63/2011 The Cabinet approved the continuation of the current Bereavement and Registration Services Grounds Maintenance Contract and to subject the contract to further Gateway 4 and/or Gateway 5 reporting requirements. Reasons: T here are no adverse observations regarding this contract and the contractor is performing to a standard equal or better than that set out in the contract specification.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report provides Cabinet with a review on the progress of the Bereavement & Registration Services – Grounds Maintenance Contract, which is currently awarded to The Landscape Group (which was previously English Landscapes).
This is based upon the procurement process which was undertaken during 2008 and which led to an award of contract on 1 September 2008.
The commencement and delivery of this procurement requirement was by the Cabinet on 17 July 2007 (decision 140/2007 refers). The subsequent approval for contract award was provided by the Cabinet at Procurement Gateway 3 on 24 June 2008 (decision 149/2008 refers).
This Procurement Gateway 4 report has been approved for submission to Cabinet after review and discussion at the Business Support Directorate Management Team meeting on 22 March 2011 and the Strategic Procurement Board on 30 March 2011.
1. Budget and Policy Framework
1.1Post Project Appraisal / Contract Management
1.1.1 This procurement post project appraisal and its subsequent review is within the Council’s policy and budget framework and ties in with all the identified Core Values, Strategic Priorities, Strategic Council Obligations and Departmental/Directorate service plans as highlighted within the Procurement Gateway 1 Report. 2. Background
2.1Contract Details
2.1.1 This contract is a Services contract
2.1.2 Contract Description
The contract is for the provision of grounds maintenance activities at Medway Crematorium and 5 cemeteries across Medway. The works include grass cutting; litter collection; road and hard surface cleaning; the maintenance of tress, hedges, roses, flower and shrub borders; the fixing of memorials and some premises security. These works help meet the service objectives which aim to provide well maintained grounds for the bereaved, that generate minimal complaint and give high levels of user satisfaction.
2.2Permissions Required
2.2.1 This report provides Cabinet with a post project appraisal and seeks permission to continue this termed contract for the remainder of the contract, which is due to expire on 31 August 2013.
2.2.2 This request is on the basis that this contract has fulfilled the requirements in accordance with the service specification and associated contract terms and because no major issues have been identified which cause concern for further continued contract management reporting to the Strategic Procurement Board and Cabinet.
2.2.3 It is acknowledged that if this option is granted, in the event of any major issues arising for the remainder of the contract term, a Gateway 5 report will be submitted with immediate effect for review by the Strategic Procurement Board or if so required and instructed for review by the Strategic Procurement Board during the remainder of the contract term.
2.2.4 This report had been referred back from a previous meeting of the Procurement Board requesting that officers look at opportunities for making financial savings from the contract sum. That work has been completed and included in the Exempt part of this report.
Options
In arriving at the preferred option as identified within Section 4.1 ‘Preferred Option’, the following options have been considered with their respective advantages and disadvantages.
3.1Conclude Current Contract and Provide Action Plan
The option of concluding the current contract at the end of the contract term on the basis that it is a one-off procurement requirement and providing an action plan for future projects has been considered and below are the advantages and disadvantages of this option:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.