102/2013 The Cabinet approved the Outline Business Case/Gateway 1 High Risk Report to progress to Gateway 2 of the procurement process and invite tenders for the building refurbishment and remodelling works . 103/2013 The Cabinet approved the virement of sufficient funding of £500,000 from the basic need capital programme to undertake further surveys, develop a detailed design and deal with asbestos removal, prior to the main contract works . Reasons: The new remodelled accommodation is required to enable the new primary academy to open in September 2014. The capital programme approved by Cabinet on 23 February 2013 includes funding for the project.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
CABINET 11 JUNE 2013 GATEWAY 1 PROCUREMENT COMMENCEMENT AND OUTLINE BUSINESS CASE: REFURBISHMENT AND REMODELLING WORKS AT CHATHAM PRIMARY FREE SCHOOL
Portfolio Holder: Councillor Mike O’Brien, Children’s Services Report from: Barbara Peacock, Director of Children and Adult Services
Authors: Sarah Woods, Interim Capital Programme Manager Jill Price, Category Specialist Summary
This report seeks approval of the Outline Business Case and proposed procurement route, based on an initial feasibility study and evaluation of procurement and construction options, for the new Chatham Primary Free School and permission from Cabinet to proceed to detailed design stage and Gateway 2 before requesting approval at Gateway 3.
1. Budget and Policy Framework
1.1This project supports the Council’s School Organisation Plan 2011 – 2016, approved by Cabinet on 1 November 2011 (decision number 143/2011), which highlights the need for more pupil places in the Chatham area. The Council has a statutory duty to ensure there are sufficient school places as set out in the Education & Inspections Act 2006.
1.2Subject to the approval of the Outline Business Case and the recommendations in this report, officers will develop the design and report to Cabinet for approval in compliance with the Council’s procurement rules. This will then lead to Gateway 2 where a tender exercise will be undertaken in compliance with applicable EU rules and Medway Council’s internal procurement processes and contract rules.
1.3The Outline Business Case confirms the level of funding required from the capital programme to provide the buildings for Chatham Primary Free School and makes a recommendation on the procurement option for delivering the expanded buildings. 2. Related Decisions
2.1On 12 June 2012, Cabinet approved the development of plans to use the former Chatham South site for the establishment of a new primary age Academy from September 2014, and for officers to formally notify the DfE of the council’s intention to consult with interested parties to identify a preferred provider.
3. Background/Introduction
3.1This procurement is a Works/Construction requirement
This report seeks permission to commence a new construction procurement project with a contract duration of 33 weeks, with provision to extend for a contract duration only in such circumstances as described by the contract conditions. Scheduled phase details as follows:
Contract period commencement - 6 November 2013 Contract period completion – 24 June 2014
The total value of this new procurement contract has been estimated by the quantity surveyor, and is below the EU threshold. This cost has been based on the outline designs developed by the architects.
The breakdown of the costs is included within the exempt appendix
The contract will be a traditional JCT intermediate form of contract with contractors design portion 2011 (Latest Edition) with specification and drawings.
4. Business Case
4.1Business Case Summary
4.1.1 The School Organisation Plan 2011-16 highlighted an emerging need for additional primary age provision in some areas of Medway, specifically, Chatham, Rochester and Gillingham West.
4.1.2 The forecasts using the data received in Spring 2012 indicate that the pressure on primary school places is likely to be even more severe than initially highlighted in the School Organisation Plan 2011-2016. This pressure is primarily a result of significant unforeseen inward migration. There have also been further increases in the birth rate, both of which have particularly impacted on the Chatham area. The proposals for development of additional primary age provision in Chatham paper approved by Cabinet on 12 June 2012 highlighted the emerging need for schools places in Chatham and presented options for the creation of sufficient provision to meet this further additional demand in the future.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.