Resolved that - (i) authority be granted to establish budgets for those new schools’ projects as set out in the body of the report submitted; (ii) authority be granted to increase the budget in connection with the Alsop High School BSF scheme (BEESK19) by £1,000,000 financed from the 2010/11 Planned Maintenance Fund, to contribute to the completion of backlog maintenance works; (iii) authority be granted to commit expenditure as requested within this approval and for the Executive Director (Children, Family and Adult Services) to accept quotations or tenders up to the value of the approved budgets at the appropriate time; (iv) authority be granted for the Executive Director (Children, Family and Adult Services) to commit expenditure up to £25,000 against unforeseen and emergency projects as required to be financed from the balance of approved capital funding; all decisions to be reported in the next available quarterly report; (v) authority be granted to create a capital budget from a revenue contribution of £1.7m to finance the Planned Maintenance Fund for 2010/11. The balance of funding of £182,459 to be retained as revenue to finance scheme development costs; (vi) the Assistant Executive Director (Strategy) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grants; (vii) Officers be requested to explore opportunities through the procurement of schemes within the Schools’ Capital Programme to maximise local employment and apprenticeship opportunities where possible; and (viii) the capital programme be amended accordingly.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to seek authority to establish budgets for specific schools’ capital projects from central government grant and supported borrowing allocations for 2010-11
Background Information and Context
The School’s Capital Programme comprises a diverse range of projects aimed at tackling specific asset management priorities at schools relating to condition, suitability and sufficiency, the delivery of national and local strategies such as the implementation of the Primary Capital Programme and BSF, Corporate aims and objectives and those set out in the Corporate Asset Management Plan and Capital Strategy.
The programme underpins the priorities set out in the Children’s and Young Peoples Plan, and by investing in the futures of young people by improving the quality of their learning environments, the programme directly supports the City Council’s aims of developing first rate education and training from early years and those Corporate aims that will:
• Ensure safeguarding and inclusion of the most needy and excluded groups in the city providing equality and real opportunity for improvement and enhanced quality of life;
• Confront barriers to employment and training through lack of access, deprivation, discrimination and poor health to ensure provision of a highly skilled workforce
• Challenge crime and antisocial behaviour safeguarding young people from becoming perpetrators or victims
• Provide sustainable communities through access to decent homes and best practice in environment management including, recycling, street cleansing and environmental enforcement against dereliction and environmental detractors. 2. Sources of Funding
The majority of projects are financed by a variety by central government grant and annual supported borrowing allocations and the programme also includes a number of specific one- off initiatives financed by other grant funding and approved general resources.
3. Option Appraisal
Projects are put forward for inclusion into the programme after being identified as priorities and the subject of option appraisals specific to each sub programme. For example, planned maintenance schemes are determined following asset management surveys and quarterly updates provided by 2020 Liverpool having regard to potential linkages with other programmes, school organisation proposals and health and safety implications. Technical solutions for each of these proposals will then factor in overall cost and value for money, proportionality and scale in relation to the nature of each project, lifecycle (e.g. initial cost compared to longer term benefits that may accrue in the form of revenue savings) and the potential benefits from delivering a more holistic solution to a project (e.g. incorporating a number of planned maintenance items as part of a larger refurbishment plan).
New projects are submitted for approval following the consideration of individual business cases by the Corporate Regeneration Group.
4. Value for Money
Value for money considerations are a key factor in determining both the initial programme proposals and the technical solutions for each scheme as outlined above recognising that the driving factors and objectives for many sub-programmes will be determined by the funding agencies themselves, principally central government.
Planned maintenance schemes have VFM benefits resulting from for example:
• Reductions in maintenance backlog and ongoing repairing liabilities for schools; • Sustainability benefits and the reduction in the cost of utilities as a result of the installation of more energy efficient systems through electrical and heating upgrades
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.