

2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS

2.1The application site comprises a triangular parcel of agricultural land that spans an area of approximately 2.4ha situated north of Marsh Lane, at the fringes of New Mills, with the public highway running parallel with the boundary on its south-western side.

2.2The site benefits from an existing field gate access from Marsh Lane, which connects Furness Vale to New Mills, which is characterised by maintained grassland bordered by mature trees and other natural vegetation including hedgerows.

2.3The strong boundary treatment described above provides considerable screening to nearby visual receptors (e.g. public footpaths) and nearest residential properties.

2.4The nearest footpaths to the site are (1) Footpath Ref: HP19/158/1 that runs northwards from Marsh Lane on the northern side of the railway in the direction of Beard Hall Farm, (2) Footpath Ref: HP19/106/2, which runs westwards to New Mills from Gow Hole Farm, and (3) Footpath Ref: Footpath Ref: H19/156/1 that runs north-eastwards from Dolly

1 Lane, near to the junction with Marsh Lane, in the direction of Beardwood Farm.

2.5The site slopes eastwards away from the highest point of the site close to a railway bridge which spans the Manchester – Sheffield railway, which runs west-east parallel to the northern boundary of the site.

2.6The nearest residential properties to the site are located on Marsh Lane, with the nearest being Gow Hole Farmhouse. A row of three properties (Nos. 3, 5 and 7 Carr View Cottages) are situated a short distance beyond the railway bridge to the north-west.

2.7The Peak District National Park boundary is located some 1.2km north- east of the site at its nearest point in an elevated position some 150m higher than the application site.

2.8As shown by Figure 1 within the supporting Planning, Design and Access Statement, there are a number of Listed Buildings within a 1km radius of the site, with the nearest heritage asset located within the built up area of Furness Vale.

2.9For the purposes of the Local Development Plan, the site lies outside of the built-up area boundary of any town or village, in the open countryside, and constrained by the North Derbyshire Green Belt.

2.10The application benefits from an extant full planning application that was granted under HPK/2024/0193 on 17th January 2025 for development which is yet to be implemented, described as follows:

“Construction and installation of an Energy Storage System (ESS) including the formation of site levels and associated access, landscaping and site infrastructure”

2.11Condition 23 that was applied to this decision states the following:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HPK/2025/0296: Land at Marsh Lane, New MillsReport 877 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
RM
Councillor Robert McKeownChair, present
SE
Councillor Simon EvansVice-Chair, absent
AB
Councillor Alan BarrowCommittee Member, present
CF
Councillor Charlotte FarrellCommittee Member, present
SG
Councillor Stewart GardnerCommittee Member, present
LG
Councillor Linda GroobyCommittee Member, present
AH
Councillor Adrian HopkinsonCommittee Member, present
IH
Councillor Ian HuddlestoneCommittee Member, apologies
DL
Councillor David LomaxCommittee Member, present
PR
Councillor Peter RobertsCommittee Member, present
GS
Councillor Gillian ScottCommittee Member, present
JT
Councillor Jean ToddCommittee Member, apologies

All 21 on the meeting page

On this subject at High Peak

Search all
  1. HPK/2025/0296 - Land at Marsh Lane, New MillsThis decision
  2. HPK/2026/0146 - Land at St Georges Rd, New Mills DerbyshireRefused
  3. HPK/2023/0328 - Portland Nursing Home, 8 Park Road, BuxtonApproved
  4. HPK/2025/0340 - Hargate Hill Equestrian Centre Hargate Hill, Glossop - Retrospective application for change of use of land for the siting of caravans for residential occupation with associated developmentRefused
  5. HPK/2025/0447 - Land at Crossings Road, Chapel-en-le-FrithApproved
  6. HPK/2024/0496 - Land off Brown Edge Close, BuxtonApproved

More from High Peak Development Control Committee

All decisions
MeetingDecisionOutcome
10 Aug 2026 Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. Approved Open
10 Aug 2026 Update SheetThat the update sheet be noted. Noted Open
10 Aug 2026 Planning ApplicationsThat the report be noted. Noted Open
10 Aug 2026 HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... Approved Open
10 Aug 2026 HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies