Cabinet, Tuesday 5 July 2011 at 3.00pm

Gateway 3 Procurement Tender Process Review and Contract Award: Brompton Academy New Buildings

Approved Executive 1 paper

Cabinet approved this item on Tuesday 5 July 2011. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

82/2011 The Cabinet approved the Final Business Case for Brompton Academy and authorised the Director of Children and Adults, in consultation with the Portfolio Holder for Children’s Services, to submit it to Partnerships for Schools for approval. 83/2011 The Cabinet agreed to the award of the contract to construct new buildings for Brompton Academy to BAM Construction Limited using the Partnerships for Schools (PfS) Design & Build Lump Sum Contract for use with the PfS Contractor Framework along with the PfS Development Agreement. The Cabinet noted the governance arrangements described in section 7 of the report
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report presents the Final Business Case for Brompton Academy to Cabinet for approval along with the associated contract documents to approve the appointment of BAM Construction Limited as the main contractor.

1. Budget and Policy Framework 1.1 The Brompton Academy final business case presents the proposals for the new building at the existing academy site, as planned in the Medway Academy Programme approved by Partnerships for Schools (PfS) in December 2009 following approval by Cabinet (decision 223/2009). 1.2 The new academy buildings will be funded by the Department for Education following their confirmation to the council on 6 August 2010 that all 3 of the council’s proposed new academy buildings will be funded using the PfS National Framework for contractors. 1.3 The final business case is a key stage in the procurement process for the Academy Programme and is presented with the various contractual documents that support the financial close for the Brompton Academy new build project. 1.4 This report seeks Cabinet approval for financial close on the new building project for Brompton Academy and the award of the contract to BAM Construction Limited, who were selected as the Preferred Panel Member following the design competition held over summer 2010. 2. RELATED DECISIONS 2.1 On 12 May 2009 Cabinet agreed to delegate authority to the Director of Children and Adults, in consultation with the Portfolio Holder for Children's

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Procurement Tender Process Review and Contract Award: Brompton Academy New BuildingsReport 144 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, apologies
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
PB
Peter BownOfficer, in attendance

All 18 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Procurement Tender Process Review and Contract Award: Brompton Academy New BuildingsThis decision
  2. Gateway 1: Procurement of Housing Related Support ServicesAgreed
  3. Gateway 1 Procurement Commencement: Repairs and Maintenance for Temporary Accommodation Owned, One Medway Lettings, One Medway – Inspiring Change LA Hostels, Housing Revenue Account (HRA) Requirements, Medway Development Company (MDC) and the Sanctuary SchemeAgreed
  4. Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayAgreed
  5. Gateway 1 Procurement Commencement: Innovation Park Medway NorthAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies