Resolved that – (i) the revised position of the 2005/06 Cityfocus Delivery Plan be approved; (ii) the capital programme of the City Council be amended to reflect reduced expenditure of £464,673 of SRB projects and SRB grant bringing the total capital expenditure to £2,229,430 as detailed in Annex 1 submitted; (iii) the revenue budget of the City Council be amended to reflect reduced SRB expenditure and SRB grant of £71,569 as detailed in Annex 1 submitted; and (iv) subject to prior approval by the City Focus Board and consultation with the Executive Member (Regeneration and Transport) (as required by the Council’s Constitution) and with the Executive Member (Resources), the Executive Director (Regeneration) and the Executive Director (Resources) be authorised to approve new projects and to vire SRB grant between projects and between the Revenue and Capital programmes within the SRB/SIA Programme in the last quarter of the 2005/2006 financial year in order to commit expenditure and achieve programme outputs or respond to specific needs, (CHS/37)
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to inform Executive Members of adjustments to the approval of the Cityfocus Delivery Plan in order to ensure the full implementation of the Programme and to amend the City Council’s Capital Programme accordingly.
Background
The NWDA and the Executive Board approved the combined SRB and SIA Delivery Plan for 2005/6 in June 2005. The Delivery Plan detailed the projects and the expected levels of investment. The financial breakdown was £2,694,103 capital and £2,058,491 revenue in 2005/6 to reflect the proposed allocation and spend of SRB resources.
During the course of the year the Cityfocus Board receives regular reports on the performance of the approved Programme, with the primary focus on ensuring that the programme is fully implemented. As part of this there is provision for projects being developed but not formally agreed until later in the year. This report details the amendments required to the City Council’s capital and revenue programmes to reflect the necessary changes to the SRB programme.
Financial Progress
Annex 1 provides details of the revised forecasts for existing projects and additional projects which have been approved since the Delivery Plan by the Cityfocus Board and now form part of the programme for the current financial year. Executive Members Peter Millea and Keith Turner Director Charlie Parker recommendations:
It is recommended that: 1) The revised position of the 2005/06 Cityfocus Delivery Plan be approved. 2) The capital programme of the City Council be amended to reflect reduced expenditure of £464,673 of SRB projects and SRB grant bringing the total capital expenditure to £2,229,430 as detailed in Annex 1; 3) The revenue budget of the City Council be amended to reflect reduced SRB expenditure and SRB grant of £71,569 as detailed in Annex 1; and 4) Subject to prior approval by the City Focus Board and consultation with the Executive Member for Regeneration (as required by the Council’s Constitution) and with the Executive Member for Resources, the Executive Director (Regeneration) and the Executive Director (Resources) be authorised to approve new projects and to vire SRB grant between projects and between the Revenue and Capital programmes within the SRB/SIA Programme in the last quarter of the 2005/2006 financial year in order to commit expenditure and achieve programme outputs or respond to specific needs,
Key Decision:
Yes
Forward Plan:
Yes .
Implementation effective from:
24 February 2006
Timescale for action:
It is important that approval is given to enable smooth delivery of the SIA and SRB programmes for the remainder of this financial year
Reason(s) for Recommendation:
To agree the City Centre SRB programme 2004/5 amendments to the capital and revenue programmes. Alternative options considered:
Not to amend the Programme – this would result in the failure to fully implement the Programme and spend the approved SRB grant.
Consultation
Consultation has been undertaken with Cityfocus Board and Working Groups, NWDA and Regeneration Finance who have agreed to the proposed amendments to the 2005/6 SRB programme.
Consultation with Ward Councillors and outcome:
None directly on this recommendation. However there is Council Member representation on the Cityfocus Board and Working Groups.
Financial implications: On approval of the report, the City Council’s budgets will be adjusted as per Annex 1 to reflect changes to the SRB programme. There are no additional requirements for City Council resources as all costs are SRB grant funded.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.