Outline Business Case: Saxon Way Primary School - Expansion to Two Forms of Entry

Approved Executive 1 paper

Cabinet approved this item on Tuesday 6 August 2013. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

136/2013 The Cabinet approved the outline business case and the preferred design option (3a) to allow more detailed design work to be undertaken . Reasons: Option 3 is the preferred choice of the design team. To be confident of the projected rising roll the preferred option is 3a, which, whilst slightly more expensive, allows us to be certain we are not building for unfilled spaces and in addition allows us to profile the spending across the whole capital programme more effectively . This option also provides best value for money. The cost estimates indicate that the preferred scheme, which will deliver the identified accommodation requirements, is the most cost effective solution. Accurate cost estimates will be developed during the detailed design stage and presented for approval at Gateway 1 stage, prior to the tendering process.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Background

2.1The School Organisation Plan 2011-16 highlighted that in some areas of Medway pressure on pupil places was expected; initially in Key Stage 1.The specific problem areas were the Chatham and Gillingham West areas. 2.2 We cannot predict with any certainty whether the birth rates will continue to rise, level out or fall in the coming years. However, 2010/11 had the highest birth numbers on record across Medway. In Gillingham the past four years have been the highest on record and the trend overall is increasing. These children will filter into reception classes over the next four years.

2.3Saxon Way Primary School is currently a 1FE primary school, enjoys a larger than average site, and is close to the major developments at Grange Farm and Victory Pier, as well as a number of smaller schemes. Expanding Saxon Way to a 2FE Primary school would be in accordance with Medway’s preferred primary school size. From a geographical and capacity aspect, Saxon Way would be a good solution.

2.4Unfortunately, Ofsted placed the school into Special Measures in May 2012, which usually would not fit with the policy of good schools expanding. However an interim head teacher and an Interim Executive Board are in place to drive standards forward and a recent monitoring inspection by Ofsted in December 2012 highlighted that the school is making reasonable progress.

2.5Colleagues from School Improvement do not think in this case that Saxon Way should be dismissed from considerations as improvement in standards is evident, and expansion could help the school’s progress and viability.

2.6Saxon Way is also at the early stages of the process to convert to academy status under the sponsorship of a successful Academy Trust, a move that has been brokered by the LA and which is subject to Secretary of State’s (SoS) approval. It is expected that conversion will have taken place before September 2014 when the first additional places will be required. This in itself does not need to affect the expansion; the LA are the commissioner of places and as this is a basic need expansion the funding responsibility falls to the council. The council would however, need the cooperation of the sponsor in any expansion project. The sponsor has confirmed that they would be supportive of an expansion at the school.

2.7Considering all of the above factors and implications for expanding Saxon Way, an underperforming school, it remains officers preferred option. Permanent expansion at this school is likely to require funding of £3-4m, but could be phased in line with demand, as the school would expand from reception upwards one year at a time, and could initially make use of temporary accommodation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Outline Business Case: Saxon Way Primary School: Expansion to Two Forms of EntryReport 343 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
RC
Councillor Rodney Chambers, OBE (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
PH
Councillor Peter Hicks (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
KT
Councillor Kelly Tolhurst (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
RC
Robin CooperOfficer, in attendance
SG
Stephanie GoadOfficer, in attendance

All 18 on the meeting page

On this subject at Medway

Search all
  1. Outline Business Case: Saxon Way Primary School - Expansion to Two Forms of EntryThis decision
  2. Outline Business Case for the Expansion of Will Adams Pupil Referral UnitApproved
  3. Gateway 1 Procurement Commencement and Outline Business Case: Refurbishment and Remodelling Works at Chatham Primary Free SchoolApproved
  4. Outline Business Case for Wainscott Primary School ExpansionApproved
  5. Outline Business Case for Brompton AcademyAgreed
  6. Bishop of rochester academy outline business caseApproved

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies