Resolved
137/2013 The Cabinet approved the commencement of the procurement process at Gateway 1 on the basis set out in paragraph 3.10 of the report, for progression to Gateway 2 of the procurement process and invite tenders for the building works .
Cabinet approved this item on Tuesday 6 August 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
137/2013 The Cabinet approved the commencement of the procurement process at Gateway 1 on the basis set out in paragraph 3.10 of the report, for progression to Gateway 2 of the procurement process and invite tenders for the building works .
CABINET 6 AUGUST 2013 GATEWAY 1 PROCUREMENT COMMENCEMENT: GREENVALE SCHOOL REFURBISHMENT PHASE 3 Portfolio Holder: Councillor Mike O’Brien, Lead Portfolio Holder - Children’s Services
Report from: Barbara Peacock, Director of Children and Adults Services
Author: Laura Johnstone, Capital Projects Officer Sarah Woods, Interim Programme Manager Children & Adults Susan Goss, Category Specialist, Place & Projects Summary
This report seeks permission to commence the procurement of a new build extension for the entrance and administration and a review of the existing accommodation to allow for two extra classrooms.
This Gateway 1 report has been approved for submission to the Procurement Board review and discussion at Children’s and Adult’s Directorate Management Team meeting on 9 July 2013.
The Children and Adults Directorate Management Team had previously recommended that this procurement project be approved as a Category B Medium Risk procurement project at Procurement Gateway 1 by the Procurement Board. Subsequently, Procurement Board on 23 July 2013 recommended that this procurement project be approved as a Category B High Risk procurement project at Procurement Gateway 1 by the Cabinet.
Approval is requested to downgrade the procurement to medium risk to enable us to maintain the outline programme. This will ensure the construction works are commenced in early 2014 and are completed in June 2014, enabling the school are able to move in and prepare for the new term in September 2014. Following the delays to completion of the phase 1 – nursery works which was delayed into the September term, this is imperative, as it would minimise the impact of the project works on the teaching staff. 1. Budget and Policy Framework
1.1Service Background Information
1.1.1 This project supports the Council’s School Organisation Plan 2011 – 2016, approved by Cabinet on 12 June 2012 (decision number 85/2012), which highlights the need for more pupil places in Chatham. The Council has a statutory duty to ensure there are sufficient school places as set out in the Education & Inspections Act 2006.
1.2Council’s Strategic Priorities And Core Values
1.2.1 The procurement of this requirement directly links into the following Council Strategic Priorities and Core Values:
Core Values
Putting our customers at the centre of everything we do.
This procurement requirement will deliver against the Core Value of ‘Putting our customers at the centre of everything we do’ through the delivery of suitable accommodation for the expansion of Greenvale Primary School.
Giving value for money
This procurement requirement will deliver against the Core Value of ‘Giving value for money’ through the use of a separate procurement via tender with local contractors. The competitive nature of recent tenders has shown good value for money, when compared with the refurbishment rates offered via the National Framework.
Strategic Priorities
Children and young people having the best start in life in Medway.
This procurement requirement will deliver against the Strategic Priority of ‘Children and young people having the best start in life in Medway’ through the delivery of investment in Medway School buildings to provide 21st Century accommodation in order to achieve and succeed in learning.
1.3Strategic Council Obligations
1.3.1 The procurement of this requirement directly links into the following Strategic Council Obligations: The Council has a statutory duty to ensure there are sufficient school places available. The Council also has a duty to promote high standards and secure sufficient school places and ensure the sustainability of its schools throughout Medway (Education Act 2006 and 2011). Medway Council Plan
This procurement requirement links into the Medway Council Plan by supporting the Council priority to give children and young people the best start in life.
1.4Departmental and Directorate Service Plans
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Gateway 1 Procurement Commencement: Greenvale Infant School Phase 3Report | 289 KB | DownloadRead as text |
Follow Cabinet at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... | Approved | Open |
| 22 Sep 2026 | Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... | Approved | Open |
| 22 Sep 2026 | Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... | Noted | Open |
| 22 Sep 2026 | Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... | Noted | Open |
| 22 Sep 2026 | Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.