Note the changes made to the Delivery Plan organisation and governance structures as agreed by Cabinet in December 2022 and March 2023; 2. Note the programmes that have been added to the People Portfolio of the Delivery Plan following Cabinet approval in December 2022 and ... view the full minutes text for item 4.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Overview and Scrutiny Committee, 12 pages
Background
3.1The Delivery Plan, which was approved by Cabinet on 5 July 2022 and Council on 20 September 2022, describes the activity that the Council will deliver to meet the priorities, objectives and ambitions set out within the Corporate Plan and the process and approach that will be followed to ensure success.
3.2Considerable progress has been made with Programmes and additional work has been completed to refine the governance approach for projects and programmes to provide greater oversight to support successful delivery.
3.3The Delivery Plan proposed that a report describing progress for all projects and programmes in the Delivery Plan should be presented quarterly to Cabinet and Overview and Scrutiny Committee to provide elected Members with oversight of the Delivery Plan and the opportunity to scrutinise progress in between the formal decision-making gateways.
4. Delivery Plan Organisation and Governance Changes
Place Portfolio
4.1In mobilising the Delivery Plan following approval by Cabinet in July 2022 it was recognised that there is a beneficial opportunity to realign the governance and oversight for place-based activity and a revised governance proposal for this activity was developed.
4.2This proposal was made to enable decision-making about what should be done in a “place” to be joined-up to ensure a holistic and aligned perspective on:
4.2.1. “Everything” we want / need to do in a place to meet our objectives
4.2.2. How the required activity can be funded
4.2.3. How the required activity can be prioritised 4.2.4. The overall business case for “transformation” of a place
4.3Cabinet agreed in December 2022 that all development activity to the built or natural environment to transform the place in line with the council’s strategic objectives be delivered and governed through a new Place Portfolio.
4.4Since this approval officers have progressed work to set up the portfolio. One of the key components of which is to define the programmes within the portfolio structured around the different places in Hounslow.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.