CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Royal Borough of Kingston upon Thames
Surbiton Neighbourhood Committee, Wednesday 1 February 2006 at 7.30pm

PLANNED HIGHWAYS MAINTENANCE 2006/7

Deferred Committee 2 papers

Surbiton Neighbourhood Committee deferred this item on Wednesday 1 February 2006. Below is the council's own wording, with the papers it was decided on.

Item70

Resolved

RESOLVED that: 1. the footway and carriageway schemes listed in Annex 1 to these Minutes be included in the planned maintenance programme for 2006/2007. 2. the allocation of the remainder of the maintenance budget be deferred to the next meeting to allow for an assessment of the condition of Arlington Road and Pine Walk to take place. Reason for Decisions To determine the planned highway maintenance programme for 2006/07.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Surbiton Neighbourhood Committee

Summary

This report updates the Committee on the progress being made to reduce the backlog of carriageway and footway maintenance works. It includes information regarding the relevant Best Value Performance Indicators (BVPI’s) for the Borough as a whole and for each Neighbourhood. This information is being used to identify the needs and priorities for resource allocations to achieve the Borough’s required performance targets. The report also lists the footway and carriageway locations, within the Neighbourhood, where responsive maintenance is no longer considered appropriate, viable and/or economic for maintenance purposes. The Committee is asked to determine those schemes they feel should be included in the 2006/07 planned maintenance programme.

Recommendations

It is RECOMMENDED that footway and carriageway schemes be chosen from those listed in Annex 1 to be included in the planned maintenance programme for 2006/2007.

Reason for recommendations

So that the planned maintenance schemes for 2006/07 can be determined and Officers can proceed with the management and implementation of the highway maintenance programme.

Background

1. Due to budget constraints, from the mid 1980’s to the late 1990’s, a large backlog of maintenance works developed for both carriageways and footways. In order to address this situation, the Council has taken advantage of flexibility allowed under its Local Public Service Agreement (LPSA) and under the Government’s Prudential Borrowing arrangements to enable an initial capital investment programme of £6.5m between 2004/05 and 2006/07. This has also been supported and helped by the Neighbourhood Committees allocating an additional £465k from their Discretionary Budgets.

HIGHWAY MAINTENANCE

Local Public Service Agreement (LPSA)

2. In 2003/04 the Borough agreed a package of 12 targets to form an LPSA with Government. This included a transport target, which related to highway C2

maintenance, based upon the condition of our non-principle classified roads and unclassified roads.

3. In order for our LPSA transport targets to be accepted, it had to be demonstrated that:

• the “stretch” targets are beyond those which could be achieved in normal circumstances; • the Council has defined constraints in achieving the targets; and • it is proposed to use available resources in a different way to support the agreement.

If the “stretch” targets are achieved, the Council receives a financial reward.

4. 2005/06 was the last year of the three year agreement period and it can now be reported that the LPSA targets for carriageway maintenance works have been achieved and surpassed:

2003/04 2004/05 2005/06 2005/06 Target Actual Non-principal Classified 12.8% 12.0% 9.0% 8.5% Unclassified 17.9% 12.2% 14.0% 8.7%

Best Value Performance Indicators (BVPI’s)

5. The Council is obliged to publish national Best Value Performance Indicators (BVPIs) as follows: - for Principal Roads (BVPI 96 NOW BVPI 223), - for Non-principal Classified and Unclassified Roads (BVPI 97a and b) - for Class 1 and 2 Footways (BVPI 187). The prescribed method of surveys and analysis to be used is UKpms (United Kingdom pavement management system). BVPI 96, for Principal Road carriageways, is based upon the London-wide surveys commissioned by TfL and undertaken by the LB of Hammersmith and Fulham. For BVPI 97 (a) and (b) and BVPI 187, UKpms surveys are commissioned and funded by the Borough.

6. The BVPI relating to the condition of carriageways is defined as follows: “To measure the percentage of roads which have exceeded the point at which surface or structural repair of the carriageway should be considered.”

The results for the past four years for the whole Borough are:

2001/02 2002/03 2003/04 2004/05 2005/06 Principal = 0.2% 12.0%* 3.9% 2.6% N/A Non-princ. Class. = 15.0% 12.6% 15.0% 14.1% 8.8% Unclassified = 17.5% 19.0% 18.0% 11.7% 7.6%

(* Corrected figure)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
to the Minutes: Planned WorksAppendix 1 13 KB Download
PDF
PLANNED HIGHWAYS MAINTENANCE 2006/7Report 37 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
DB
Councillor David BerryMember, present
RB
Councillor Robert BlevinMember, present
DB
Councillor David BoothMember, apologies
JB
Councillor Janet Bowen-HitchingsMember, present
DK
DAVIS, Kevin JohnMember, present
PF
Councillor Patricia FranksCo-Chair, present
PJ
Councillor Paul JohnstonMember, present
OB
O'MAHONY BarryCo-Chair, in the Chair, present
MR
Councillor Maureen RowleyMember, apologies
LG
Councillor Liz GreenMember, present
JS
Councillor Jane SmithMember, present
YY
Councillor Yogan YoganathanMember, present

On this subject at Kingston upon Thames

Search all
  1. PLANNED HIGHWAYS MAINTENANCE 2006/7This decision
  2. Planned Highways and Street Lighting Capital Programme 2022/23Noted
  3. Planned Highways Maintenance 2010/11Agreed
  4. Planned Highways Maintenance 2010/11Decided
  5. Planned Highways Maintenance 2010/11Decided
  6. Planned Highways Maintenance 2010/11Decided

More from Kingston upon Thames Surbiton Neighbourhood Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Community Grants ProgrammeRESOLVED that: ( i ) the application for a £2,800 Neighbourhood Community Grant from Surbiton Town Centre Partnership... Approved Open
9 Jun 2026 Appointment of Chair and Vice-ChairRESOLVED that: 1. Councillor Tom Reeve be appointed Chair of the Committee for the Municipal Year 2026/27 until the f... Decided Open
9 Jun 2026 Double Yellow Lines on Villiers Avenue - Objections to Traffic Management OrderRESOLVED that: 1. the comments and objections received on the Traffic Management Order (TMO) on conversion of Single ... Noted Open
9 Jun 2026 Planning ApplicationsRESOLVED to PERMIT subject to the conditions set out in the report including such amendments, additions and/or deleti... Decided Open
9 Jun 2026 Councillor Ward Funding Arrangements 2026/27RESOLVED that the Committee’s current working arrangements for the allocation of Councillor Ward Funding, as set out ... Decided Open