The City Focus Delivery Plan for the City Centre SRB and SIA Programmes 2004/05 (REG/6)

Approved Executive 1 paper

Executive Board approved this item on Friday 23 July 2004. Below is the council's own wording, with the papers it was decided on.

Item11b

Resolved

Resolved that – (i) the Delivery Plan, at Annex 1 submitted, be approved and its submission to the North West Development Agency (NWDA), be supported; (ii) subject to the approval of the Delivery Plan by the NWDA and Government Office North West (GONW) and the receipt of an offer of grant funding, the amendment to the City Council’s revenue budget for the financial year 2004/05 to incorporate £2,012,189 expenditure funded by SRB grant and £768,158 expenditure funded by European Regional Development Fund (ERDF) grant, as illustrated at Annexes 2 and 3 of the report, submitted be approved; (iii) subject to the approval of the Delivery Plan by the NWDA and GONW and the receipt of an offer of grant funding, approve the amendment to the City Council’s capital programme in the financial year 2004/05 by £664,664 to reflect additional expenditure funded by SRB grant and £5,255,411 to reflect additional expenditure funded by ERDF grant, as illustrated at Annexes 2 and 3 of the report submitted be approved; (iv) the Executive Director (Regeneration) be authorised, in his capacity as a City Council Chief Officer, to allocate SRB funds to projects on behalf of the City Council in accordance with the approved Delivery Plan and Standing Orders and Financial Regulations, once it has been approved by the NWDA and the Cityfocus Board; (v) the Assistant Executive Director (Financial Management) be authorised to create new cost centre codes and amend the budget accordingly for revenue schemes which have received Board Approval where the NWDA has approved general resources that can be allocated to specific schemes by the Partnership Board; (vi) the Executive Director (Regeneration) be authorised to submit the necessary applications for funding for projects included in the Delivery Plan and to act as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and (vii) commitment of capital expenditure totalling £2,307,034 for all SRB projects as shown on at Annex 2 submitted be approved.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 31 pages

Executive summary

The purpose of the report is to present to Executive Members the Cityfocus Delivery Plan for the city centre Single Regeneration Budget (SRB) and Strategic Investment Area (SIA) programmes for 2004/5.

Background

Cityfocus is the delegated board of Liverpool Partnership Group (LPG) with responsibility for the day to day management of the city centre SRB and SIA programmes. Every year Cityfocus is requested by Government Office in the North West (GONW) and North West Development Agency (NWDA) to produce a delivery plan for each programme detailing the projects it expects to support. This year for 2004/5 a combined plan has been produced to provide a more comprehensive and user friendly guide to investment in the city centre.

The plan was approved by the Cityfocus Board on 5 February 2004 and endorsed by Liverpool First Board and LPG partners on 24 February 2004. There was than a delay with the NWDA regarding all funding for 2004/5 and beyond. This situation was only resolved once the NWDA had completed its review of all its financial commitments over the next three years. As a consequence there have been some amendments to the SRB elements of the Delivery Plan since the approval by the Cityfocus Board as a result of a reprofiling of expenditure for the Cruiseliner Facility. These were approved in principle by the Cityfocus Board on 10 June 2004. These amendments have been included in this report to give the most up to date information. The SIA programme is currently under review and an update will be provided later in the year. Please note that Liverpool City Council is the accountable body for the SRB programme and a number of SIA projects. Progress in 2003/04

An evaluation was carried out in 2003/4 following the major changes to the organisation of Cityfocus in the previous year and a bringing together of the 2 programmes. This confirmed that our adoption of a more integrated approach to the city centre in recognition of its role as a key driver is hugely important. Both programmes are now at a significant stage and largely committed to projects.

Achievements

Notable success in 2003/4 include:

• The Liverpool Jobs Education and Training (JET) Service exceeding its target number of people from priority areas into jobs. • Major public realm works such as those at Williamson Square and the Cavern Quarter are well underway. • The new grand entrance to Liverpool Metropolitan Cathedral is completed. • Mersey Maritime has attracted 2 major maritime companies to the city centre bringing with them 140 new jobs. • Over £8 million was invested in 2003/4 by the 2 programmes.

Summary of Outputs

The Delivery Plan shows that the combined effect of the Programmes will bring about 300 new jobs in the city centre over the coming year and 1,400 residents will secure employment through the JETs.

Summary of Key Indicator Report

An important element of the Delivery Plan is the Key Indicator Report, which provides a snapshot of the year. For the environment element of the programmes example, key indicators are the completion the public realm schemes in Williamson Square and Cavern Quarter by October. The completion of the development at 101 Old Hall Street in May and the grand opening of St George’s Hall by March 2005.

The Economy Programme will continue to develop key business support mechanisms for city centre businesses. Key indicators of performance will therefore be the completion of the ‘How to profit through e-business’ course by December and Mersey Maritime delivering a cruise liner conference in the city by March 2005.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The City Focus Delivery Plan for the City Centre SRB and SIA Programmes 2004/05 (REG/6)Report 31 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. The City Focus Delivery Plan for the City Centre SRB and SIA Programmes 2004/05 (REG/6)This decision
  2. 2007/8 Cityfocus Delivery Plan for the City Centre SRB and SIA Programmes (SI/8)Approved
  3. Cityfocus SRB Delivery Plan 2006/07 - Programme Amendments (SI/5)Approved
  4. City Focus Delivery Plan 2006/07 Plan for City Centre SRB and SIA Programmes (RT/14)Approved
  5. City Focus SRB Delivery Plan 2005/06 Programme Amendments (RT/3)Approved
  6. City Focus Delivery Plan for the City Centre SRB and SIA Programmes 2005/06 (REG/10)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies