The Cabinet noted the spending forecasts summarised at Table 1 in the report . The Cabinet noted the virements outlined at paragraph 4.2.5 of the report . The Cabinet noted the increase to the total Academies programme, reflecting the final ringfenced grant figure following changes to the assumptions in the gateway 3 reports . The Cabinet noted the additions to the capital programme made under delegated powers as outlined in paragraphs 4.2.3 and 4.3.3 of the report . Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1The approved capital programme for 2013/14 and future years is £76.8m, being £41.6m in respect of brought forward schemes and £35.2.m in respect of new approvals.
2.2This report consolidates the capital monitoring undertaken by each directorate as summarised in the appendices.
3. Progress
3.1Table 1 below summarises the current overall expenditure and the forecast position against the capital programme, representing a summary of the detailed information at Appendix 1. Appendices 2 to 5 show the position by directorate. Table 1: Summary – capital spend and forecasts
Forecast spend
Forecast spend in later years Programme
March 2013 Approved
Spend to
Forecast Variance 2013-14 Directorate
£’000 £’000 £’000 £’000 £’000 Business Support 34,150 28,528 2,798 2,697 (127) Department Children and 155,611 123,865 22,460 9,341 55 Adult Services Regeneration, Community and 91,746 52,914 26,614 12,218 0 Culture Member Priorities 1,332 707 618 1 (6) TOTAL 282,839 206,014 52,490 24,257 (78)
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
Scheme progressing on time and within budget Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget.
Table 2 summarises the projects progress. Full detail is shown in the appendices:
Table 2: Project Progress Summary
Progress Monitoring Total Schemes BSD 9 1 0 10 Children & Adults 36 16 0 52 RCC 38 5 0 43 Member Priorities 18 1 0 19 Total 101 23 0 124 4. Specific Scheme Monitoring Issues and Completions 81% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support (Appendix 2)
4.1.1 Council has currently agreed one addition to the Business Support Department’s capital programme for 2013-2014 and beyond, an increase of £1.591m in respect of the ‘Thin Client’ project. To this has been added £4.03 million rolled forward from the 2012/13 programme, giving the directorate a total capital programme of £5.62 million this year.
4.1.2 The directorate forecast reflects the planned phasing of expenditure and forecasts a roll forward of £2.8m into future years. There are no areas of concern to report.
4.2Children and Adults (Appendix 3)
4.2.1 Since the 2013/14 capital programme was agreed by Council, the directorate’s final 2012/13 carry forward has been confirmed at £19.0 million. The 2013/14 grant settlement was also confirmed comprising the following:
Condition Programme - £3.0 million; Basic Need - £5.0 million, covering 2013/14 and 2014/15; Adult Social Care - £537,000; Schools Devolved Formula Capital - £532,000.
4.2.2 The agreed capital programme also included £1.3 million of new developer contributions to supplement the Basic Need Grant.
4.2.3 Since Council agreed the capital programme the following additions have been made, under delegated powers, being fully funded from external sources;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.