Schools' Capital Programme - 2009/10 projects (ESE/6)

Approved Executive

Executive Board approved this item on Friday 31 July 2009. Below is the council's own wording, with the papers it was decided on.

Item40c

Resolved

Resolved that - (i) the revised capital allocations for the Schools’ Capital Programme for 2009/11 as set out in Appendix 1 submitted be accepted; (ii) authority be granted to establish budgets for those new projects as set out in Appendix 2 submitted; (iii) a School Travel Plan for Broadgreen Primary School in the sum of £5,320 be accepted and allocated to the school; (iv) authority be granted to commit to expenditure as requested within the approval and for the Executive Director (Children, Family and Adult Services) to accept quotations or tenders up to the value of the approved budgets at the appropriate time; (v) authority be granted to commit the balance of programme contingency against project overspends and/or reserve projects as funding permits; (vi) an allocation of £1,091,345 be set aside from the Primary Capital Programme grant towards the rebuilding of Faith Primary School comprising £800,000 in 2009/10 and £291,345 in 2010/11; (vii) the amendments to the Capital Programme as set out in Appendix 2 submitted be approved; (viii) authority be granted to create a capital budget from a CERA contribution of £1.371m to finance the Planned Maintenance fund. An additional £250,000 CERA contribution be established to finance the 2009/10 Sporting Playground programme in accordance with the approval of the Executive Board of 30th March 2007. The balance of funding of £145,000 to be retained as revenue to finance scheme development costs; and (ix) the capital programme be amended accordingly.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

Who was there

14 of 19 attended
WB
Councillor Warren BradleyChair, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RG
Councillor Ron GouldMember, present
PK
Councillor Paula KeaveneyMember, apologies
GM
Councillor Gary MillarMember, apologies
PM
Councillor Peter MilleaMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
PT
Councillor Paul TwiggerMember, present
CH
Colin HiltonOfficer, present
RC
Robert CorbettOfficer, present

All 19 on the meeting page

On this subject at Liverpool

Search all
  1. Schools' Capital Programme - 2009/10 projects (ESE/6)This decision
  2. Schools Capital Programme 2010/11 (ESE/44)Approved
  3. Kingsley and St Silas Primary Schools - capital building works following completion of Phase 2a Primary Review (ESE/34)Approved
  4. Schools' Capital Programme 2009/10 - Update (ESE/35)Approved
  5. Building Schools for the Future Wave 2 Capital Programme and Associated 2020 Liverpool Consultancy Services (CHS/34)Approved
  6. Construction Framework for the Delivery of Building Schools for the Future Wave 2 Capital Projects (CHS/35)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open